Residential/Commercial Solar Photovoltaic (PV) and Solar Water Heater Permit in Bisbee, Arizona

Required for installation of photovoltaic solar systems, solar hot water heaters, and other similar solar-energy-conversion devices in Bisbee. The City's codified ordinance grants a fee exemption for the solar-device-specific portion of these permits, though the City's separately published Fee Schedule lists specific dollar figures for these categories — an unresolved discrepancy documented below. Properties within the Old Bisbee Historic District have a dedicated Administrative Approval Checklist for Solar Devices.

Verified 2026-07-06 · Source

When you need this permit

  • Solar PV, solar hot water heater, and similar solar-energy-conversion devices require a building/electrical permit via the City's unified Building Permit Application
  • Per City Code Section 7.1.3, the City is prohibited from charging any fee for the portion of any building permit, plan review, or inspection services associated with installing a photovoltaic solar device, solar hot water heater, or similar solar-energy-conversion device that reduces global warming emissions — this exemption does NOT extend to skylights, windows, other daylighting means, or passive solar building design
  • Properties within the Old Bisbee Historic District (HP Overlay Zone) must use the City's Administrative Approval Checklist for Solar Devices in the Historic District, allowing qualifying solar installations to be approved administratively (by the Building Official/DRB Liaison) without a full Design Review Board hearing
  • 12-volt battery charging systems require no permit fee ('No Charge' per the Fee Schedule)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Photovoltaic Solar Device — ResidentialCity of Bisbee Fee Schedule (Effective 05/07/2020, Updated 06/15/2026). NOTE: this published dollar figure appears to conflict with City Code Section 7.1.3's codified exemption stating the City 'shall not charge any fee' for the solar-device portion of such permits — both sources are cited here; the discrepancy was not independently resolved and should be confirmed directly with the Building Inspector's office before assuming either source controls.
$325.00 (itemized on the Fee Schedule as $175.00 permit fee + $150.00 plan review)
Photovoltaic Solar Device — CommercialCity of Bisbee Fee Schedule. Same fee-exemption-vs-fee-schedule discrepancy noted above applies.
$375.00 (itemized on the Fee Schedule as $225.00 permit fee + $150.00 plan review)
Solar Hot Water Heater or similar solar device (excluding passive solar)City of Bisbee Fee Schedule. Same fee-exemption-vs-fee-schedule discrepancy noted above applies; passive solar heating/cooling building design is explicitly excluded from any solar fee category since it isn't a discrete 'device' permit.
$75.00
12 Volt Battery Charging SystemsCity of Bisbee Fee Schedule.
No Charge

Review timeline

Plan review
Not published — contact the department

How long did your Residential/Commercial Solar Photovoltaic (PV) and Solar Water Heater Permit permit actually take in Bisbee?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing, per 2017 NEC as amended

  2. 2

    Final

    Panel mounting, roof penetration sealing, electrical connections, and interconnection point verified

See the full Bisbee inspection guide — scheduling & re-inspection fees →

Tips

  • There is a real, documented conflict between Bisbee's codified fee exemption for solar devices (City Code Section 7.1.3, which states no fee shall be charged for the solar-specific portion of the permit/plan-review/inspection) and its published Fee Schedule's itemized $325/$375/$75 solar fee lines. This file cites both rather than picking one — verify directly with the Building Inspector (520-432-6000) which actually applies at time of application.
  • Historic District properties can often use the Administrative Approval Checklist for Solar Devices to bypass a full DRB hearing, significantly shortening the historic-district approval step (though the underlying building/electrical permit process is unaffected).
  • As of July 2026, the City of Bisbee does not appear to publish permit-specific plan review turnaround times for solar permits on its public website. There is no verifiable online source for this — call the Building Inspector's office directly at 520-432-6000.

Frequently asked questions

Properties in the Old Bisbee Historic District can use the City's dedicated Administrative Approval Checklist for Solar Devices, which allows the Building Official/DRB Liaison to approve qualifying installations without a full Design Review Board hearing.

This is unclear from the City's own published materials: City Code Section 7.1.3 states the City may not charge any fee for the solar-device-specific portion of a building permit, plan review, or inspection, but the City's separately published Fee Schedule lists a $325 fee (itemized as $175 permit + $150 plan review) for residential PV. Confirm directly with the Building Inspector's office (520-432-6000) before applying.

