Change of Use (via Commercial Building Permit) -- No Distinct Certificate of Occupancy Product in Eagar, Arizona

Covers a change in use of an existing commercial building or space in the Town of Eagar (e.g., converting a retail space to a restaurant). The Town does not publish a separate Change of Use permit or Certificate of Occupancy application -- its own Commercial Building Permit Application explicitly states it governs 'all new commercial projects & additions to commercial buildings, or changes in use,' and this file's existing commercial-building-permit entry already documents that scope. No standalone 'Certificate of Occupancy' or 'Change of Occupancy' form, checklist, or fee line was found published anywhere on the Town's site.

Verified 2026-07-23 · Source

When you need this permit

  • A change in use of an existing commercial building or space is processed through the Town's Commercial Building Permit Application -- confirmed directly in the source PDF text: 'ALL NEW COMMERCIAL PROJECTS & ADDITIONS TO COMMERCIAL BUILDINGS, OR CHANGES IN USE WHICH EQUAL 3000 SQ. FT. OR MORE, MUST HAVE A STAMP ON THE PLANS FROM AN ARIZONA CERTIFIED PROFESSIONAL DESIGNER'
  • Changes in use equal to 3,000 sq ft or more require a stamp on the plans from an Arizona-certified/registered design professional, the same threshold already documented on this file's commercial-building-permit entry
  • Two plot plans and two sets of plans/specifications required, per the same Commercial Building Permit requirements already documented elsewhere in this file
  • All commercial projects, including changes in use, must be approved by the Town's Design Review Board
  • No distinct final 'Certificate of Occupancy' document or fee was found published -- the Commercial Building Permit's own Final inspection (already documented in this file's commercial-building-permit entry) is the last step described in the Town's own materials

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan reviewEagar’s published plan-review target
10–10 business days

How long did your Change of Use (via Commercial Building Permit) -- No Distinct Certificate of Occupancy Product permit actually take in Eagar?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    All work and conditions associated with the change of use complete per approved plans -- same Final inspection step already documented on this file's commercial-building-permit entry; no separate occupancy-specific inspection was found published

See the full Eagar inspection guide — scheduling & re-inspection fees →

Tips

  • Eagar has no distinct 'Change of Use Permit' or 'Certificate of Occupancy' product -- a change in the use of an existing commercial building or space is processed through the same Commercial Building Permit Application already documented elsewhere in this file, confirmed directly against the source PDF's own scope statement.
  • The 3,000 sq ft design-professional-stamp threshold applies to changes in use exactly as it applies to new commercial construction and additions -- this is stated as a single combined rule on the application form, not a separate change-of-use-specific rule.
  • No dedicated fee line, checklist, or timeline distinct from the standard Commercial Building Permit was found for a change of use -- the same town-wide fee-schedule gap already documented elsewhere in this file applies here as well.
  • Applicants converting an existing commercial space to a new use should still confirm parking, zoning-district use-table compliance, and Design Review Board scope with Community Development (928-333-4128 ext. 222) before submitting, since these are administered under Title 18 zoning provisions that sit alongside, not inside, the Commercial Building Permit application itself.

Frequently asked questions

Eagar requires a change of use (via commercial building permit) -- no distinct certificate of occupancy product for: A change in use of an existing commercial building or space is processed through the Town's Commercial Building Permit Application -- confirmed directly in the source PDF text: 'ALL NEW COMMERCIAL PROJECTS & ADDITIONS TO COMMERCIAL BUILDINGS, OR CHANGES IN USE WHICH EQUAL 3000 SQ. FT. OR MORE, MUST HAVE A STAMP ON THE PLANS FROM AN ARIZONA CERTIFIED PROFESSIONAL DESIGNER'; Changes in use equal to 3,000 sq ft or more require a stamp on the plans from an Arizona-certified/registered design professional, the same threshold already documented on this file's commercial-building-permit entry; Two plot plans and two sets of plans/specifications required, per the same Commercial Building Permit requirements already documented elsewhere in this file; All commercial projects, including changes in use, must be approved by the Town's Design Review Board; No distinct final 'Certificate of Occupancy' document or fee was found published -- the Commercial Building Permit's own Final inspection (already documented in this file's commercial-building-permit entry) is the last step described in the Town's own materials. If your project isn't listed, confirm with Town of Eagar Community Development Department — Building Department at 928-333-4128 ext. 222 (Community Development); ext. 230 or ext. 228 (Building Department inspection requests) before starting work.

