Building Permit in Victorville, California

Victorville publishes the most usable set of local design and field values in this corpus - twelve of them, from snow load to the buried depth of a gas line - alongside a plainly numbered seven-step permit process. Applications and inspections both run through a Citizen Self Service Portal.

Verified 2026-09-19 · Source

When you need this permit

  • THE PROCESS IS PUBLISHED AS SEVEN NUMBERED STEPS: "Prepare plans for the job (according to current codes and standards); Apply for the proper permit for the job on the Self-Service Portal; Have the plans reviewed and approved by the Development Department; Pay the appropriate development fees; Await permit issuance; Construct the project according to the approved plans; Have the construction inspected and approved by the Development Department."
  • NOTE WHERE THE MONEY SITS IN THAT ORDER: fees are paid AFTER plan review and approval, not before it. Visalia, three hours north, requires plan check fees "before processing" - the same step in the opposite position, and worth checking rather than assuming.
  • APPLICATION ROUTES ARE SPLIT BY PROJECT CLASS: the city publishes separate online routes for Commercial, Residential, Planning Entitlements, and Streets & Right of Way.
  • CONSTRUCTION HOURS ARE A CODE PROVISION, NOT A COURTESY: "7:00am to 10:00pm (VMC 13.01 Noise Control)".

Required documents

Check off what you have — your progress is saved on this device.

Fee schedule

When fees fall dueStep four of the city's own seven-step process is "Pay the appropriate development fees", following "Have the plans reviewed and approved by the Development Department". The fee is not a precondition of review here.
After plan review and approval.
Fee scheduleThe city publishes a Fees & Forms section which was not opened here, so no schedule, amount or fee basis is asserted.
NOT TRANSCRIBED for this record.

Review timeline

Plan review
Not published — contact the department

How long did your Building Permit permit actually take in Victorville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Booked in the portal, with a note to the inspector

    "Inspections are scheduled online using your City's Citizen Self Service Portal." And unusually: "When scheduling, you will be able to choose your inspection date with morning or afternoon preference, as well as the ability to leave a note for the inspector." A free-text field to the person attending is rare - Fullerton captures a gate code, but only Victorville offers an open note.

  2. 2

    AM and PM windows, and a shorter Friday

    "Inspections are conducted Monday-Friday. AM time slots are between 8:00am-12:00pm. PM time slots are between 1:00pm-5:00pm (1:00pm-4:00pm Fridays)." The Friday afternoon window is an hour shorter than the rest of the week.

  3. 3

    Cancel by phone, not in the portal

    "If you need to cancel an inspection, please call the Building Division line at (760) 955-5100." Booking is online; cancelling is a telephone call.

  4. 4

    Today's inspections are published

    The city maintains a public "View Today's Inspections" page alongside the scheduling route. No data from it is reproduced in this record - it is a live view and belongs to the city.

See the full Victorville inspection guide — scheduling & re-inspection fees →

Tips

  • READ THE COMMON QUESTIONS LIST BEFORE DESIGNING - twelve local values including snow load, wind exposure and buried depths.
  • FEES COME AFTER PLAN APPROVAL HERE, not before review.
  • CANCEL AN INSPECTION BY PHONE on (760) 955-5100; booking is online but cancelling is not.

Frequently asked questions

Victorville requires a building permit for: THE PROCESS IS PUBLISHED AS SEVEN NUMBERED STEPS: "Prepare plans for the job (according to current codes and standards); Apply for the proper permit for the job on the Self-Service Portal; Have the plans reviewed and approved by the Development Department; Pay the appropriate development fees; Await permit issuance; Construct the project according to the approved plans; Have the construction inspected and approved by the Development Department."; NOTE WHERE THE MONEY SITS IN THAT ORDER: fees are paid AFTER plan review and approval, not before it. Visalia, three hours north, requires plan check fees "before processing" - the same step in the opposite position, and worth checking rather than assuming.; APPLICATION ROUTES ARE SPLIT BY PROJECT CLASS: the city publishes separate online routes for Commercial, Residential, Planning Entitlements, and Streets & Right of Way.; CONSTRUCTION HOURS ARE A CODE PROVISION, NOT A COURTESY: "7:00am to 10:00pm (VMC 13.01 Noise Control)".. If your project isn't listed, confirm with City of Victorville Development Department, Building Division at (760) 955-5100 (Building Division); (760) 955-5000 (City) before starting work.

Victorville does not publish a plan-review timeline for this permit. Contact City of Victorville Development Department, Building Division at (760) 955-5100 (Building Division); (760) 955-5000 (City) for current turnaround.

Monday to Friday, in two windows: 8:00am to 12:00pm in the morning and 1:00pm to 5:00pm in the afternoon - except Fridays, when the afternoon window ends at 4:00pm.

Apply through City of Victorville Development Department, Building Division at 14343 Civic Drive, PO Box 5001, Victorville, CA 92392. Phone: (760) 955-5100 (Building Division); (760) 955-5000 (City), email: vville@victorvilleca.gov (City). Office hours: NOT PUBLISHED on the pages read for this record. The Permit Center, Building Codes and Inspection Process pages give the process, the design criteria and the inspection windows but no counter opening times. What IS published is when inspections happen - Monday to Friday, mornings 8:00am-12:00pm and afternoons 1:00pm-5:00pm, with Friday afternoons ending an hour earlier at 4:00pm. Call (760) 955-5100 before travelling.. Official information: https://www.victorvilleca.gov/Government/City-Departments/Building/Permit-Center.

Twelve of them, as a Common Questions list: Climate Zone 14; snow load "5 lbs ground"; wind load "100-115 mph dependent on occupancy (most are 110), exposure C"; roof drain sizing at "2.5" of rainfall per hour"; seismic design category "D - can be modified with soils report; E for residential"; gas line air test "10 lbs for 15 minutes (except large systems)"; construction hours 7:00am to 10:00pm under VMC 13.01; buried depths of water pipes 1 foot, sewer pipes 2 feet, gas lines 18 inches and electrical lines 2 feet; driveway slope 12% maximum; solid patio covers at "Rolled roofing 1/4" per 1 foot minimum slope, Asphalt shingles 2:12 (or manufacturers specs)"; and patio/roof sheathing "Plywood 1/2" or T1-11 5/8" minimum".

After the plans are approved. The city's step order is prepare plans, apply, have plans reviewed and approved, then "Pay the appropriate development fees", then await issuance. Do not assume this holds elsewhere - Visalia requires plan check fees before processing begins.

Yes. The scheduling form lets you "choose your inspection date with morning or afternoon preference, as well as the ability to leave a note for the inspector."

"7:00am to 10:00pm", and it is a code provision rather than guidance - the city cites VMC 13.01 (Noise Control).

Victorville's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Victorville yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Victorville lands. Privacy.

Compare building permit fees across California

Look up this fee in a different city →