Bisbee does not publish a plan-review timeline for this permit. Contact City of Bisbee Community Development Department — Building Safety / Building Inspector at 520-432-6000 for current turnaround.

You'll need: Building Permit Application (Bisbee, Fillable). Depending on your project, Bisbee may also ask for: Administrative Approval Checklist for Solar Devices in the Historic District. See the required-documents checklist on this page for details on each.

Bisbee requires 2 inspection(s) for a residential/commercial solar photovoltaic (pv) and solar water heater permit, in order: Rough Electrical, Final. Schedule each through City of Bisbee Community Development Department — Building Safety / Building Inspector (520-432-6000).

Apply through City of Bisbee Community Development Department — Building Safety / Building Inspector at 118 Arizona Street, Bisbee, AZ 85603. Phone: 520-432-6000, email: jward@bisbeeaz.gov. Office hours: Monday - Friday. Applications are submitted using the City's own single-page Building Permit application (covering building, sign, and solar permits alike) either in person at 118 Arizona Street or through the City's CloudPermit online e-permitting portal; permits within the Old Bisbee Historic District (HP Overlay Zone) additionally require Design Review Board approval before a building permit may be issued.. Official information: https://web.archive.org/web/20251028012416/https://www.bisbeeaz.gov/2545/30202/Building-Permits-Code-Enforcement.

Bisbee, Arizona has adopted: Arizona has no statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Bisbee is a home-rule city that independently codifies and administers its own construction codes through its Community Development Department / Building Inspector (Building Codes page, bisbeeaz.gov/2449/Building-Codes; City of Bisbee City Code, Chapter 7, Updated 05/22/2024).; 2018 International Building Code (IBC), including all tables and appendices (Appendices C, E, F, G adopted; A, B, D, H, I, J, K, L, M not adopted), adopted by reference with City of Bisbee amendments (City Code Article 7.1, Section 7.1.1, Updated 05/22/2024).; 2018 International Existing Building Code (IEBC), adopted by reference with City amendments; existing buildings undergoing repair, alteration, addition, or change of occupancy are permitted to comply with the IEBC in lieu of full IBC compliance (City Code Article 7.1, Section 7.1.1.B(1) and 7.1.1.C).; 2018 International Residential Code (IRC), adopted by reference with City of Bisbee amendments (City Code Article 7.1, Section 7.1.1.D).; 2018 International Plumbing Code (IPC), adopted by reference with City amendments, including Appendix B (adopted at a 3 inch/hour rainfall rate) and Appendices C, D, F as informational resources; Appendix A not adopted (City Code Article 7.2).; 2017 National Electrical Code (NEC), adopted by reference with City of Bisbee amendments (City Code Article 7.3, Section 7.3.1) — one edition behind the 2018 ICC set, consistent with typical AZ municipal practice.; 2018 International Fire Code (IFC), adopted by reference with City amendments; administered with references to the Bisbee Fire Department (City Code Article 7.4).; 2018 International Mechanical Code (IMC), adopted by reference with City amendments; Appendix A adopted, Appendix B not adopted (City Code Article 7.5).; 2018 International Property Maintenance Code (IPMC), adopted by reference with City amendments, including a fence/barrier height amendment raising all referenced heights from 48 inches to 60 inches (City Code Article 7.6).; 2018 International Fuel Gas Code (IFGC) and 2018 International Energy Conservation Code (IECC), adopted by reference with City amendments; City of Bisbee is designated Climate Zone 2 or stricter for all IECC purposes (City Code Article 7.7, Sections 7.7.1-7.7.3).; Arizonans with Disabilities Act standards (A.R.S. Title 41, Chapter 9, Article 8) and implementing rules, including the ADA Accessibility Guidelines for Buildings and Facilities (Resolution R-96-46), adopted as an amendment applying to new construction and alterations of public entities (City Code Article 7.1, Section 7.1.4).; Manufactured home installation is permitted via a dedicated Manufactured Home Installation Permit (flat fee $350.00 per the City Fee Schedule); construction/installation standards for the home itself are regulated by the State of Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing, consistent with statewide practice (A.R.S. Title 41-4001 et seq.).. Local amendments apply — see the Bisbee overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bisbee building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.