Eagar's published plan-review target for a change of use (via commercial building permit) -- no distinct certificate of occupancy product is 10–10 business days.

You'll need: Commercial Building Permit Application. See the required-documents checklist on this page for details on each.

Eagar requires 1 inspection(s) for a change of use (via commercial building permit) -- no distinct certificate of occupancy product, in order: Final. Schedule each through Town of Eagar Community Development Department — Building Department (928-333-4128 ext. 222 (Community Development); ext. 230 or ext. 228 (Building Department inspection requests)).

Apply through Town of Eagar Community Development Department — Building Department at 22 W. 2nd St., PO Box 1300, Eagar, AZ 85925. Phone: 928-333-4128 ext. 222 (Community Development); ext. 230 or ext. 228 (Building Department inspection requests), email: No published department email address found as of this review; contact via phone at 928-333-4128 ext. 222 (Community Development) or submit a request via the Town's 'Submit a Request or Concern' web form.. Office hours: Community Development Department: 7:00 a.m. - 5:30 p.m., Monday through Thursday (Town of Eagar operates a 4-day, 10-hour workweek). Building Department inspection requests are taken 8:00 a.m. - 4:00 p.m. Monday-Thursday or 8:00 a.m. - 12:00 p.m. Fridays, per the Town's own permit application forms, and should be made at least 24 hours in advance.. Official information: https://www.eagaraz.gov/o/tofe/page/building.

Eagar, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The Town of Eagar runs its own Community Development / Building Department and independently adopts and administers its own construction codes; it does NOT defer building permitting to Apache County or to the neighboring Town of Springerville. Source: Town of Eagar Building page (eagaraz.gov/o/tofe/page/building) and the Town's own published Building, Commercial, Electrical, Plumbing, Mechanical, and Demolition Permit Application forms, each captioned 'Return this application... to the Building Department.'; 2018 International Residential Code (IRC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page (eagaraz.gov/o/tofe/page/building): 'Adopted Building Codes – 2018 IRC, IBC, IPC, IMC, IPMC, IFC and 2011 NEC.'; 2018 International Building Code (IBC), as adopted by the Town of Eagar for commercial/non-residential construction. Source: Town of Eagar Building Design Specifications page.; 2018 International Plumbing Code (IPC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.; 2018 International Mechanical Code (IMC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.; 2018 International Property Maintenance Code (IPMC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.; 2018 International Fire Code (IFC), as adopted by the Town of Eagar as its uniform fire code. Source: Town of Eagar Building Design Specifications page. (Fire/EMS response in the Round Valley — Eagar and Springerville jointly — is provided by the Round Valley Fire & Medical Department, a genuinely joint public-safety service; this is distinct from building-code adoption and permitting, which each town administers separately.); 2011 National Electrical Code (NEC), as adopted by the Town of Eagar (electrical code cycle predates the 2018 ICC set). Source: Town of Eagar Building Design Specifications page.; Note on code-text access: the Town's Code of Ordinances (Title 15, Buildings and Construction) is hosted on Municode Library (library.municode.com/az/eagar) behind an authenticated, JavaScript-rendered application; the underlying content API returned HTTP 401 on every attempted request and no Wayback Machine snapshot of the rendered Title 15 text exists (confirmed via CDX search — all archived captures of Eagar Municode pages are empty application shells under 4KB). The specific code edition years above are instead sourced directly from the Town's own Building Design Specifications page, which is a primary, town-published, non-mirror source.. Local amendments apply — see the Eagar overview page for the full list.

No. The Town of Eagar's own Commercial Building Permit Application explicitly states it covers new commercial projects, additions, and changes in use -- there is no distinct Certificate of Occupancy or Change of Use permit, application, or fee. A change of use is submitted and reviewed the same way as any other commercial building permit, with approval normally given within 10 working days.

Yes, if the space involved is 3,000 sq ft or more -- the Town's Commercial Building Permit Application states this stamp requirement applies to new commercial projects, additions, AND changes in use of that size, as a single combined rule.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.