Change of Use / Change of Occupancy Permit — Apache Junction, Arizona · Requirements sheet
Verified 2026-07-23 · Source: https://apachejunctionaz.gov/DocumentCenter/View/19881/2020-Development-Services-Fee-Table
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Change of Occupancy Permit in Apache Junction, Arizona
Required whenever a commercial building or tenant space's use or occupancy classification changes in Apache Junction — even without any construction or remodeling work — under Apache Junction City Code § 7-1-6(A) and § 7-1-8. Administered by the Division of Building Safety and Inspection using the City's own 'Change of Use' explanation and checklist guidance documents; a compliant change of use results in a new Certificate of Occupancy for the building or space.
Verified 2026-07-23 · Source
When you need this permit
- A Change of Use/Occupancy application and a new Certificate of Occupancy are required whenever a commercial building or tenant space's use or occupancy classification changes — even if no construction or remodeling work is proposed — per Apache Junction City Code § 7-1-6(A) (permit required to 'change the occupancy of a building or structure') and § 7-1-8 (no change in occupancy classification without a Certificate of Occupancy)
- Apache Junction classifies commercial buildings/spaces into the same 10 IBC Occupancy Groups (Assembly 'A', Business 'B', Educational 'E', Factory/Industrial 'F', High Hazard 'H', Institutional 'I', Mercantile 'M', Residential 'R', Storage 'S', Utility/Miscellaneous 'U', several with numbered subgroups); a use change that shifts a building into a different classification can trigger new code-compliance requirements (e.g., fire sprinklers) that the existing building or space must be verified to meet before a new Certificate of Occupancy is issued
- Required submittal per the City's Change of Use or Occupancy Checklist (rev. 8/28/2019): a site plan (building/space location, parking, accessible route, address/suite number, current zoning, property owner's name/address) and an architectural plan showing current/existing and proposed occupancy group and occupancy load, building construction type, fire sprinkler and fire alarm data, existing and proposed floor plans, exiting/egress details (number, travel distance, exit signage, emergency lighting, locks/latching), restroom configuration, and adjacent uses if in a multi-tenant location
- For buildings predating Apache Junction's 1985 incorporation and code adoption, the City will honor an existing (Pinal County-era) use if it can be established that the use has been continuous and the building has been maintained in a safe condition since 1985
- Failure to obtain a new Certificate of Occupancy before changing use is a City Code violation and can result in an order to close or cease use of the structure plus fines
- Apply through the City of Apache Junction Building Division, electronically via MyGovernmentOnline (MGO), consistent with other City building permit types
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Occupancy Inspection
Verifies the building/space meets the currently adopted code for the new occupancy classification before a new Certificate of Occupancy is issued
See the full Apache Junction inspection guide — scheduling & re-inspection fees →
Tips
- A Change of Use/Occupancy permit is required even when NO construction work is proposed — simply changing a tenant's business type (e.g., retail 'M' occupancy to a restaurant 'A-2' occupancy) can change which code requirements apply, and may require building upgrades (such as fire sprinklers) before a new Certificate of Occupancy can be issued.
- The City will honor a pre-1985 use established under Pinal County jurisdiction (before Apache Junction incorporated and adopted its own building codes) if the use has been continuous and the building kept in a safe condition since 1985.
- Fee depends on scenario: $150 for a pure Change of Occupancy with no proposed work, versus $100 (new commercial) or $80 (tenant improvement/commercial shell) for a standard Certificate of Occupancy tied to a construction permit, or $200 for a Temporary Certificate of Occupancy (max 30 days, up to 2 renewals).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Apache Junction building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Apache Junction
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Arizona →
Look up this fee in a different city →