Building Permit in Mountain View, California

Mountain View publishes a full review-timeline table with a separate figure for every project type AND for resubmittals, and runs three application routes including a genuine same-day permit for minor residential work.

Verified 2026-09-20 · Source

When you need this permit

  • SUBMITTAL IS ELECTRONIC, WITHOUT EXCEPTION ON THE PAGES READ: "All Building and Fire Protection permits must be submitted electronically online at ePermitsMV."
  • THREE ROUTES, EACH WITH A STATED PURPOSE. Same-Day Permit: "Submit a building permit for minor projects at single-family homes/duplexes. No building plans required." Building Permit: "Submit a new building permit, resubmit, or submit a revision to an issued permit." Solar Permit: "Submit for a Solar Permit."
  • PAYMENT GATES THE START OF REVIEW, AND MAY ITSELF TAKE DAYS: "initial fee payment to process your planning, building, or public works permit may take multiple business days to process and confirm receipt. Payment must be confirmed before staff can begin review of your permit."
  • THE CLOCK STARTS AT COMPLETENESS: the published timelines are "for the initial and subsequent resubmittals for a building or fire permit after an application has been deemed complete."
  • COMMERCIAL PERMITS CARRY A STATUTORY DISABILITY-ACCESS DISCLOSURE: "AB 3002 and SB 748 require cities issuing building permits for commercial construction or issuing any business licenses to make available the following information regarding compliance with disability access provisions", pointing to the Division of the State Architect CASp inspection programme, the California Commission on Disability Access and the ADA. A "Mandatory ADA Disclosure" is published for all properties.
  • A PROFESSIONAL DESIGN LIMITATIONS page sets out where a licensed design professional is required; it was not opened for this record.

Required documents

Check off what you have — your progress is saved on this device.

Fee schedule

Permit feesA dedicated Fees page is published and was not opened, so no amount or fee basis is asserted.
NOT TRANSCRIBED for this record.
When payment matters"Payment must be confirmed before staff can begin review of your permit", and initial payment "may take multiple business days to process and confirm receipt." The published review timelines run from completeness, so the payment-confirmation period sits outside them.
Before review begins, and confirmation itself takes time.

Review timeline

Plan reviewMountain View’s published plan-review target
7–42 business days

How long did your Building Permit permit actually take in Mountain View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building inspections are booked online

    "Building inspections can be scheduled online (Click on Inspections tab)" within ePermitsMV.

  2. 2

    Fire Protection inspections are booked by telephone instead

    "Fire Protection inspections can be scheduled by calling 650-903-6313 (Extension 0)." Two disciplines, two different channels, from the same permit system.

  3. 3

    Special inspections are a separate published programme

    The city publishes a Special Inspections and Testing section with its own Special Inspection Application. Neither was opened for this record, so no requirement is quoted.

  4. 4

    NOT PUBLISHED on the pages read: notice period, daily cut-off and arrival windows

    No advance-notice requirement, request cut-off or AM/PM window appeared on the pages read for this record. A Schedule Inspections section exists on the Building and Fire Codes page and was not opened; it may carry them.

See the full Mountain View inspection guide — scheduling & re-inspection fees →

Tips

  • LOOK UP YOUR PROJECT TYPE IN THE TIMELINE TABLE - initial and resubmittal are quoted separately.
  • GET THE PAYMENT CONFIRMED EARLY; review cannot start until it is, and confirmation takes days.
  • FIRE INSPECTIONS ARE BOOKED BY PHONE, not in the portal.

