Required for new commercial construction, and for commercial remodels, additions, and tenant improvements/alterations, within Town of Akron limits. Administered directly by the Town's own Building Inspector (Town Code 10-1-1) — NOT by Washington County (whose Land Use Office covers only the unincorporated county) and NOT by any regional building department. Reviewed under the 2018 International Building Code, chapters 1-35 plus appendices C, E, G, H, I, and J, as adopted by Town Code 10-2-1 (Ord. 514, 1-6-2014; amd. Ord. 589, 6-5-2023) and locally amended by Town Code 10-2-2 (Ord. 548, 1-3-2018). Commercial projects use the SAME unified Building Permit Application form as residential — the current form ('BUILDING PERMIT - UPDATED 08-2024.pdf') has a top-level 'PERMIT TYPE: RESIDENTIAL or COMMERCIAL' checkbox pair, confirmed by direct reading of the live form 2026-08-02. There is no separate commercial application, no separate tenant-improvement permit type, and no commercial-specific fee schedule anywhere in the Town Code or on the Town's website.

Verified 2026-08-02 · Source

When you need this permit

  • Plans/work must comply with the 2018 IBC (chapters 1-35, appendices C, E, G, H, I, J) as adopted by Town Code 10-2-1 and amended by 10-2-2 — full section text re-verified live 2026-08-02 against the current amlegal 2025 S-5 code edition; Ord. 589 (6-5-2023) amended the adoption section but the currently published text still names the 2018 edition
  • Akron's local amendment to IBC Section 105.2 (Town Code 10-2-2) DELETES base-code permit-exemption items Building 1, 2, 3, 4, 6, 7, & 12 — several small-project exemptions a national-code reader would expect do not apply in Akron; per the Town's live Building Department page, 'Any structure built, placed, or added to within town limits... will first require completion of a building permit'
  • Permit expiration per locally amended Section 105.5 (verified from the live code text and restated on the application form itself): permit becomes invalid if work is not commenced within 180 days of issuance or is suspended/abandoned for 180 days; standard validity is 12 months, extendable — a permit valid up to 3 years may be issued if the applicant shows at application time the project will exceed 12 months (relevant to larger commercial builds), and the Building Official may grant written 180-day extensions on written request with justifiable cause
  • A plot plan showing placement of the structure, grades, elevations, sidewalks, curb and gutters, and other pertinent information must be attached to the application (stated on both the live Building Department page and the application form)
  • The application requires the total project value (material and labor) and cost of materials (with purchase location, for use-tax purposes); all applicable fees must be paid at the time of application, and the form states any extraordinary cost incurred by the Town in reviewing/processing the application, including attorney fees, is the applicant's responsibility
  • Electrical and plumbing work is NOT permitted by the Town — Akron's Title 10 has no electrical or plumbing chapter; obtain Colorado State Electrical Board and State Plumbing Board permits (DORA/DPO) and record the permit numbers in the application form's dedicated 'STATE ELECTRIC PERMIT #' and 'STATE PLUMBING PERMIT #' fields
  • The applicant must certify on the form that the construction is not related to the production or dispensing of marijuana
  • A Certificate of Occupancy (CO) must be obtained before any building can be occupied (Town's live Building Department page)
  • Note: Akron has adopted NO energy code (no IECC chapter exists in Title 10) and no standalone mechanical or fuel-gas code — see this file's codesAdopted/localAmendments for the HB22-1362 analysis

