Change of Use (Business Change of Certificate of Occupancy) — Thornton, Colorado · Requirements sheet
Verified 2026-08-14 · Source: https://www.thorntonco.gov/business-development/city-development/building-permits-inspections
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use (Business Change of Certificate of Occupancy) in Thornton, Colorado
Thornton does not have a permit literally named “Change of Use Permit.” Its functional equivalent is the Business Change of Certificate of Occupancy (Business Change of CO) process, administered by the Building Inspection Division through the CityView Portal, which covers a change of building ownership, change of business ownership, change in business name, and change of use in a building (e.g., retail to restaurant, a new business into an existing or vacant space, or a new business sharing space with an existing business) — provided there are NO construction modifications to the tenant space. If construction modifications are needed (walls, MEP work, kitchen equipment change-out), a Tenant Improvement permit is required instead, and Change-in-Use applications are reviewed case by case to determine which path applies.
Verified 2026-08-14 · Source
When you need this permit
- Applies to a change of building ownership, change of business ownership, change in business name, or change of use in the building (e.g., retail to restaurant, new business into an existing/vacant space, new business sharing space with an existing business), provided there are NO construction modifications to the tenant space
- If there are or will be construction modifications (building/removing walls; electrical, mechanical, or plumbing additions/deletions/alterations; kitchen equipment change-out), a Tenant Improvement permit is required instead of a Business Change of CO
- Applications classified as a Change in Use are reviewed case by case by the Building Inspection Division to determine whether a Tenant Improvement permit is required instead
- A floor plan must be uploaded showing the dimensions of the space, all interior partition walls, the location/size of all exit doors, and a label of each room's use including restrooms (plus a building layout/key plan for multi-tenant buildings showing suite/unit numbers)
- Submitted online via the CityView Portal as a ‘Business Change of CO’ application type under the Building Department
- Both the Building Inspection Division and the Fire Department conduct inspections before a Certificate of Occupancy is issued (e.g., exit/bathroom signage, emergency lighting, exit doors, corridor obstructions, mechanical/electrical/plumbing code issues; a Tri-County Health inspection report is required for food service businesses)
- Businesses equipped with a Fire Alarm, Fire Sprinkler, or Hood (kitchen suppression) System must provide proof of annual testing, maintenance, and inspection within the past 12 months as part of the Fire Prevention Certificate of Occupancy checklist
- New businesses and businesses occupying a new space must obtain a Certificate of Occupancy before opening to the public
- A separate Sign Permit is required if the business is replacing or installing new signs, or placing banners/temporary signs
- A business license must also be obtained through the City's Sales Tax office
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Building Inspection (Change of Occupancy)
Checks exit/bathroom signage, emergency lighting, exit doors, corridor/hallway obstructions, and mechanical/electrical/plumbing code issues; food service businesses must submit a Tri-County Health Inspection Report prior to final inspection
- 2
Fire Prevention Inspection (Change of Occupancy)
Checks Knox Box access, occupant load posting, fire lane/hydrant clearance, means of egress, and fire extinguisher service; businesses with an existing Fire Alarm, Sprinkler, or Hood System must show proof of testing/inspection within the past 12 months
See the full Thornton inspection guide — scheduling & re-inspection fees →
Tips
- If your new use requires ANY construction work — even minor wall changes or MEP alterations — the City redirects you from the $25 Business Change of CO application to a full Tenant Improvement permit, which is reviewed and fee'd very differently. Confirm scope before applying.
- Both Building Inspection AND Fire Prevention must sign off before your Certificate of Occupancy issues — if your space has an existing fire alarm, sprinkler, or kitchen hood system, have your annual testing/inspection report ready (dated within the past 12 months) or the Fire inspection will fail.
- Changing or adding signage as part of your business change requires a SEPARATE Sign Permit application — it is not bundled into the Business Change of CO process.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-14.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Thornton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Thornton
Change of Use (Business Change of Certificate of Occupancy) in other cities
Compare change of use (business change of certificate of occupancy) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Thornton project checklist
Describe your project once and get every permit, document, and fee it triggers in Thornton — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →