Required for the placement of a permanent commercial or business sign in the Town of Eagar, whether mounted on a building or freestanding in a yard. Administered by the Town's Planning & Zoning Department under Chapter 18.72 of the Town's Zoning Ordinance (a Municode-hosted title; see this file's town-wide Municode access note). Temporary banners are not approved as a permanent sign and may only be used for a short period for occasions approved by the Planning and Zoning Administrator.

Verified 2026-07-23 · Source

When you need this permit

  • Sign Permit required before placing a sign on a building or in a yard within Eagar town limits, per Chapter 18.72 of the Town's Zoning Ordinance
  • Physical address and parcel number of the sign location required on the application
  • Sketch showing size, height, and shape of the sign required
  • Description of materials used and method of mounting required
  • Proposed location that the sign(s) will be placed on the building or in the yard required
  • Application is reviewed and signed off by the Town's Zoning Administrator, not the Building Official
  • Banners are not approved as a permanent sign; temporary banner use is limited to short-period occasions approved by the Planning and Zoning Administrator

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Sign Permit filing feeThe Town's own Application for Sign Permit form has a blank 'FILING FEE' line filled in per-application by staff rather than a printed dollar amount; confirmed by rendering the source PDF to PNG and reading it visually (no fee figure appears anywhere on the one-page form). This is the same town-wide gap already documented on this file's other permit-type entries -- the Town's linked Fee Schedule (under Departments > Finance) is flagged 'draft' in the site's own navigation and its underlying S3 document returns AccessDenied on every fetch attempt (re-confirmed this session). No fee figure is invented here.
Not published — contact the department

Review timeline

Plan reviewEagar’s published plan-review target
10–10 business days

How long did your Sign Permit permit actually take in Eagar?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verifies the installed sign matches the approved sketch, materials, mounting, and location (no separately itemized multi-stage inspection sequence was published for this permit type, consistent with a single-page administrative sign-review process)

See the full Eagar inspection guide — scheduling & re-inspection fees →

Tips

  • Sign Permits in Eagar are reviewed by the Planning & Zoning Administrator, not the Building Department -- a different reviewing official than the Town's building/electrical/plumbing/mechanical permits.
  • Per the application form: 'Ten days are required for plan review and approval of application' -- this is a flat 10-day figure with no stated 15-day escalation-letter clause (unlike the Town's building/electrical/plumbing forms).
  • Banners are explicitly NOT approved as a permanent sign under this permit; they may only be used briefly for occasions approved by the Planning and Zoning Administrator.
  • No dedicated sign-permit fee amount is published -- as with the rest of this file's fee data, the Town's Fee Schedule link is flagged 'draft' and its underlying document returns AccessDenied. Contact the Building/Community Development Department, 928-333-4128 ext. 222, for a current quote.
  • The application form directs applicants to Chapter 18.72 of the Town's Zoning Ordinance (Title 18) for the substantive sign standards (size/height/placement limits); that title is hosted on Municode behind the same JS-rendered, authentication-gated interface documented elsewhere in this file for Title 15, and no Wayback snapshot of its rendered text exists.

Frequently asked questions

Eagar requires a sign permit for: Sign Permit required before placing a sign on a building or in a yard within Eagar town limits, per Chapter 18.72 of the Town's Zoning Ordinance; Physical address and parcel number of the sign location required on the application; Sketch showing size, height, and shape of the sign required; Description of materials used and method of mounting required; Proposed location that the sign(s) will be placed on the building or in the yard required; Application is reviewed and signed off by the Town's Zoning Administrator, not the Building Official; Banners are not approved as a permanent sign; temporary banner use is limited to short-period occasions approved by the Planning and Zoning Administrator. If your project isn't listed, confirm with Town of Eagar Community Development Department — Building Department at 928-333-4128 ext. 222 (Community Development); ext. 230 or ext. 228 (Building Department inspection requests) before starting work.

Eagar's published plan-review target for a sign permit is 10–10 business days.

You'll need: Application for Sign Permit. See the required-documents checklist on this page for details on each.

Eagar requires 1 inspection(s) for a sign permit, in order: Final. Schedule each through Town of Eagar Community Development Department — Building Department (928-333-4128 ext. 222 (Community Development); ext. 230 or ext. 228 (Building Department inspection requests)).

Apply through Town of Eagar Community Development Department — Building Department at 22 W. 2nd St., PO Box 1300, Eagar, AZ 85925. Phone: 928-333-4128 ext. 222 (Community Development); ext. 230 or ext. 228 (Building Department inspection requests), email: No published department email address found as of this review; contact via phone at 928-333-4128 ext. 222 (Community Development) or submit a request via the Town's 'Submit a Request or Concern' web form.. Office hours: Community Development Department: 7:00 a.m. - 5:30 p.m., Monday through Thursday (Town of Eagar operates a 4-day, 10-hour workweek). Building Department inspection requests are taken 8:00 a.m. - 4:00 p.m. Monday-Thursday or 8:00 a.m. - 12:00 p.m. Fridays, per the Town's own permit application forms, and should be made at least 24 hours in advance.. Official information: https://www.eagaraz.gov/o/tofe/page/building.

Eagar, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The Town of Eagar runs its own Community Development / Building Department and independently adopts and administers its own construction codes; it does NOT defer building permitting to Apache County or to the neighboring Town of Springerville. Source: Town of Eagar Building page (eagaraz.gov/o/tofe/page/building) and the Town's own published Building, Commercial, Electrical, Plumbing, Mechanical, and Demolition Permit Application forms, each captioned 'Return this application... to the Building Department.'; 2018 International Residential Code (IRC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page (eagaraz.gov/o/tofe/page/building): 'Adopted Building Codes – 2018 IRC, IBC, IPC, IMC, IPMC, IFC and 2011 NEC.'; 2018 International Building Code (IBC), as adopted by the Town of Eagar for commercial/non-residential construction. Source: Town of Eagar Building Design Specifications page.; 2018 International Plumbing Code (IPC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.; 2018 International Mechanical Code (IMC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.; 2018 International Property Maintenance Code (IPMC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.; 2018 International Fire Code (IFC), as adopted by the Town of Eagar as its uniform fire code. Source: Town of Eagar Building Design Specifications page. (Fire/EMS response in the Round Valley — Eagar and Springerville jointly — is provided by the Round Valley Fire & Medical Department, a genuinely joint public-safety service; this is distinct from building-code adoption and permitting, which each town administers separately.); 2011 National Electrical Code (NEC), as adopted by the Town of Eagar (electrical code cycle predates the 2018 ICC set). Source: Town of Eagar Building Design Specifications page.; Note on code-text access: the Town's Code of Ordinances (Title 15, Buildings and Construction) is hosted on Municode Library (library.municode.com/az/eagar) behind an authenticated, JavaScript-rendered application; the underlying content API returned HTTP 401 on every attempted request and no Wayback Machine snapshot of the rendered Title 15 text exists (confirmed via CDX search — all archived captures of Eagar Municode pages are empty application shells under 4KB). The specific code edition years above are instead sourced directly from the Town's own Building Design Specifications page, which is a primary, town-published, non-mirror source.. Local amendments apply — see the Eagar overview page for the full list.

Yes. A Sign Permit from the Town's Planning & Zoning Department is required before installing a sign on a building or in a yard, per Chapter 18.72 of the Town's Zoning Ordinance. The Town's own application states plan review and approval normally takes ten days.

Only briefly. The Town's Sign Permit application states banners will not be approved as a permanent sign, and may only be used for a short period of time for occasions approved by the Planning and Zoning Administrator.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.