Residential Building Permit (New Structure) in Avon, Colorado
Required for new single-family homes and new residential structures in the Town of Avon, referred to on the Town's own permit-types guide as a 'New structure permit.' Reviewed under the 2021 IRC/IBC as locally adopted, plus the Town's published design criteria. Mechanical and plumbing are included in a New Structure Permit; electrical permits must be separately obtained through DORA (state), and a fire sprinkler permit is separately obtained through the Eagle River Fire Protection District.
Verified 2026-07-06 · Source
When you need this permit
- Plans must comply with the 2021 IRC/IBC as adopted, and meet the Town's Design Criteria: 129 psf ground snow load (above 8,200 ft) / 107 psf (below), 115 mph wind speed, 48-inch minimum frost depth, -20F winter design temperature, Seismic Design Category B
- One full-size paper plan set required for all new construction before plan review can begin, in addition to the Cloudpermit electronic submittal
- Electrical permits are NOT issued by the Town — must be separately obtained through the Colorado Department of Regulatory Agencies (DORA)
- Fire sprinkler permit (if applicable) obtained separately through the Eagle River Fire Protection District
- Contractor Business License (Cloudpermit) required for the General Contractor/Project Manager before the building permit can be issued
- Exterior design/site elements typically require Planning Division Development Plan review (Minor or Major) in addition to Building Division review
- Applications submitted via the Town of Avon Cloudpermit portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour, per 48-inch minimum frost depth
- 2
Framing
Structural framing complete before cover
- 3
Rough Plumbing / Mechanical
Trade rough-ins before concealment (electrical rough-in inspected separately by DORA)
- 4
Final Inspection
All work complete per approved plans and applicable codes; scheduled through Cloudpermit
See the full Avon inspection guide — scheduling & re-inspection fees →
Tips
- A New Structure Permit in Avon includes mechanical and plumbing review, but NOT electrical — electrical permits and inspections must be separately obtained through the Colorado Department of Regulatory Agencies (DORA), not the Town. Budget a separate DORA application into your project timeline.
- Avon's design criteria vary by elevation: projects above 8,200 feet carry a higher ground snow load (129 psf) and roof snow load (90 psf) than those below (107 psf / 75 psf) — confirm which threshold applies to your specific parcel elevation.
- One full-size paper plan set is still required for new construction even though applications are submitted through Cloudpermit — don't assume the process is fully paperless.
- Avon's adopted code cycle (2021 I-Codes) is one edition behind Vail's (2024 I-Codes) despite being in the same county — do not assume code parity between Eagle County towns.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Avon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Avon
Residential Building Permit (New Structure) in other cities
Compare residential building permit (new structure) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Avon project checklist
Describe your project once and get every permit, document, and fee it triggers in Avon — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →