Change Of Use / Zoning Certificate Of Occupancy Permit in Akron, Colorado
Unlike sign and fire-sprinkler/alarm permitting, Akron's change-of-use process is genuinely well-documented: Town Code 11-2-5 (Title 11, Zoning Regulations) requires a certificate of occupancy "for the use of vacant land or the change in the use of land" to be applied for before such land is occupied or used, and states the certificate "shall be issued within ten (10) days after the application has been made, provided such use is in conformity with the provisions of this title" -- a real, specific, statutory timeline, one of very few fixed numeric figures found anywhere in this file for Akron. This zoning-level Certificate of Occupancy is distinct from the Title 10 building-code Certificate of Occupancy already documented in the residential-building-permit and commercial-building-permit entries (which sign off on construction quality, not land-use conformity), though a single project can trigger both. Town Code 11-4-1 (Nonconforming Uses) separately governs how a change of use interacts with property that does not conform to its zoning district's regulations.
Verified 2026-08-05 · Source
When you need this permit
- A certificate of occupancy "for the use of vacant land or the change in the use of land" must be applied for BEFORE such land is occupied or used (Town Code 11-2-5.A); the certificate "shall be issued within ten (10) days after the application has been made, provided such use is in conformity with the provisions of this title" -- the only fixed statutory review-timeline figure found anywhere in this file for any Akron permit type, confirmed by direct reading of the current Title 11 text at codelibrary.amlegal.com/codes/akron_co, 2026-08-05
- The certificate "shall state that the building or proposed use of a building or land, complies with all the building and health laws and ordinances and with the provisions of this title" (11-2-5.B.1); a record of all certificates is kept on file in the office of the Building Inspector, with copies furnished on request to any person having a proprietary or tenant's interest in the affected building (11-2-5.B.2)
- No permit for excavation for any building may be issued before an application has been made for a certificate of occupancy (11-2-5.C) -- meaning this change-of-use/CO application can be a gating step ahead of certain building-permit activity, not merely a closing step at the end of a project
- Town Code 11-4-1 (Nonconforming Uses) governs changes to a use that does not conform to its district's zoning regulations: a lawful nonconforming use of land or of a building may continue, but once discontinued any future use must conform (11-4-1.B, C); once a nonconforming BUILDING use has been changed to a more restricted or fully conforming use, "such use shall not thereafter be changed to a less restricted use" (11-4-1.D) -- a one-way ratchet relevant to any change-of-use application on a currently nonconforming property
- A building damaged by fire, explosion, flood, act of God, or a public enemy to more than seventy five percent (75%) of its fair value may not be restored except in conformity with the zoning regulations of the district it sits in (11-4-1.D) -- relevant where a change of use is being considered alongside reconstruction
- If the change of use also involves construction or alteration work, the Town's ordinary Building Permit Application (Title 10) applies as well -- see the residential-addition-remodel and commercial-building-permit entries in this file; the Title 10 building-code Certificate of Occupancy referenced there (which must be obtained before a building can be occupied, per the Town's live Building Department page) is a distinct, construction-quality sign-off from the Title 11 zoning Certificate of Occupancy documented here, though a single project can trigger both
- Contact Akron Town Hall (970-345-2624, Monday-Thursday 7:30 AM-5:30 PM) to obtain the current zoning Certificate of Occupancy / change-of-use application -- no standalone application form for this specific Title 11 process, distinct from the general Zoning Permit Requirements described in Town Code 11-2-4 (application to the office of the town clerk, accompanied by plans/specifications), was located published online as of this research pass
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Zoning compliance review
Per Town Code 11-2-6 (Inspections and Tests), the Building Inspector "shall make or cause to be made such inspections as are necessary to see to the enforcement of the provisions of this title" [Title 11, Zoning Regulations] -- this general zoning-enforcement authority is the basis for confirming a proposed land/building use is "in conformity with the provisions of this title" before the certificate of occupancy is issued under 11-2-5.A. No distinct inspection checklist specific to a change-of-use application, separate from this general authority, is published.
See the full Akron inspection guide — scheduling & re-inspection fees →
Tips
- Akron's change-of-use process is one of the more concretely documented permit types in this file: a real 10-day statutory issuance timeline (Town Code 11-2-5.A) and a real, if nominal, $1.00 fee for non-concurrent certificates (11-2-5.B.3) -- in contrast to nearly every other Akron permit type in this file, where no numeric review timeline is published anywhere.
- Remember there are TWO different "Certificate of Occupancy" concepts in Akron's Code: the Title 11 zoning-level certificate documented in this entry (which addresses land-use conformity and carries the 10-day timeline) and the Title 10 building-code certificate documented in the residential-building-permit and commercial-building-permit entries (which addresses construction-quality sign-off before a building can be occupied). A single project involving both new construction and a use change could require both.
- If the property in question currently has a nonconforming use, review Town Code 11-4-1 before applying -- changing a nonconforming building use to a more restricted or conforming use cannot later be changed back to a less restricted use (11-4-1.D), a one-way ratchet that could permanently affect future flexibility on the property.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Akron building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Akron
Change Of Use / Zoning Certificate Of Occupancy Permit in other cities
Compare change of use / zoning certificate of occupancy permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Akron project checklist
Describe your project once and get every permit, document, and fee it triggers in Akron — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →