Residential Building Permit (New Construction) — Aurora, Colorado · Requirements sheet
Verified 2026-06-30 · Source: https://www.auroragov.org/business_services/building_division/permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Aurora, Colorado
Required for construction of new single-family homes and other R-3/R-4 occupancy residential structures in Aurora. Reviewed against the 2021 IRC with City of Aurora Amendments. Billed per square foot using the 2026 New Building Construction Fee Table rather than a valuation-based formula.
Verified 2026-06-30 · Source
When you need this permit
- Application submitted via the Building Division (Aurora4Biz.org online portal or in person at the Permit Center)
- Plans must comply with the 2021 IRC with City of Aurora Amendments (Aurora City Code Chapter 22) and 2021 IECC
- Table R301.2(1) climatic and geographic design criteria must be shown on plans: 40 psf ground snow load, wind speed per Aurora's wind map/ASCE Hazard Tool, Seismic Design Category B, 36-inch minimum frost depth, 1°F winter design temperature
- Site-specific geotechnical report required for new homes (soil lateral/bearing design)
- Fee is calculated per square foot by occupancy group: R-3 (Single Family Homes) = $1.30/sq ft, plus a minimum state-mandated fee at the $5,000 valuation tier
- R-3 Master Plans (repeat single-family plan sets within a subdivision) are billed a flat $2,655 fee instead of the per-square-foot rate
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footings
Before concrete pour — footings must extend below 36-inch minimum frost depth
- 2
Framing
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-in before walls closed
- 4
Insulation / Energy
Insulation and 2021 IECC compliance verification before drywall
- 5
Final
All work complete, ready for Certificate of Occupancy
See the full Aurora inspection guide — scheduling & re-inspection fees →
Tips
- Aurora bills new single-family construction per square foot ($1.30/sq ft for R-3) rather than using a project-valuation formula like Denver or Reno — request the 2026 New Building Construction Fee Table (Form #A176) to estimate cost.
- Aurora's 36-inch minimum frost depth is deeper than Denver's typical requirement — verify footing depth on plans.
- Ground snow load (40 psf) and Seismic Design Category B are fixed city-published values (Form #A200) — no need to consult the ASCE Hazard Tool for those two criteria, only for site-specific wind speed interpolation.
- Builders working on subdivision-wide single-family plans should ask about the R-3 Master Plan flat fee ($2,655), which can be more economical than per-square-foot billing across repeat plan sets.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aurora building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Aurora
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Aurora project checklist
Describe your project once and get every permit, document, and fee it triggers in Aurora — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →