Residential Building/Grading Permit (New Construction, Additions, Accessory Structures) in Unincorporated Santa Cruz County, Arizona
Required for new single-family/two-family residential construction, additions, and accessory structures in the unincorporated areas of Santa Cruz County. Reviewed against the 2012 IBC/IRC and 2011 NEC as adopted by the County. Grading (where cut/fill exceeds 50 cubic yards) is bundled into the same permit rather than issued standalone. Applications are submitted to the Building Department (Community Development) using the County's Building/Grading Permit Application, accompanied by the Plan Submittal Check List items.
Verified 2026-07-07 · Source
When you need this permit
- Building/Grading Permit Application, including the Applicant's Certification and Acknowledgement page, fully signed
- Two complete hard-copy sets of plans (including 2 site plans), plus an electronic PDF copy emailed to permitting@santacruzcountyaz.gov
- Site plan drawn to scale (1:20, 1:30, 1:40, 1:50, or 1:60) showing property line distances/bearings, north arrow, physical address, APN, owner of record, front/rear/side setbacks, all existing and proposed structures with location/size/height, street name, driveway, utility easements, entire parcel, and area to be graded
- Landscape Acknowledgement Form (Article 19, Section 1906(A) of the County Zoning & Development Code)
- Right of Way Application for driveway access
- Approved Flood Hazard Information Sheet or issued Flood Plain Use Permit (required if parcel is in the FEMA floodplain)
- Copy of the approved septic Construction Authorization Permit (from Santa Cruz County Health/ADEQ) including the approved site plan and floor plan, OR a water/sewer letter confirming service
- Proof of ownership (Assessor's Office parcel print-out); if owner name does not match, a recorded deed copy is required
- Owner Builder Form, if applicable (owner and immediate family performing the work; any hired labor must be Arizona ROC-licensed) Owner-builderContractor
- Exterior Lighting Schedule with cut sheets (lumens/watts) for all exterior lights, per County Outdoor Lighting Regulations
- Homes 3,600 sq ft or larger (living space + garage) require Fire Department approval, but only in the Rio Rico and Tubac Fire Districts
- Contractor's Transaction Privilege Tax License Number required for projects over $50,000
- Bond exemption certificate from the Arizona Department of Revenue required for contractors when construction value exceeds $50,000
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour — after all forms, reinforcement steel, and anchor/hold-down bolts are in place; verifies footing depth, dimensions, reinforcement, and property-line setbacks per 2012 IBC/IRC
- 2
Rough Frame / Rough Electrical / Rough Plumbing / Rough Mechanical
After the building is made weather-tight (roof, windows, doors, siding/stucco lath installed) and all rough trade work is in place, before wall cover or insulation, per 2012 IBC/IRC/IMC/IPC and 2011 NEC
- 3
Gas Line Pressure Test
Required before concealing gas piping — verify no leaks under test pressure
- 4
Final
All work complete per approved plans and applicable Fire Department sign-off where required (homes 3,600 sq ft+ in Rio Rico/Tubac Fire Districts); Certificate of Occupancy issued upon passing final
See the full Unincorporated Santa Cruz County inspection guide — scheduling & re-inspection fees →
Tips
- The Applicant's Certification and Acknowledgement page (part of the Building/Grading Permit Application) spells out your exact statutory rights and deadlines under A.R.S. §11-1602 through §11-1610 — read it before submitting; it governs how the County's 15/45/105/150-business-day review clock works and what happens if you or the County miss a deadline.
- Water availability must be resolved before submittal: if there is no connection to the main water line on your property, you must sign an acknowledgment on the application taking responsibility for coordinating your own utility connection.
- Do not attempt a single combined check for multiple fee types — the County's own submittal checklist explicitly states it will not accept multiple fees combined onto a single check; pay the Plan Review Fee and Zoning Clearance Fee as separate payments.
- If your parcel needs a new address, street name, or is on an unnamed road, get routed through Planning & Zoning for address verification before applying — no permit will be issued without an approved street name/address.
- Grading is not a separate permit track here: if your project involves more than 50 cubic yards of cut/fill, the grading review and fee (2x Table A-33-B) are bundled into your building permit application, not filed separately.
- Contact the Building Department for the current-year fee table before budgeting — the valuation-based Table 1-A fee schedule identified in this review dates to a 2014 revision of the Guidelines for Builders and no newer public fee-schedule PDF for Building Department permits specifically could be located as of this review.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Santa Cruz County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Santa Cruz County
Residential Building/Grading Permit (New Construction, Additions, Accessory Structures) in other cities
Look up this fee in a different city →