Unincorporated Santa Cruz County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Santa Cruz County, Arizona.

Verified 2026-07-23 · Source

How to schedule

Inspections are requested through the building department below.

Address
2150 N. Congress Drive, Suite #206, Nogales, AZ 85621
Phone
520-375-7880
Office hours
Monday–Thursday, 7:00 AM – 6:00 PM. Due to the time required to accept or issue a building permit, no applications are accepted and no permits are issued after 5:00 PM. Source: Santa Cruz County Building Department page (live, browser-header fetch confirmed 2026-07-07) and Guidelines for Builders (Rev. 03/2014).

Inspection sequence

Applies to: Residential Building/Grading Permit (New Construction, Additions, Accessory Structures)

  1. 1

    Foundation/Footing

    Before concrete pour — after all forms, reinforcement steel, and anchor/hold-down bolts are in place; verifies footing depth, dimensions, reinforcement, and property-line setbacks per 2012 IBC/IRC

  2. 2

    Rough Frame / Rough Electrical / Rough Plumbing / Rough Mechanical

    After the building is made weather-tight (roof, windows, doors, siding/stucco lath installed) and all rough trade work is in place, before wall cover or insulation, per 2012 IBC/IRC/IMC/IPC and 2011 NEC

  3. 3

    Gas Line Pressure Test

    Required before concealing gas piping — verify no leaks under test pressure

  4. 4

    Final

    All work complete per approved plans and applicable Fire Department sign-off where required (homes 3,600 sq ft+ in Rio Rico/Tubac Fire Districts); Certificate of Occupancy issued upon passing final

Applies to: Commercial/Multi-Family Building Permit (New Construction, Tenant Improvement)

  1. 1

    Foundation/Footing

    Before concrete pour, per 2012 IBC

  2. 2

    Rough Frame / Rough Electrical / Rough Plumbing / Rough Mechanical

    After structural framing and rough trades complete, before wall cover

  3. 3

    Final

    All work complete per approved plans; TAC and Fire Department sign-off confirmed; Certificate of Occupancy issued

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In / Service Inspection

    EVSE wiring installed before concealment or energizing

  2. 2

    Final

    EVSE equipment complete and operational per adopted 2011 NEC

Applies to: Grading Permit (Standalone / Excavation and Grading)

  1. 1

    Grading / Cut-Fill Inspection

    Verify graded areas match approved grading plan depths/amounts; cross-section verified if cuts/fills exceed 5 feet

  2. 2

    Final

    Grading work complete per approved plan

Applies to: Minor Electrical, Solar, and Gas Permit

  1. 1

    Rough-In / Service Inspection

    After wiring, solar racking/panels, or gas piping installed, before concealment or energizing

  2. 2

    Final

    Work complete and operational per 2012 IPC/IMC and 2011 NEC as applicable

Applies to: Solar PV Permit

  1. 1

    Rough-In / Service Inspection

    After wiring and solar racking/panels installed, before concealment or energizing

  2. 2

    Final

    Work complete and operational per 2012 IPC/IMC and 2011 NEC as applicable

Re-inspection fees

Residential Building/Grading Permit (New Construction, Additions, Accessory Structures)After-hours inspection / re-inspection / unspecified inspection / additional plan review · Guidelines for Builders (Rev. 03/2014), Exhibit A, 'Other Inspections and Fees.'
$47.00 per hour (or the jurisdiction's actual hourly cost, whichever is greater); after-hours inspections have a 2-hour minimum charge; unspecified-fee inspections have a half-hour minimum
Grading Permit (Standalone / Excavation and Grading)After-hours inspection / re-inspection (grading-specific) · Guidelines for Builders (Rev. 03/2014), Table A-33-B, 'Other Inspections and Fees.'
$50.50 per hour (2-hour minimum for after-hours; $47.00 minimum for unspecified-fee inspections)

Unincorporated Santa Cruz County building permits

Get alerts for Unincorporated Santa Cruz County

We'll email you when Unincorporated Santa Cruz County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.