Frequently asked questions

Mountain View requires a building permit for: SUBMITTAL IS ELECTRONIC, WITHOUT EXCEPTION ON THE PAGES READ: "All Building and Fire Protection permits must be submitted electronically online at ePermitsMV."; THREE ROUTES, EACH WITH A STATED PURPOSE. Same-Day Permit: "Submit a building permit for minor projects at single-family homes/duplexes. No building plans required." Building Permit: "Submit a new building permit, resubmit, or submit a revision to an issued permit." Solar Permit: "Submit for a Solar Permit."; PAYMENT GATES THE START OF REVIEW, AND MAY ITSELF TAKE DAYS: "initial fee payment to process your planning, building, or public works permit may take multiple business days to process and confirm receipt. Payment must be confirmed before staff can begin review of your permit."; THE CLOCK STARTS AT COMPLETENESS: the published timelines are "for the initial and subsequent resubmittals for a building or fire permit after an application has been deemed complete."; COMMERCIAL PERMITS CARRY A STATUTORY DISABILITY-ACCESS DISCLOSURE: "AB 3002 and SB 748 require cities issuing building permits for commercial construction or issuing any business licenses to make available the following information regarding compliance with disability access provisions", pointing to the Division of the State Architect CASp inspection programme, the California Commission on Disability Access and the ADA. A "Mandatory ADA Disclosure" is published for all properties.; A PROFESSIONAL DESIGN LIMITATIONS page sets out where a licensed design professional is required; it was not opened for this record.. If your project isn't listed, confirm with City of Mountain View Community Development Department, Building Division at 650-903-6313 (Building and Fire Protection; extension 0 to schedule a Fire Protection inspection); 650-903-6306 (Community Development); 650-903-6300 (City) before starting work.

It depends on the project, and the city publishes a figure for each. Among plan-checked building permits, initial review runs from 1 week (demolition, interior nonstructural demolition, wireless telecommunication) to 6 weeks (new multi-family, new commercial and new mixed-use buildings). A single-family new build is 4 weeks initial and 3 on resubmittal; a commercial tenant improvement is 4 and 3, or 2 and 2 on the fast track.

It depends which kind. Building inspections are scheduled online in ePermitsMV under the Inspections tab. Fire Protection inspections are scheduled by telephone on 650-903-6313, extension 0.

Apply through City of Mountain View Community Development Department, Building Division at 500 Castro St., Mountain View, CA 94041. Phone: 650-903-6313 (Building and Fire Protection; extension 0 to schedule a Fire Protection inspection); 650-903-6306 (Community Development); 650-903-6300 (City), email: building@mountainview.gov. Office hours: NOT PUBLISHED as counter hours on the pages read for this record - the Permit Center, Permit Timelines, Building and Fire Codes, Apply for Building Permits and Contact Us pages. What IS published is the shape of access rather than its hours: "In-Person assistance is available at the public counter, along with Virtual Public Counter appointments", plus a separate "Schedule Virtual Appointment with Building Staff" route. NOTE THE DOMAIN: permit content lives on its own site, developmentpermits.mountainview.gov, and www.mountainview.gov redirects into it.. Official information: https://developmentpermits.mountainview.gov/about-permits/permit-center.

The 2025 California codes, and the trigger is your submittal date: "Effective January 1, 2026, all applications submitted for Building and Fire permits will be required to comply with" the 2025 Title 24 codes "adopted by reference with local amendments". A design prepared under the 2022 codes but submitted after that date is reviewed against the 2025 ones.

For two things. A Same-Day Permit covers "minor projects at single-family homes/duplexes. No building plans required", and single-family solar through SolarApp+ is also same day. Solar without SolarApp+ is 3 business days for a house or ADU, 5 for multi-family or nonresidential.

Later than you might expect. The timelines run "after an application has been deemed complete", and before that, "initial fee payment... may take multiple business days to process and confirm receipt. Payment must be confirmed before staff can begin review." Completeness and payment both sit outside the published figures.

Yes. Under AB 3002 and SB 748 the city must make available information on disability access compliance when it issues a commercial building permit or any business licence - covering CASp property inspections through the Division of the State Architect, the California Commission on Disability Access, and the ADA.

Mountain View's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Mountain View yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Mountain View lands. Privacy.

Compare building permit fees across California

Look up this fee in a different city →

Embed this data card →