Inspection sequence, scheduling, and re-inspection fees for building permits in Eagar, Arizona.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
22 W. 2nd St., PO Box 1300, Eagar, AZ 85925
Phone
928-333-4128 ext. 222 (Community Development); ext. 230 or ext. 228 (Building Department inspection requests)
Office hours
Community Development Department: 7:00 a.m. - 5:30 p.m., Monday through Thursday (Town of Eagar operates a 4-day, 10-hour workweek). Building Department inspection requests are taken 8:00 a.m. - 4:00 p.m. Monday-Thursday or 8:00 a.m. - 12:00 p.m. Fridays, per the Town's own permit application forms, and should be made at least 24 hours in advance.

Published scheduling rules

  • Request all inspections at least 24 hours in advance by calling the Building Department at 928-333-4128 ext. 230 or ext. 228, providing permit number, applicant name, type of inspection, and job location. (Residential Building Permit)
  • Request inspections at least 24 hours in advance via the Building Department at 928-333-4128 ext. 230 or ext. 228. (Residential Electrical Permit)
  • Request inspections at least 24 hours in advance via the Building Department at 928-333-4128 ext. 230 or ext. 228. (Plumbing Permit)
  • Request inspections at least 24 hours in advance via the Building Department at 928-333-4128 ext. 230 or ext. 228. (Mechanical Permit)
  • Request inspections at least 24 hours in advance via the Building Department at 928-333-4128 ext. 230 or ext. 228; permits expire 360 days after issuance. (Solar PV Permit (via Building + Electrical Permits))

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footings or Foundation

    Before laying any concrete; requires clearly marked property lines and setbacks

  2. 2

    Underground Plumbing

    Before covering

  3. 3

    Concrete Slab or Under-Floor

    Before laying concrete or plywood deck

  4. 4

    Shear Bracing

    Before covering

  5. 5

    Rough Framing, Electrical, Plumbing and Mechanical

    Combined rough-in inspection

  6. 6

    Gypsum Nailing

    Before taping/finishing

  7. 7

    Final

    All work complete per approved plans

Applies to: Residential Building Permit

  1. 1

    Footings or Foundation

    Before laying any concrete; footings/foundations are only approved when clearly and accurately marked property lines and setbacks are provided

  2. 2

    Underground Plumbing

    Before covering

  3. 3

    Concrete Slab or Under-Floor

    Before laying concrete or floor deck

  4. 4

    Shear Wall Nailing

    Before covering shear-braced walls

  5. 5

    Rough Framing, Electrical, Plumbing and Mechanical

    Combined rough-in inspection for framing and all trades

  6. 6

    Gypsum Nailing

    Before taping/finishing

  7. 7

    Final

    All work complete per approved plans

Applies to: EV Charger / EVSE Permit (via Residential Electrical Permit)

  1. 1

    Rough Electrical

    Wiring and box placement before walls closed (if applicable)

  2. 2

    Final

    Charger circuit/unit installed and system energized per 2011 NEC as adopted by the Town

Applies to: Mechanical Permit

  1. 1

    Rough-In

    Equipment placement and connections before enclosure (per the standard Town trade-permit inspection sequence used for electrical/plumbing)

  2. 2

    Final

    Equipment operational and connections verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Vent and water tests

  2. 2

    Final

    Fixtures connected, no leaks

Applies to: Residential Electrical Permit

  1. 1

    Rough Electrical

    Wiring and box placement before walls closed

  2. 2

    Final

    Devices installed and system energized per 2011 NEC as adopted by the Town

Applies to: Solar PV Permit (via Building + Electrical Permits)

  1. 1

    Rough Electrical

    Wiring and box placement before walls closed / before energizing

  2. 2

    Final

    Panel mounting, racking attachment, and electrical connections verified; system energized per 2011 NEC as adopted by the Town

Eagar building permits

Get alerts for Eagar

We'll email you when Eagar's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.