Demolition Permit in Casa Grande, Arizona

Required for demolition of any residential or commercial structure in Casa Grande. Billed as a flat fee and classified under the Miscellaneous category on the City's A.R.S. § 9-835 review timeframe chart, alongside single-trade permits.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required before demolishing a residential or commercial structure within Casa Grande city limits
  • Site plan required showing lot dimensions and location of the building to be demolished, plus other existing structures
  • Coordination with Pinal County Air Quality Control District (asbestos/NESHAP requirements) is expected prior to demolition, consistent with Arizona state and federal asbestos abatement rules for structure demolition
  • Project is not legally complete until an approved final inspection has occurred

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition PermitCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule, Building Permit Fees section (flat fee)
$100.00

Review timeline

Plan reviewCasa Grande’s published plan-review target
2–24 business days

How long did your Demolition Permit permit actually take in Casa Grande?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verifies site condition and completion of demolition; the project is not legally complete without an approved final inspection

See the full Casa Grande inspection guide — scheduling & re-inspection fees →

Tips

  • Demolition is classified under the Miscellaneous category on the City's A.R.S. § 9-835 review timeframe chart at 2 business days Administrative Completeness Review, plus 10 business days each for Initial and Resubmittal Substantive Review — a 24-business-day Over-All Timeframe maximum, the same track as single-trade (MPE) permits.
  • The flat $100 demolition permit fee is one of the lowest-cost permit types on the City's schedule, but asbestos/air-quality clearance requirements (governed by Pinal County / ADEQ, not the City) should be arranged before applying, as with any Arizona jurisdiction.

Frequently asked questions

Casa Grande requires a demolition permit for: Building permit required before demolishing a residential or commercial structure within Casa Grande city limits; Site plan required showing lot dimensions and location of the building to be demolished, plus other existing structures; Coordination with Pinal County Air Quality Control District (asbestos/NESHAP requirements) is expected prior to demolition, consistent with Arizona state and federal asbestos abatement rules for structure demolition; Project is not legally complete until an approved final inspection has occurred. If your project isn't listed, confirm with City of Casa Grande Planning & Development Department — Development Center (Building Division) at 520-421-8630 before starting work.

$100.00 flat fee, per the City of Casa Grande FY 2025-2026 Consolidated Fee Schedule.

Demolition is processed under the Miscellaneous category of the City's A.R.S. § 9-835 review timeframe chart: 2 business days for Administrative Completeness Review, plus 10 business days each for Initial and Resubmittal Substantive Review, for a 24-business-day Over-All Timeframe maximum.

You'll need: Building Permit Application (Demolition); Site Plan. See the required-documents checklist on this page for details on each.

Casa Grande requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through City of Casa Grande Planning & Development Department — Development Center (Building Division) (520-421-8630).

Apply through City of Casa Grande Planning & Development Department — Development Center (Building Division) at 510 E. Florence Boulevard, Casa Grande, AZ 85122. Phone: 520-421-8630, email: cgplanning@casagrandeaz.gov. Office hours: Monday - Friday, 7:30 a.m. - 5 p.m. The Development Center is a 'one-stop shop' for building, engineering, fire, and planning plan review/permits/inspections. Building inspections are scheduled online through the WebPermits portal (rogue.casagrandeaz.gov/WebPermits); the City does not offer same-day inspections unless the request is received by 11:59 p.m. the prior business day, and inspectors run routes between 6 a.m. and 3:30 p.m.. Official information: https://casagrandeaz.gov/231/Building.

Casa Grande, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Casa Grande runs its own Planning & Development Department / Development Center and independently adopts and administers its own construction codes under Title 15 (Buildings and Construction) of the Casa Grande Code of Ordinances; it does not defer permitting to Pinal County. Source: City of Casa Grande Building page (casagrandeaz.gov/231/Building) and Casa Grande Code of Ordinances Title 15.; 2018 International Building Code (IBC), adopted by reference with City of Casa Grande amendments (Casa Grande Code of Ordinances § 15.08.010), made a public record by Resolution No. 5170. Source: City of Casa Grande Quick Codes Design Criteria Handout (Building Department, rev. 11/8/2024) and Casa Grande Code of Ordinances § 15.08.010, International Building Code.; 2018 International Residential Code (IRC), adopted by reference with City of Casa Grande amendments under Title 15. Climatic and geographic design criteria (IRC Table R301.2(1)) are published separately by the Building Department. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Mechanical Code (IMC), adopted by reference with City of Casa Grande amendments under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Plumbing Code (IPC), adopted by reference with City of Casa Grande amendments under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Fuel Gas Code (IFGC), adopted by reference with City of Casa Grande amendments under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Fire Code (IFC), adopted by reference as the City's uniform fire code under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Energy Conservation Code (IECC) governs residential and commercial energy-efficiency requirements. Residential energy efficiency design minimums published by the Building Department include: new/replacement HVAC sized per ACCA Manual J & S (gas furnaces/boilers 80% AFUE minimum; air conditioners and heat pumps 14 SEER minimum); duct insulation per ACCA Manual D (R-8 within attics/exterior, R-6 within other portions); common insulation values of R-13 walls, R-38 ceilings, U-0.40 windows, R-0 crawlspace/slab-on-grade, R-3 water/refrigerant lines. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Property Maintenance Code (IPMC), adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2017 National Electrical Code (NEC/NFPA 70), adopted by reference with City of Casa Grande amendments (note: electrical code cycle is one edition behind the 2018 ICC set). Arc-fault and tamper-resistant outlet protection is required at most locations per the 2017 NEC. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; NFPA 99 Standards for Health Care Facilities, adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2009 ICC A117.1 Accessible and Usable Buildings and Facilities, adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2019 City of Casa Grande Building and Technical Administrative Code (CG-BTAC), made a public record by Resolution No. 5170, with a 2022 Amendment made a public record by Resolution No. 5397. This locally-authored administrative code governs permit administration, fees cross-references, and technical amendments layered on top of the adopted ICC model codes. Source: City of Casa Grande Building and Technical Administrative Code, 2019 Edition (casagrandeaz.gov/DocumentCenter, Resolution 5170) and Casa Grande Code of Ordinances § 15.04.010.. Local amendments apply — see the Casa Grande overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casa Grande building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.