Building Permit in Santa Barbara, California
Santa Barbara publishes a first-review schedule banded by project size, with worked examples for each band - and then publishes two other answers to the same question in the same document. Its expiry rule discards your submittal and forfeits your fees, with no notice.
Verified 2026-09-21 · Source
When you need this permit
- PLANNING APPROVAL COMES FIRST AND IS A SEPARATE APPLICATION: "Planning approvals must be granted before you can apply for a building permit." Those fees "are separate from the building permit fees."
- SIX DIVISIONS REVIEW SIMULTANEOUSLY, NOT IN SEQUENCE. The Land Development Team is Building & Safety, Fire, Public Works Engineering / Water Resources / Transportation, Planning, Environmental Services, and Parks & Recreation Creeks Division. "All building permit reviews are completed by all City reviewers simultaneously."
- A PAYMENT GATE SITS BETWEEN YOUR FIRST REVIEW AND YOUR RECHECK: "Other division plan check fees will be invoiced after your first review, and must be paid before rechecks can begin, with any remaining fees due before permit issuance." An unpaid invoice stops the clock and the city does not chase it.
- A RESUBMITTAL CAN RESET YOU TO THE FIRST-REVIEW CLOCK: "The City's goal is to process rechecks within 5 days. If the initial plans were considered incomplete, another first review timeline may be instituted." So an incomplete first submittal does not merely delay the recheck - it can put you back on a 5-to-28-working-day band.
- A LICENSED PROFESSIONAL IS REQUIRED ABOVE STATED THRESHOLDS: "required for projects that are greater than two residential units on a lot, or greater than two stories in height. A licensed professional is required for all structural commercial tenant improvements and any work that alters the safety of a building."
- SOME WORK NEEDS NO PERMIT AT ALL, with numbers: "one-story detached accessory structure (sheds, playhouse, etc.) not exceeding 120 square feet, fences not over 42 inches high, retaining walls not over 4 ft. in height (measured from the bottom of the footing to the top of the wall) with no surcharge." The complete list is at SBMC 22.04.
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
The structure is published even though the amounts are not, and the structure is the part that bites. Show full citationHide
The structure is published even though the amounts are not, and the structure is the part that bites. Fees are invoiced after submittal rather than paid at the counter - "City Staff will follow up electronically with an invoice for the appropriate fee amount." Other divisions' plan check fees are invoiced only AFTER the first review and must be paid before any recheck begins. Remaining fees are due before permit issuance. And on expiry "all fees forfeited".Review timeline
Inspection process
- 1
Book by 5:00 p.m. the day before
"Building inspectors will conduct an inspection on any City working day you request, provided you call or email a request for an inspection by no later than 5:00 p.m. the day before you wish the inspection to take place." The Inspection Request Line is (805) 564-5492 or Inspections@SantaBarbaraCA.gov. A cut-off TIME is a different and more useful commitment than a lead time in days, because it tells you exactly when tomorrow stops being available.
- 2
But not on every Friday
"(Building & Safety is closed every other Friday of the month.)" The guide does not say which Fridays, so a Thursday 5:00 p.m. booking for a Friday inspection needs checking against the closure calendar first.
- 3
Keep the Inspection Record Card and approved plans on site
"you must have the inspection card and the approved plans available during all inspections. PDF format of these documents is acceptable." Inspector approval is required before covering or concealing work.
- 4
A milestone inspection every 180 days or the permit expires
"Once construction begins, you must have passed at least one 'milestone inspection' approval every 180 days to avoid permit expiration." The guide names them: "foundation, rough framing or combination frame, insulation, lath/drywall, final building inspection." Ordinary progress inspections are not milestones.
- 5
Other departments may also need to sign off before final
"you must obtain approvals from all City departments listed on the Inspection Record Card before final inspection. Your job card will identify if any inspections are required from other City departments."
- 6
A Certificate of Occupancy is issued for new non-residential buildings only
"we will provide a Certificate of Occupancy for new non-residential buildings only. All other projects can obtain an Inspection Summary, available through the Accela Citizen Access Portal (ACA)." Building & Safety separately authorises "utility releases" allowing electricity and gas to be connected.
See the full Santa Barbara inspection guide — scheduling & re-inspection fees →
Tips
- PAY THE POST-FIRST-REVIEW INVOICE PROMPTLY - rechecks cannot begin until it clears.
- DIARISE SIX MONTHS. No activity and the application expires, materials are discarded and fees are forfeited, unannounced.
- A MILESTONE INSPECTION EVERY 180 DAYS keeps the permit alive; ordinary progress visits do not count.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-21.
Fee schedules
Applications & forms
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santa Barbara building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Santa Barbara's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Santa Barbara yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Santa Barbara lands. Privacy.
Building Permit in other cities
Compare building permit fees across California →
Look up this fee in a different city →
Now live
Build your Santa Barbara project checklist
Describe your project once and get every permit, document, and fee it triggers in Santa Barbara — in one checklist. Free, for any city and any number of projects.
Get started →