Inspection sequence, scheduling, and re-inspection fees for building permits in Bisbee, Arizona.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
118 Arizona Street, Bisbee, AZ 85603
Phone
520-432-6000
Office hours
Monday - Friday. Applications are submitted using the City's own single-page Building Permit application (covering building, sign, and solar permits alike) either in person at 118 Arizona Street or through the City's CloudPermit online e-permitting portal; permits within the Old Bisbee Historic District (HP Overlay Zone) additionally require Design Review Board approval before a building permit may be issued.

Inspection sequence

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Underground Rough-In

    Underground fire sprinkler supply piping inspected before backfill, where applicable (bundled into the $150 Fire Sprinkler Systems fee per the Fee Schedule's 'to include underground and above ground inspections' note)

  2. 2

    Above-Ground Rough-In / Trim

    Above-ground sprinkler piping, heads, and alarm system devices/wiring inspected before concealment

  3. 3

    Final Acceptance Test

    Sprinkler system flow/hydrostatic test and/or fire alarm functional test, verifying the system notifies the Bisbee Fire Department on activation per the amended IFC Section 903.2 monitoring requirement

Applies to: Plumbing Permit

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, tracer wire, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    Fixtures connected and verified for compliance with Bisbee's water-conservation flow-rate standards; water heater connections checked

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation/Footing

    Required before concrete pour for additions

  2. 2

    Framing

    Structural connections to the existing structure

  3. 3

    Final

    Completed work verified against approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing

    Structural framing and connections per 2018 IRC and City of Bisbee amendments (including upgraded 5/8-inch Type X gypsum board garage separation where applicable)

  3. 3

    Final

    All work complete per approved plans; permit includes one initial inspection and up to two re-inspections per stage at no extra charge (additional re-inspections billed at $47.00 per City Code Section 7.1.3)

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before walls are closed

  2. 2

    Final / Utility Clearance (Green Tag)

    Devices installed and verified per 2017 NEC as amended; Utility Clearance Inspection required for utility company meter release

Applies to: Manufactured Home Installation Permit

  1. 1

    Foundation/Tie-Down

    Verifies foundation and tie-down compliance before final placement

  2. 2

    Utility Clearance Inspection (Green Tag)

    Utility connections verified before utility company service release; separate $55 flat fee applies

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and equipment placement before walls closed

  2. 2

    Final

    Equipment operational, clearances and combustion air verified per 2018 IMC as amended

Applies to: Residential/Commercial Solar Photovoltaic (PV) and Solar Water Heater Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing, per 2017 NEC as amended

  2. 2

    Final

    Panel mounting, roof penetration sealing, electrical connections, and interconnection point verified

Bisbee building permits

Get alerts for Bisbee

We'll email you when Bisbee's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.