Residential Building Permit (New Construction) — Akron, Colorado · Requirements sheet
Verified 2026-07-13 · Source: https://codelibrary.amlegal.com/codes/akron_co/latest/akron_co/0-0-0-1416
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Akron, Colorado
Required for new construction of one- and two-family dwellings and townhomes (not more than three stories) in the Town of Akron. Reviewed under the 2009 IRC as locally adopted and amended (Town Code 10-3-1, 10-3-2), including Akron's specific Table R301.2(1) design criteria (20 psf ground snow load, 90 mph wind speed, Seismic Design Category C, 30-inch frost depth). Issued by the Town's Building Inspector.
Verified 2026-07-13 · Source
When you need this permit
- Plans/work must comply with the 2009 IRC as locally adopted and amended, including Akron's Table R301.2(1) design criteria: 20 psf ground snow load, 90 mph wind speed (no topographic effects), Seismic Design Category C, 30-inch minimum frost line depth, Slight-to-Moderate termite exposure, 0 F winter design temperature, no ice shield underlayment required, Air Freezing Index 0-1000, Mean Annual Temp 47 F
- Automatic residential fire sprinkler systems are NOT required for one- and two-family dwellings under Akron's local amendment to Section R313.2 (deleted); this requirement applies only to townhouses (Section R313.1, effective 2-3-2014)
- Permit becomes invalid if work is not commenced within 180 days of issuance, or if suspended/abandoned for 180 days; standard permit validity is 12 months from issuance, extendable in limited circumstances (see localAmendments)
- Fees are paid to the Town Clerk and deposited in the Town's General Fund per Town Code 10-1-1; building fees and use taxes are calculated based on construction cost and are due at the time the application is submitted (per the Town's live Building Department page) — there is no separate fixed dollar fee schedule to look up
- A Certificate of Occupancy (CO) must be obtained before any building can be occupied (Town's live Building Department page, corroborated by Wayback snapshots of the same page dated 2020-08-13 and 2021-10-06)
- All building permits require a plot plan showing placement of the structure, grades, elevations, sidewalks, curb and gutters, and other pertinent information (per the current application form and the live Building Department page)
- If the work involves roofing, shingles must carry a National Wind Warranty of 89 mph sustained or 115 mph 3-second gust per the current application form; separately, the Town's live Building Department page states roofing must meet Ground Snow 20 / Roof Snow 30 loading, a minimum 110 mph wind shingle rating, and that ice-and-water-guard and drip-edge underlayment are NOT required by the Town (check with your insurer, as their requirements may differ) — both figures are cited as stated by their respective sources and have not been reconciled into a single number
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Confirmed on the Town's live Building Department page (townofakron.com/179/Building) and independently corroborated by Wayback snapshots of the same page dated 2020-08-13 and 2021-10-06; Show full citationHide
Confirmed on the Town's live Building Department page (townofakron.com/179/Building) and independently corroborated by Wayback snapshots of the same page dated 2020-08-13 and 2021-10-06; no separate published fee schedule exists anywhere on the Town's site or in Town Code Title 10.Live Building Department page (townofakron.com/179/Building), checked 2026-07-13: 'Fill out a building permit for the Town of Akron and pay the base pay of $24.60.' Applicant must also submit a… Show full citationHide
Live Building Department page (townofakron.com/179/Building), checked 2026-07-13: 'Fill out a building permit for the Town of Akron and pay the base pay of $24.60.' Applicant must also submit a Google Maps satellite image marking the placement location with the application. This is the only fixed dollar figure published anywhere on the Town's current site or Town Code; it applies specifically to manufactured/mobile home placement, not general new construction.Review timeline
Inspection process
- 1
Foundation
Before concrete pour, per Akron's 30-inch minimum frost line depth (Table R301.2(1))
- 2
Framing
Structural framing complete before cover
- 3
Final Inspection
All work complete per approved plans and applicable codes; required for permanent power/occupancy
See the full Akron inspection guide — scheduling & re-inspection fees →
Tips
- Akron's Table R301.2(1) design criteria are set locally: 20 psf ground snow load, 90 mph wind speed, Seismic Design Category C, and 30-inch frost depth. Confirm your design professional is using these specific figures rather than a generic Colorado Front Range or mountain-town assumption.
- The Town's adopted IRC edition (2009) is notably older than its adopted IBC edition (2018) — if your project spans both codes (e.g., a mixed-use or ambiguous-occupancy structure), confirm with the Building Inspector which edition/chapter governs.
- The Town's website migrated from townofakron.colorado.gov to www.townofakron.com — old bookmarked colorado.gov links now redirect to the new homepage, but the Building Department page and current application PDF are live at townofakron.com/179/Building and townofakron.com/DocumentCenter/View/201 respectively; call Town Hall (970-345-2624, Monday-Thursday 7:30 AM-5:30 PM) to confirm project-specific fees, which are calculated from construction cost rather than published as a table.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Akron building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Akron's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Akron yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Akron lands. Privacy.
Other permits in Akron
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Akron project checklist
Describe your project once and get every permit, document, and fee it triggers in Akron — in one checklist. Free, for any city and any number of projects.
Get started →