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Commercial building permit feeConfirmed on the Town's live Building Department page (townofakron.com/179/Building, re-checked 2026-08-02): 'Building fees and use taxes are calculated based on construction cost' and are due with the application. No published fee table exists anywhere in Town Code Title 10 or on the Town's website, for commercial or any other permit class (the only fixed dollar figure on the entire site is the $24.60 manufactured/mobile-home placement base fee, which does not apply here). Beware the amlegal.com same-name collision: the 'Town of Akron Building Code Fee Schedule' that search engines surface is Akron, INDIANA's code (codes/akron/latest/akron_in/...), not this jurisdiction — re-confirmed in search results 2026-08-02. Call Town Hall (970-345-2624) for a project-specific fee quote.
Not a fixed figure — calculated based on construction cost (valuation-based), due at time of application submission
Use taxes (county and city) on construction materialsThe application form collects Total Value (material and labor) and Cost of Material with purchase location (In Akron / Out of Akron / Delivered), and its office-use fee block itemizes 'Permit Fee', 'County Tax', 'City Tax', and 'Rec' lines — direct reading of the current application form, 2026-08-02. The live Building Department page confirms use taxes are calculated based on construction cost and due at application.
Calculated from construction cost / cost of materials; no published rate table on the Town's building pages
Extraordinary review/processing cost recoveryStated on the current application form itself: 'Any extraordinary cost incurred by the Town of Akron in reviewing and processing this application, including attorney fees, is the responsibility of the applicant.' Plausibly relevant to larger/complex commercial projects a one-person building office may send out for review, though the Town publishes no threshold or policy for when outside review is used.
Actual cost, including attorney fees, if incurred

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Akron?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings/Foundation

    Before concrete pour; the Building Inspector's worksheet on page 2 of the current application form has dedicated fields for footing size/type and foundation size/type, plus a 'Special Inspector Required: Yes/No' determination for the project

  2. 2

    Framing/Rough (trades as applicable)

    Structural framing complete before cover; state inspectors separately perform rough electrical/plumbing inspections under the state-issued trade permits

  3. 3

    Final Inspection / Certificate of Occupancy

    All work complete per approved plans and the 2018 IBC as locally amended; a Certificate of Occupancy must be obtained before the building can be occupied (Town's live Building Department page)

See the full Akron inspection guide — scheduling & re-inspection fees →

Tips

  • There is NO separate tenant-improvement permit in Akron — commercial interior alterations/TI work goes through the same unified Building Permit Application (check 'COMMERCIAL' plus 'Remodeling or Addition'), with the same valuation-based fee calculation, confirmed by direct reading of the current application form and the Town's live Building Department page (2026-08-02). No TI-specific fee, form, or timeline is published anywhere in the Town Code or on the Town's site.
  • Akron is the seat of Washington County, but the County's Land Use Office administers permits only for the UNINCORPORATED county — inside Akron town limits, the Town's own Building Inspector (Town Code 10-1-1) is the permitting authority. Do not apply to the county for a project inside town limits.
  • Larger commercial builds should invoke the locally amended Section 105.5 up front: if you show at application time that the work is substantial and likely to exceed 12 months, the Town may issue a permit valid up to 3 years instead of the standard 12 months — cheaper than chasing 180-day extensions later.
  • Budget for the trade-permit split: the Town permit covers only the building scope; electrical and plumbing are permitted and inspected by the Colorado State Electrical and Plumbing Boards (DORA/DPO), and their permit numbers must be reported on the Town's application form.
  • Akron has adopted no energy code and no mechanical/fuel-gas code chapter — scope questions on mechanical systems in a commercial project should go directly to the Building Inspector (970-345-2624), since the 2018 IBC as adopted is the only locally codified standard.

Frequently asked questions

Akron requires a commercial building permit for: Plans/work must comply with the 2018 IBC (chapters 1-35, appendices C, E, G, H, I, J) as adopted by Town Code 10-2-1 and amended by 10-2-2 — full section text re-verified live 2026-08-02 against the current amlegal 2025 S-5 code edition; Ord. 589 (6-5-2023) amended the adoption section but the currently published text still names the 2018 edition; Akron's local amendment to IBC Section 105.2 (Town Code 10-2-2) DELETES base-code permit-exemption items Building 1, 2, 3, 4, 6, 7, & 12 — several small-project exemptions a national-code reader would expect do not apply in Akron; per the Town's live Building Department page, 'Any structure built, placed, or added to within town limits... will first require completion of a building permit'; Permit expiration per locally amended Section 105.5 (verified from the live code text and restated on the application form itself): permit becomes invalid if work is not commenced within 180 days of issuance or is suspended/abandoned for 180 days; standard validity is 12 months, extendable — a permit valid up to 3 years may be issued if the applicant shows at application time the project will exceed 12 months (relevant to larger commercial builds), and the Building Official may grant written 180-day extensions on written request with justifiable cause; A plot plan showing placement of the structure, grades, elevations, sidewalks, curb and gutters, and other pertinent information must be attached to the application (stated on both the live Building Department page and the application form); The application requires the total project value (material and labor) and cost of materials (with purchase location, for use-tax purposes); all applicable fees must be paid at the time of application, and the form states any extraordinary cost incurred by the Town in reviewing/processing the application, including attorney fees, is the applicant's responsibility; Electrical and plumbing work is NOT permitted by the Town — Akron's Title 10 has no electrical or plumbing chapter; obtain Colorado State Electrical Board and State Plumbing Board permits (DORA/DPO) and record the permit numbers in the application form's dedicated 'STATE ELECTRIC PERMIT #' and 'STATE PLUMBING PERMIT #' fields; The applicant must certify on the form that the construction is not related to the production or dispensing of marijuana; A Certificate of Occupancy (CO) must be obtained before any building can be occupied (Town's live Building Department page); Note: Akron has adopted NO energy code (no IECC chapter exists in Title 10) and no standalone mechanical or fuel-gas code — see this file's codesAdopted/localAmendments for the HB22-1362 analysis. If your project isn't listed, confirm with Town of Akron — Office of the Building Inspector (Town Hall) at 970-345-2624 before starting work.

There is no published fee table. Building fees and use taxes are calculated per-application based on construction cost and are due when the application is submitted; the application form also makes any extraordinary review costs (including attorney fees) the applicant's responsibility. Call Town Hall (970-345-2624) for a project-specific quote — and note that the 'Town of Akron Building Code Fee Schedule' findable online belongs to Akron, Indiana, not Akron, Colorado.

Akron does not publish a plan-review timeline for this permit. Contact Town of Akron — Office of the Building Inspector (Town Hall) at 970-345-2624 for current turnaround.

You'll need: Building Permit Application (unified form — check 'COMMERCIAL'); Plot Plan; State Electrical and Plumbing Permit Numbers. See the required-documents checklist on this page for details on each.

Akron requires 3 inspection(s) for a commercial building permit, in order: Footings/Foundation, Framing/Rough (trades as applicable), Final Inspection / Certificate of Occupancy. Schedule each through Town of Akron — Office of the Building Inspector (Town Hall) (970-345-2624).

Apply through Town of Akron — Office of the Building Inspector (Town Hall) at 250 Main Ave, Akron, CO 80720. Phone: 970-345-2624, email: deputyclerk@townofakron.com. Office hours: Monday - Thursday, 7:30 AM - 5:30 PM; closed Fridays. Fax: 970-345-2617. Per Town Code 10-1-1, the Building Inspector is appointed by the Board of Trustees at its first regular meeting following each biennial election and serves as chief enforcement officer for all Title 10 building regulations (except fire prevention code); there is no separate physical 'Building Department' office distinct from Town Hall in this small Eastern Plains town (2020 Census population 1,757).. Official information: https://www.townofakron.com/179/Building.

The Town of Akron's own Building Inspector, appointed by the Board of Trustees under Town Code 10-1-1. Akron does not contract building safety to Washington County or a regional building department — the county's Land Use Office covers only unincorporated areas. Commercial projects are reviewed under the 2018 IBC as adopted by Town Code 10-2-1 and amended by 10-2-2.

No. Tenant improvements and commercial remodels use the same unified Building Permit Application as all other work — check the 'COMMERCIAL' permit-type box and the 'Remodeling or Addition' project box. Fees are calculated from construction cost the same way as any other permit; no TI-specific permit type, fee, or process is published anywhere in Akron's Town Code or on the Town's website.

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Akron building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Akron.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.