EV Charger / EVSE Permit in Bullhead City, Arizona

Installation of an electric vehicle charger (EVSE) at a Bullhead City property is electrical work processed under the standard Electrical Permit — the City's itemized, Uniform Administrative Code-style Comprehensive Fee Schedule (FY2025-2026) has no distinct EV-charger/EVSE line item. A residential EVSE circuit installation is billed as a standard Electrical Permit Issuance plus applicable per-item fees (e.g., a new circuit/outlet or a service upgrade, depending on installation type).

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for hard-wired electrical work, per BHCMC Chapter 15.20 (2017 NEC as adopted by the City)
  • Minor repairs, lamp replacement, and plugging into an approved permanently-installed receptacle are exempt from a permit — a dedicated EVSE circuit does not qualify for this exemption
  • Apply via Permit Application submitted in person or by mail to the Building Division at City Hall
  • No EV-charger-specific application form or fee category was found published separately from the general Electrical Permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Issuance, each permitCity of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.021.06 — base issuance fee applicable to any electrical permit, including an EVSE circuit
$26.48
Service, 600 volts or less, not over 200 amperes (if a new/upgraded service is required)Applies if the EVSE installation requires a new or upgraded electrical service
$34.38 each
Power apparatus (motors/generators/transformers), by size (possible applicable category for EVSE equipment)The fee schedule has no dedicated EVSE line; this UAC-style category is the closest fit for charging equipment if not billed as a simple circuit/outlet
$5.37-$83.98 each depending on size tier

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Bullhead City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In / Final Electrical

    Circuit wiring, breaker sizing, and EVSE connection verified

See the full Bullhead City inspection guide — scheduling & re-inspection fees →

Tips

  • Bullhead City's fee schedule is itemized down to individual outlets, services, and apparatus by size (a Uniform Administrative Code style), but has no EV-charger-specific line — expect the base $26.48 Electrical Permit Issuance fee plus whichever itemized category the inspector determines applies (circuit/outlet, service upgrade, or power apparatus).
  • Confirm with the Building Division which itemized fee category will be applied to your specific EVSE installation before applying, since the schedule does not name EV chargers directly.

Frequently asked questions

Bullhead City requires an ev charger / evse permit for: Electrical permit required for hard-wired electrical work, per BHCMC Chapter 15.20 (2017 NEC as adopted by the City); Minor repairs, lamp replacement, and plugging into an approved permanently-installed receptacle are exempt from a permit — a dedicated EVSE circuit does not qualify for this exemption; Apply via Permit Application submitted in person or by mail to the Building Division at City Hall; No EV-charger-specific application form or fee category was found published separately from the general Electrical Permit. If your project isn't listed, confirm with City of Bullhead City Development Services Department — Building Division at 928-763-0124 before starting work.

In Bullhead City, the published Electrical Permit Issuance, each permit is: $26.48. Additional published fees: Service, 600 volts or less, not over 200 amperes (if a new/upgraded service is required) — $34.38 each; Power apparatus (motors/generators/transformers), by size (possible applicable category for EVSE equipment) — $5.37-$83.98 each depending on size tier. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Bullhead City does not publish a plan-review timeline for this permit. Contact City of Bullhead City Development Services Department — Building Division at 928-763-0124 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Bullhead City requires 1 inspection(s) for an ev charger / evse permit, in order: Rough-In / Final Electrical. Schedule each through City of Bullhead City Development Services Department — Building Division (928-763-0124).

Apply through City of Bullhead City Development Services Department — Building Division at 2355 Trane Road, Bullhead City, AZ 86442. Phone: 928-763-0124, email: schooniyom@bullheadcityaz.gov. Office hours: City Hall, 2355 Trane Road, Bullhead City, AZ 86442. Building Division main line 928-763-0124 (fax 928-763-0131); Inspection Requests line 928-763-0172. Development Services Director/Building Official: Saritti "Billy" Chooniyom, CBO (schooniyom@bullheadcityaz.gov). Sr. Plan Review/Administrative Manager: Wendy Lewis (wlewis@bullheadcityaz.gov). Manufactured-home permitting contact: dking@bullheadcityaz.gov. Permit Application Packets are submitted in person or by mail to the Building Division/Planning & Zoning Division at City Hall. Source: City of Bullhead City Building and Renovating page and 2025 AZBO Directory.. Official information: https://www.bullheadcityaz.gov/business-development/building-and-renovating/.

Bullhead City, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9, §§ 9-831 through 9-840). The City of Bullhead City runs its own Development Services Department / Building Division and independently adopts and administers its own construction codes; it does not defer permitting to Mohave County. Source: City of Bullhead City 'Adopted Building Codes' notice (effective 07/01/2026) and 'Work Exempt From Permits' handout (effective 07/01/2024).; 2018 International Building Code (IBC), as published by the International Code Council, adopted with local amendments (Bullhead City Municipal Code (BHCMC) Chapter 15.12). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Residential Code (IRC), for one- and two-family dwellings and associated accessory structures, adopted with local amendments (BHCMC Chapter 15.14). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026; City of Bullhead City 2018 IRC Design Criteria sheet, effective 07/01/2024.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted with local amendments (BHCMC Chapter 15.20) — one edition behind the 2018 ICC code set. Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026. The City Council approved adoption of the 2018-cycle ICC codes and 2017 NEC on 04/16/2024, effective for applications beginning 07/01/2024. Source: Mohave Daily News, 'Bullhead City moves toward updating building codes.'; 2018 International Mechanical Code (IMC), adopted with local amendments (BHCMC Chapter 15.28). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Plumbing Code (IPC), adopted with local amendments (BHCMC Chapter 15.32). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Fuel Gas Code (IFGC), adopted with local amendments (BHCMC Chapter 15.34). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Energy Conservation Code (IECC), adopted with local amendments (BHCMC Chapter 15.22). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Existing Building Code (IEBC), adopted with local amendments (BHCMC Chapter 15.26). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted with local amendments (BHCMC Chapter 15.30). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Fire Code (IFC) is referenced by the City for demolition/fire-safety provisions, but fire code administration in Bullhead City is handled by the Arizona Department of Fire, Building and Life Safety, which has separately adopted the 2024 International Fire Code; contact the Bullhead City Fire Department at (928) 758-3971 / planreview@bullheadfire.org for fire plan review. Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2010 ADA Standards for Accessible Design (ADAAG Manual, US Access Board) adopted, no local BHCMC chapter assignment (NA). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; Manufactured homes, factory-built buildings, and park model trailers are separately regulated through the City's intergovernmental agreement with the Arizona Department of Housing (ADOH) for installation, reinspection, additional inspections and extensions (fees per the ADOH Fee Schedule, A.R.S. Title 41, Chapter 37, Article 3); the City separately issues Zoning Clearance permits for placement/siting. Source: City of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.022.07.. Local amendments apply — see the Bullhead City overview page for the full list.

No. EVSE installation is processed as a standard Electrical Permit under BHCMC Chapter 15.20. The Comprehensive Fee Schedule FY2025-2026 has no distinct EV-charger line item; a base $26.48 Electrical Permit Issuance fee applies, plus whichever itemized fee category (circuit/outlet, service, or apparatus) fits the specific installation.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bullhead City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.