Bisbee building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Bisbee, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 118 Arizona Street, Bisbee, AZ 85603
- Phone
- 520-432-6000
- jward@bisbeeaz.gov
- Office hours
- Monday - Friday. Applications are submitted using the City's own single-page Building Permit application (covering building, sign, and solar permits alike) either in person at 118 Arizona Street or through the City's CloudPermit online e-permitting portal; permits within the Old Bisbee Historic District (HP Overlay Zone) additionally require Design Review Board approval before a building permit may be issued.
- Website
- Official site
Inspection sequence
Applies to: Fire Sprinkler & Fire Alarm System Permit
- 1
Underground Rough-In
Underground fire sprinkler supply piping inspected before backfill, where applicable (bundled into the $150 Fire Sprinkler Systems fee per the Fee Schedule's 'to include underground and above ground inspections' note)
- 2
Above-Ground Rough-In / Trim
Above-ground sprinkler piping, heads, and alarm system devices/wiring inspected before concealment
- 3
Final Acceptance Test
Sprinkler system flow/hydrostatic test and/or fire alarm functional test, verifying the system notifies the Bisbee Fire Department on activation per the amended IFC Section 903.2 monitoring requirement
Applies to: Plumbing Permit
- 1
Underground/Slab
Before concrete pour — verify pipe slope, materials, tracer wire, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
Fixtures connected and verified for compliance with Bisbee's water-conservation flow-rate standards; water heater connections checked
Applies to: Residential Addition / Remodel Permit
- 1
Foundation/Footing
Required before concrete pour for additions
- 2
Framing
Structural connections to the existing structure
- 3
Final
Completed work verified against approved plans
Applies to: Residential Building Permit (New Construction)
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing and connections per 2018 IRC and City of Bisbee amendments (including upgraded 5/8-inch Type X gypsum board garage separation where applicable)
- 3
Final
All work complete per approved plans; permit includes one initial inspection and up to two re-inspections per stage at no extra charge (additional re-inspections billed at $47.00 per City Code Section 7.1.3)
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final / Utility Clearance (Green Tag)
Devices installed and verified per 2017 NEC as amended; Utility Clearance Inspection required for utility company meter release
Applies to: Manufactured Home Installation Permit
- 1
Foundation/Tie-Down
Verifies foundation and tie-down compliance before final placement
- 2
Utility Clearance Inspection (Green Tag)
Utility connections verified before utility company service release; separate $55 flat fee applies
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and equipment placement before walls closed
- 2
Final
Equipment operational, clearances and combustion air verified per 2018 IMC as amended
Applies to: Residential/Commercial Solar Photovoltaic (PV) and Solar Water Heater Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing, per 2017 NEC as amended
- 2
Final
Panel mounting, roof penetration sealing, electrical connections, and interconnection point verified
Final inspection only: Certificate of Occupancy / Change of Use, Demolition Permit, EV Charger / EVSE Installation Permit, Sign Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bisbee building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Bisbee building permits
Get alerts for Bisbee
We'll email you when Bisbee's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.