Building Permit in Citrus Heights, California
Citrus Heights requires every building permit to be submitted online, shows you only the permits you are named on, and wants any oak tree on your lot or your neighbour's drawn on the plot plan.
Verified 2026-09-20 · Source
When you need this permit
- ONLINE IS NOT AN OPTION, IT IS THE RULE: "All building permits are required to be submitted and processed online using our Citizen Access Portal. This site allows you to submit a permit application with PDF attachments, pay the required fees, and request inspections."
- WHO MAY HOLD ONE: "The homeowner, their agent, and/or contractors licensed by the State of California may obtain building permits." Contractor
- THE ACCOUNT NEEDS APPROVING, NOT JUST CREATING: "once the account is created and approved (this may take a few hours) you may submit permit applications online anytime."
- THE PORTAL SHOWS YOU ONLY YOUR OWN WORK: "the Citizen Access Portal will only allow you to look up permits where you are named as a contact (property owner, contractor, etc.), you will not be able to research permits that do not involve your property or business."
- THE PLOT PLAN MUST BE DRAWN TO SCALE and show: "The shape and dimensions of the lot; Location of any oak trees on the property or adjoining properties; Any existing structures and its use; Size and location of the proposed structure and its use; The required setbacks; Location of any existing roads, any dedicated rights-of-way, or easements; The drainage flows of the property."
- A CITY BUSINESS LICENCE GATES ISSUANCE for contractors - the city states it in capitals and links its Business License Portal beside the statement.
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
Available only where the original expired through failure to commence within a year or through a year's suspension or abandonment, AND "a new permit is sought within two years after the issuance of the original permit". Show full citationHide
Available only where the original expired through failure to commence within a year or through a year's suspension or abandonment, AND "a new permit is sought within two years after the issuance of the original permit". A permit that simply reached its two-year life does not qualify.Review timeline
Inspection process
- 1
A 4 p.m. cut-off, with the overflow day being yours to choose
"Building inspection requests received by 4 p.m. on a business day can be scheduled for the next business day. Inspection requests received after 4 p.m. will be scheduled for the 2nd business day or other day of your choice." Missing the cut-off does not simply push you to the following day - the city offers the choice.
- 2
Two routes, one of which never closes
"Inspection request can be made utilizing the inspection request line (916-727-4750) or the Citizen Access Portal." The line is not staffed but always open: "Our 24-hour voice mail system allows you to schedule building inspections 24 hours a day, 7 days a week."
- 3
Six things to say on the voicemail
The city lists them: "Your name; Permit number; Address of job; Type of inspection requested; Requested date for inspection; Time preference: morning or afternoon." On a voicemail system there is no form to prompt you, so the list is the form.
- 4
AM or PM can be requested, and the schedule can still move
"Inspections can be requested for AM or PM", but "Every effort is made to accommodate each request, but sometimes the schedule will be altered according to the staff work load."
- 5
Failing an inspection means correcting and re-inspecting
"Any work or materials that are not up to code will need to be corrected and re-inspected. The inspections are for the owners and/or occupant's health and safety, as well to protect investments."
See the full Citrus Heights inspection guide — scheduling & re-inspection fees →
Tips
- GET REQUESTS IN BY 4 P.M. for the next business day; after that you pick the day.
- SHOW OAK TREES ON THE PLOT PLAN, including any on the neighbouring property.
- CONTRACTORS NEED A CITRUS HEIGHTS BUSINESS LICENCE before the permit will issue.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-20.
Online permit portal
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Citrus Heights building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Citrus Heights's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Citrus Heights yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Citrus Heights lands. Privacy.
Building Permit in other cities
Compare building permit fees across California →
Look up this fee in a different city →
Now live
Build your Citrus Heights project checklist
Describe your project once and get every permit, document, and fee it triggers in Citrus Heights — in one checklist. Free, for any city and any number of projects.
Get started →