Demolition Permit in Casa Grande, Arizona
Required for demolition of any residential or commercial structure in Casa Grande. Billed as a flat fee and classified under the Miscellaneous category on the City's A.R.S. § 9-835 review timeframe chart, alongside single-trade permits.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required before demolishing a residential or commercial structure within Casa Grande city limits
- Site plan required showing lot dimensions and location of the building to be demolished, plus other existing structures
- Coordination with Pinal County Air Quality Control District (asbestos/NESHAP requirements) is expected prior to demolition, consistent with Arizona state and federal asbestos abatement rules for structure demolition
- Project is not legally complete until an approved final inspection has occurred
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final
Verifies site condition and completion of demolition; the project is not legally complete without an approved final inspection
See the full Casa Grande inspection guide — scheduling & re-inspection fees →
Tips
- Demolition is classified under the Miscellaneous category on the City's A.R.S. § 9-835 review timeframe chart at 2 business days Administrative Completeness Review, plus 10 business days each for Initial and Resubmittal Substantive Review — a 24-business-day Over-All Timeframe maximum, the same track as single-trade (MPE) permits.
- The flat $100 demolition permit fee is one of the lowest-cost permit types on the City's schedule, but asbestos/air-quality clearance requirements (governed by Pinal County / ADEQ, not the City) should be arranged before applying, as with any Arizona jurisdiction.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casa Grande building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Casa Grande
Demolition Permit in other cities
Compare demolition permit fees across Arizona →
Look up this fee in a different city →