Residential/Commercial Solar Photovoltaic (PV) and Solar Water Heater Permit — Bisbee, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.bisbeeaz.gov/DocumentCenter/View/7341/City-Fee-Schedule-Updated-020724
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential/Commercial Solar Photovoltaic (PV) and Solar Water Heater Permit in Bisbee, Arizona
Required for installation of photovoltaic solar systems, solar hot water heaters, and other similar solar-energy-conversion devices in Bisbee. The City's codified ordinance grants a fee exemption for the solar-device-specific portion of these permits, though the City's separately published Fee Schedule lists specific dollar figures for these categories — an unresolved discrepancy documented below. Properties within the Old Bisbee Historic District have a dedicated Administrative Approval Checklist for Solar Devices.
Verified 2026-07-06 · Source
When you need this permit
- Solar PV, solar hot water heater, and similar solar-energy-conversion devices require a building/electrical permit via the City's unified Building Permit Application
- Per City Code Section 7.1.3, the City is prohibited from charging any fee for the portion of any building permit, plan review, or inspection services associated with installing a photovoltaic solar device, solar hot water heater, or similar solar-energy-conversion device that reduces global warming emissions — this exemption does NOT extend to skylights, windows, other daylighting means, or passive solar building design
- Properties within the Old Bisbee Historic District (HP Overlay Zone) must use the City's Administrative Approval Checklist for Solar Devices in the Historic District, allowing qualifying solar installations to be approved administratively (by the Building Official/DRB Liaison) without a full Design Review Board hearing
- 12-volt battery charging systems require no permit fee ('No Charge' per the Fee Schedule)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing, per 2017 NEC as amended
- 2
Final
Panel mounting, roof penetration sealing, electrical connections, and interconnection point verified
See the full Bisbee inspection guide — scheduling & re-inspection fees →
Tips
- There is a real, documented conflict between Bisbee's codified fee exemption for solar devices (City Code Section 7.1.3, which states no fee shall be charged for the solar-specific portion of the permit/plan-review/inspection) and its published Fee Schedule's itemized $325/$375/$75 solar fee lines. This file cites both rather than picking one — verify directly with the Building Inspector (520-432-6000) which actually applies at time of application.
- Historic District properties can often use the Administrative Approval Checklist for Solar Devices to bypass a full DRB hearing, significantly shortening the historic-district approval step (though the underlying building/electrical permit process is unaffected).
- As of July 2026, the City of Bisbee does not appear to publish permit-specific plan review turnaround times for solar permits on its public website. There is no verifiable online source for this — call the Building Inspector's office directly at 520-432-6000.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bisbee building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bisbee
Residential/Commercial Solar Photovoltaic (PV) and Solar Water Heater Permit in other cities
Look up this fee in a different city →
Now live
Build your Bisbee project checklist
Describe your project once and get every permit, document, and fee it triggers in Bisbee — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →