Commercial Building Permit (New Structure / Remodel-Tenant Improvement) — Avon, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.avon.org/151/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Structure / Remodel-Tenant Improvement) in Avon, Colorado
Commercial construction in the Town of Avon runs through the same Building Division permit tracks as residential — there is no separately-published commercial permit process. The Town's own 'Common Building Permit Types' guide states a New Structure Permit is 'Required for a new home or new commercial building' (mechanical and plumbing included; electrical separately through DORA; fire sprinkler separately through the Eagle River Fire Protection District), and commercial interior remodels/tenant improvements fall under the same Addition/Remodel permit track. The Town's live Cloudpermit permit reports confirm this in practice: commercial projects are issued under a 'Commercial building' category (CRE-prefixed permit numbers) with work type 'Remodel' — no 'tenant improvement' or 'tenant finish' permit type, fee line, or timeline exists anywhere in the Town's published materials. Reviewed under the 2021 IBC as adopted, with the Town's published design criteria.
Verified 2026-08-02 · Source
When you need this permit
- Plans must comply with the 2021 IBC as adopted, and meet the Town's Design Criteria: 129 psf ground snow load (above 8,200 ft) / 107 psf (below), 115 mph wind speed, 48-inch minimum frost depth, -20F winter design temperature, Seismic Design Category B
- One full-size paper plan set required for all new construction before plan review can begin, and for any remodel project requiring architect/engineer-stamped plans, in addition to the Cloudpermit electronic submittal
- Electrical permits are NOT issued by the Town — must be separately obtained through the Colorado Department of Regulatory Agencies (DORA), including illuminated signage
- Fire sprinkler and fire alarm permits obtained separately through the Eagle River Fire Protection District (ERFPD); commercial kitchen hoods require a Town building permit IN ADDITION to the ERFPD permit
- Contractor Business License (via Cloudpermit, valid one year) required before the building permit can be issued
- Exterior work and new commercial structures require Planning Division Development Plan review (Avon Municipal Code 7.16.080) — within the Town Core, a Major Development Plan is a pass-through/deposit application ($1,500 deposit, billed at staff hourly rates); outside the Town Core it is a $750 flat fee; Minor Development Plan is $250
- Applications submitted via the Town of Avon Cloudpermit portal (us.cloudpermit.com/avon)
- Occupant load calculated per IBC Table 1004.5 (1 occupant per 200 gross sq ft for business areas) per the Town's commercial-conversion guidance
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour, per 48-inch minimum frost depth (new structures)
- 2
Framing
Structural framing complete before cover
- 3
Rough Plumbing / Mechanical
Trade rough-ins before concealment; electrical rough-in inspected separately by DORA, fire systems separately by ERFPD
- 4
Final Inspection
Required for ALL projects that require a building permit, per the Town's General Department Information page — 'ALL projects that require a building permit will require a final inspection at the very least. Often, multiple inspections will be required throughout the project.' Scheduled through Cloudpermit; certificate-of-occupancy scope also requires DORA electrical final and any ERFPD finals
See the full Avon inspection guide — scheduling & re-inspection fees →
Tips
- There is NO separate tenant-improvement or tenant-finish permit type in Avon — despite the town's heavy hotel/retail/restaurant turnover, commercial buildouts are issued as 'Commercial building / Remodel' permits (CRE-prefixed in Cloudpermit) under the same Addition/Remodel process, the same unified valuation-based fee table, and the same published review timeline as everything else. Do not look for a TI-specific fee schedule; it does not exist.
- Budget for THREE permitting authorities on most commercial projects: the Town (building/plumbing/mechanical), DORA (all electrical, including illuminated signs), and the Eagle River Fire Protection District (fire alarm/sprinkler, plus kitchen hoods and EV charge stations which need a Town building permit in addition to the ERFPD permit).
- Commercial projects in the Town Core face the most expensive design-review path: a Major Development Plan within the Town Core is a pass-through deposit application ($1,500 down, billed at staff hourly rates up to $140/hr) rather than the $750 flat fee that applies outside the core — factor Planning Division review time and cost in before the building permit clock even starts.
- A restaurant buildout typically stacks: Commercial building/Remodel permit (Town) + kitchen hood building permit (Town) + hood/fire-suppression permit (ERFPD) + electrical (DORA) + sign permit with planning approval (Town) — plan applications in parallel where possible.
- The 4% use tax on construction materials applies to commercial projects valued at $250,000+ (effective January 1, 2025); below that threshold, materials purchased outside Avon may require a Sales Tax License instead.
- The fee schedule's own $500,001-$1,000,000 tier line contains a typographical error in the source PDF ('$3,560 for the first $50,000'); the tier structure makes clear it means the first $500,000 — confirm the exact computed fee with the Building Division, since the Building Official approves all final fee determinations.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Avon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Avon.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Avon
Commercial Building Permit (New Structure / Remodel-Tenant Improvement) in other cities
Look up this fee in a different city →
Now live
Build your Avon project checklist
Describe your project once and get every permit, document, and fee it triggers in Avon — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →