Avon building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Avon, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 100 Mikaela Way, P.O. Box 975, Avon, CO 81620
- Phone
- 970-748-4030
- eblock@avon.org
- Office hours
- 8:00 a.m. - 5:00 p.m., Monday - Friday. Building Official Derek Place: dplace@avon.org, 970-748-4011. Building Inspector Matt Waldrop: mwaldrop@avon.org, 970-748-4098. Community Development Coordinator Emily Block: eblock@avon.org, 970-748-4012. Main Town line: 970-748-4000.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Structure)
- 1
Foundation
Before concrete pour, per 48-inch minimum frost depth
- 2
Framing
Structural framing complete before cover
- 3
Rough Plumbing / Mechanical
Trade rough-ins before concealment (electrical rough-in inspected separately by DORA)
- 4
Final Inspection
All work complete per approved plans and applicable codes; scheduled through Cloudpermit
Applies to: Addition / Remodel Permit
- 1
Rough Frame
Framing complete, connection to existing structure verified
- 2
Rough Plumbing / Mechanical
Trade rough-ins before concealment where applicable
- 3
Final Inspection
All work complete per approved plans
Applies to: Solar Photovoltaic (PV) Permit
- 1
Town Building/Roof-Mount Inspection
Racking and roof-penetration compliance verified by the Town
- 2
Fire Department Final (ERFPD)
Solar electrical PV final inspection required by the Eagle River Fire Protection District
- 3
DORA Electrical Final
Separate final electrical inspection required through the Colorado Department of Regulatory Agencies
Applies to: Mechanical / Gas Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Final inspection only: Replacement / New Roof Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Avon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Avon building permits
Get alerts for Avon
We'll email you when Avon's fees, documents, or codes change — not often.