Commercial Building Permit (New Construction and Tenant Improvement) in Bullhead City, Arizona
Required for new commercial and multi-family construction, additions, and tenant-improvement/build-out work in Bullhead City. The City publishes a single combined 'Commercial and Multi-Family' submittal handout (effective 07/01/2026) covering both scenarios, and the standard Permit Application form itself has a dedicated 'Tenant' field alongside the property-owner fields — no separate tenant-improvement permit product, handout, or fee line item was found anywhere in the City's published materials, so tenant-improvement work is treated as folded into this same general commercial building permit process rather than a distinct permit type. Reviewed against the 2018 IBC as adopted by the City (BHCMC Chapter 15.12) plus Planning & Zoning site/parking/landscape/screening requirements.
Verified 2026-07-29 · Source
When you need this permit
- Building permit required for new commercial/multi-family construction, additions, and tenant-improvement/build-out work within Bullhead City limits; reviewed against the 2018 IBC as adopted by the City (BHCMC Chapter 15.12, effective 07/01/2024)
- One completed Permit Application worksheet; two copies of an 8.5"x11" site plan; three complete sets of full-size (minimum 24"x36") plans, per the Commercial and Multi-Family Handout's 'General Requirements for Plan Submittal'
- Structural calculations (two copies) required for areas of unconventional construction, or as required by the Arizona State Board of Technical Registration — the Handout specifically flags commercial/multi-family buildings over two stories, over 3,000 sq ft, intended for occupancy by more than twenty persons, or with spans over 20 feet not achieved by trusses as requiring an Arizona-licensed registrant's seal
- Building plans must show ADA accessibility (parking, signage, accessible route, ramp, entrance, restrooms, etc.) per the Handout's 'Building Plans' section
- Planning & Zoning Plan Check List (Commercial and/or Multiple Family Plan Review) applies in parallel: parking calculations/surfacing/dimensions, landscaping calculations and plant list, screening for outside storage/loading/trash enclosures, signage compliance, and — for parcels zoned C1/C2/C3 within 150 ft of a major/minor arterial street — supplemental exterior building-material standards (at least 33% of visible wall area within that zone must be masonry, stucco, or brick)
- General Contractor must provide an Arizona State Contractor's License Number, Arizona Transaction Privilege Tax (TPT) Number, and City of Bullhead City Business License Number on the Permit Application; for projects valued at $50,000.00 or more, the contractor must also provide an Arizona Department of Revenue Bond Exemption Certificate or a One-Time Bond Exemption Contractor
- Owner-Builder applicants must complete a separate 'Declaration of Intent' form Owner-builder
- Prior to City permit issuance, the applicant is responsible for obtaining all required non-City agency approvals applicable to the project scope (Bullhead City Fire Department plan review, Mohave County Development Services, Mohave County Environmental Health Department, ADOT, utility providers, etc.), per the Handout's 'Outside Agency Approvals' section and the City's separate 'Outside Agency Approvals' form
- A separate Flood Plain Development Permit is required if the lot is in a FEMA-designated flood zone; separate permits are also required for related work such as signs, fences/screening devices, and driveway/right-of-way approaches
- Subject to the City's A.R.S. § 9-835 review timeframe: the Handout's 'General Information' section directs applicants to the City's 'Building and Zoning Permits' timeline guide, i.e. the same 15-working-day Administrative Completeness Review followed by a 45-working-day Substantive Review (60 working days combined) applied to all City building permits — no separate or expedited commercial-specific timeline was found
- A soil-treatment report from an Arizona-licensed pest control agency, for prevention of termite infestation, is required prior to issuance of a Certificate of Occupancy
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing, connections, and shear-transfer details per approved structural plans
- 3
Rough Electrical/Plumbing/Mechanical
Wiring, piping, and ductwork before wall closure
- 4
Planning / Engineering / Fire Final Sign-Offs
Required departmental approvals (parking/landscaping/screening compliance, drainage, fire-protection systems) feeding into the Building Division's final sign-off
- 5
Final / Certificate of Occupancy
All work complete per approved plans; ADA accessibility features, utility connections, and life-safety systems verified before occupancy
See the full Bullhead City inspection guide — scheduling & re-inspection fees →
Tips
- Bullhead City's Building Valuation Rates (Section A3.40.021.01) are organized by 2006 IBC occupancy group (A-1 through U) and construction type (IA-VB), each with its own per-square-foot dollar rate — the applicable rate for a specific project depends on its occupancy classification and construction type as determined by the Building Official, not a single flat commercial rate.
- There is no separate 'Tenant Improvement Permit' in Bullhead City's published fee schedule or handout library — the Permit Application form's built-in 'Tenant' field and the single combined 'Commercial and Multi-Family' Handout indicate TI/build-out work is processed as the same commercial building permit product as new construction, using the same graduated Valuation Fee table.
- Plan Review Fee for commercial/industrial/multi-family work is numerically the same 65% of the building permit fee used for single-family residential (Section A3.40.021.04), except for standard/repeat plans (75% first submittal, 50% each additional) and medical marijuana facilities (90%, Section A3.40.021.05).
- Contractors on projects valued at $50,000 or more must provide an Arizona Department of Revenue Bond Exemption Certificate (or One-Time Bond Exemption) in addition to the standard AZ Contractor's License, TPT, and City Business License numbers. Contractor
- No specific commercial building permit review-timeline figure distinct from the general A.R.S. § 9-835 process was published; the Commercial and Multi-Family Handout explicitly points applicants back to the same 'Building and Zoning Permits Guide' used for all other permit types.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bullhead City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Bullhead City.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Bullhead City
Commercial Building Permit (New Construction and Tenant Improvement) in other cities
Compare commercial building permit (new construction and tenant improvement) fees across Arizona →