Commercial Building Permit (New Construction / Addition) — Apache Junction, Arizona · Requirements sheet
Verified 2026-07-29 · Source: https://www.apachejunctionaz.gov/DocumentCenter/View/21705/New-Commercial-Guide-6320
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction / Addition) in Apache Junction, Arizona
Required for new commercial buildings (including new commercial shell buildings and new multi-family construction of three or more units) and for additions to existing commercial buildings in Apache Junction, per the City's 'New/Addition Commercial Construction Building Application Guide' (rev. 6/15/2020). Reviewed against the 2018 IBC and other codes adopted by the City. Tenant improvement build-out, interior/exterior remodels, change of use, roof replacement, and related scopes are NOT folded into this permit — the City runs those through a distinctly different guide with its own required-materials checklist and its own valuation-based fee lines (10% and 25% of valuation, versus 1.20% here), confirmed by the City's own published fee table and application guides; see the companion 'commercial-tenant-improvement-permit' entry for that separate process.
Verified 2026-07-29 · Source
When you need this permit
- Building permit required for a new commercial building, a new commercial shell building, new multi-family construction of 3 or more units, or an addition to an existing commercial building
- All applications must be submitted electronically through the MyGovernmentOnline (MGO) system; a public kiosk with a USB-drive workflow is available at 300 E. Superstition Blvd. Building D for applicants needing accommodation
- Construction Plans (combined into a single PDF, ARCH 'C' 18x24, ARCH 'D' 24x36, or ARCH 'E' 36x48 format, natively CAD-generated and flattened to a single layer) must include a title sheet, scaled site plan, floor plans, exterior elevations, building cross sections, roof plan, roof/truss framing, structural plans, detail sheets, mechanical/plumbing/electrical plans, and building energy-efficiency compliance information
- The guide's own title-sheet requirement lists applicable codes as: 2018 IBC, 2015 IFC, 2010 ADA, 2018 IMC, 2018 IPC, 2018 IFGC, 2018 IECC, and 2017 NEC — note this guide text cites '2015 IFC' while the City's separately published 'Currently Adopted Building Codes' notice states the 2018 IFC is currently adopted; this discrepancy between the two City-published documents is reported here rather than silently resolved
- Soils report (by a geotechnical firm), truss manufacturer engineering/layout (required at submittal for truss roof systems), and structural calculations (by a registered design professional) are required as additional documentation unless a DBS staff member excludes them in writing
- Acknowledgement Form is required for all applications
- Construction hours are limited to 5:00 a.m.-6:30 p.m. Monday-Friday (April 15-Oct 15) and 6:00 a.m.-6:00 p.m. Monday-Friday (Oct 16-April 14); 7:00 a.m.-5:00 p.m. on weekends/City holidays year-round, and this restriction must be stated on the plan title sheet
- A permit application expires 120 days after the date of last city-initiated contact/plan review/request for information (longer than the 90-day residential expiration); an issued commercial building permit expires if an inspection is not passed within every 180 days of issuance (longer than the 120-day residential interval)
- Payment of fees is due within 2 business days of city acceptance of the application, or the application is rejected
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Apache Junction inspection guide — scheduling & re-inspection fees →
Tips
- Per the City's New/Addition Commercial Construction Building Application Guide (rev. 6/15/2020), allow a minimum of 3 to 4 weeks (15-20 business days) for the first plan-check and 1 to 2 weeks (5-10 business days) for all subsequent reviews — the same timeline language published for residential review.
- Construction plans are reviewed concurrently by both the Building Safety and Inspection Division and the Planning Division; comments from both are released together via the MGO portal.
- A commercial building permit application expires 120 days from the last city-initiated contact (versus 90 days for residential); an issued commercial permit expires if an inspection is not passed every 180 days (versus 120 days for residential).
- New commercial construction is billed as 'Shell Only' at 80% of total valuation; the remaining tenant space build-out is billed separately, and at a higher percentage of valuation (25%), as a 'Tenant Improvement/Shell Buildout' permit under the City's separate Commercial Remodel/Misc. Construction process — see the 'commercial-tenant-improvement-permit' entry.
- Certificate of Occupancy fees for new commercial construction ($100) and Certificate of Completion for a commercial shell ($80) are billed separately from the building permit fee itself — see the 'change-of-use-permit' entry, which documents the City's Occupancy fee table.
- Separate agency approvals may be required: Superstition Mountains Communities Facility District No. 1 (480-941-6754) for sewer availability/connection, Superstition Fire and Medical District (480-982-4440) for fire sprinkler/alarm plan review, and Pinal County Aquifer Protection Division (520-866-6442) for septic permitting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Apache Junction building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Apache Junction.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Apache Junction
Commercial Building Permit (New Construction / Addition) in other cities
Compare commercial building permit (new construction / addition) fees across Arizona →
Look up this fee in a different city →