Residential Over-the-Counter (OTC) Permit — Electrical / Mechanical / Plumbing / Building — Camp Verde, Arizona · Requirements sheet
Verified 2026-08-16 · Source: https://www.campverde.az.gov/departments/community_development/permits.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Over-the-Counter (OTC) Permit — Electrical / Mechanical / Plumbing / Building in Camp Verde, Arizona
For minor residential building, electrical, mechanical, or plumbing projects (e.g., electrical service upgrades, yard gas lines, water heater installations) in the Town of Camp Verde, issued on a fast-track, minimal-plan-review basis relative to standard building permits.
Verified 2026-08-16 · Source
When you need this permit
- Available for minor residential building, electrical, mechanical, or plumbing projects such as electrical service upgrades, yard gas lines, and hot water heater installations
- Governed by the 2023 NEC, 2024 IPC, 2024 IMC, and 2024 IFGC as adopted by the Town of Camp Verde (Ordinance 2026-A512, effective 02-26-2026)
- Combo permits (any combination of electrical/mechanical/plumbing/building OTC scopes) are available under a single application
- Apply via the GovWell One-Stop Permitting Portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Where applicable to the scope (electrical, plumbing, or mechanical rough-in) before covering
- 2
Final
Devices/fixtures installed and operational, verified per adopted code; up to 2 inspections included in the Combo OTC fee
See the full Camp Verde inspection guide — scheduling & re-inspection fees →
Tips
- Both the Town's general permits page ('Over the Counter - 0-3 business days') and the Building Division's detailed process flow chart ('Residential Over-the-Counter and Demo Applications 0-3 Business Days') agree on this timeframe — it is a doubly-confirmed, verified figure.
- A Combo OTC permit bundling multiple trades (e.g., a water heater replacement needing both plumbing and electrical) is more economical than separate single-trade OTC permits: $90 flat plus $30 per additional trade, versus $90 each.
- OTC permits carry a smaller non-refundable retention on cancellation ($25 or 25%, whichever is greater) compared to standard building permits ($50 or 25%).
- New for FY2026-27: the adopted schedule adds a parallel 'Commercial Over the Counter Permits' block immediately below the residential one, listing Electrical, Mechanical, Plumbing and Building at the same $90 each, annotated in the change column 'We are seeking to allow for OTC permits for commercial in addition to residential.' Until FY2026-27 the OTC track was residential-only. The Town has not published a commercial Combo line, so confirm with the Building Division whether the $90 + $30-per-added-trade Combo structure extends to commercial work.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-16.
Fee schedules
Applications & forms
Online permit portal
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Camp Verde building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Camp Verde's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Camp Verde yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Camp Verde lands. Privacy.
Other permits in Camp Verde
Look up this fee in a different city →
Now live
Build your Camp Verde project checklist
Describe your project once and get every permit, document, and fee it triggers in Camp Verde — in one checklist. Free, for any city and any number of projects.