Building permit in Daly City, California
Daly City publishes an initial plan review figure, which many building departments do not: fifteen working days. Two qualifications travel with it and both matter. The clock starts "from the date of routing" rather than from submittal, and routing is never defined on the pages read. And the Building Division states plainly that review is currently taking longer than that figure.
Verified 2026-09-22 · Source
When you need this permit
- "Building Permit Application (PDF) or Re-Roofing Permit Application (PDF)"
- "Credit Card Authorization (PDF)"
- "Any other supporting documentation; e.g., electronic PDF files of your drawings/plans, calculations, etc."
- Resubmittals go by email: "Resubmittal documents should be emailed to the Building Division."
- Design to the code in force when the application is DEEMED COMPLETE: "Permit applications deemed complete before January 1, 2026, may continue to be reviewed under the codes in effect on the date the application was deemed complete."
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
No fee schedule, valuation table or deposit figure appears on the Building Division page or the Permits Involving Plans page. Show full citationHide
No fee schedule, valuation table or deposit figure appears on the Building Division page or the Permits Involving Plans page. The city does publish a "Credit Card Authorization (PDF)" among the required submittal documents, so payment is collected at submittal, but no amount is stated on the pages read.Review timeline
Inspection process
Scheduled through the city's inspection page
The Building Division page links "Schedule a Building Permit Inspection". The inspection request method, any notice period and any daily cutoff time are NOT STATED on the pages read for this record.
Tips
- Fifteen working days is three calendar weeks before any delay, and the city says there is currently delay. Plan from the caveat, not the number.
- "From the date of routing" is not "from the date you submitted". The gap between those two events is not published, so it is unbudgeted time.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-22.
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Daly City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Daly City's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Daly City yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Daly City lands. Privacy.
Building permit in other cities
Compare building permit fees across California →
Look up this fee in a different city →