Residential Building Permit (New Construction) in Alamosa, Colorado

Required for construction of new single-family homes and other one- and two-family dwellings within City of Alamosa limits. Reviewed under the 2018 IRC/IBC as locally adopted, plus the City's own structural design criteria (snow, wind, frost depth, seismic). Issued by the City of Alamosa Building Department; electrical and plumbing work on the project is permitted and inspected separately by the State of Colorado, not the City.

Verified 2026-07-06 · Source

When you need this permit

  • Plans must comply with the 2018 IRC/IBC as adopted by the City of Alamosa
  • Must meet the City's published design criteria: Ground Snow Load 30 psf, Wind Design Speed 115/89 mph, Frost Line Depth 36 inches (ice) / 32 inches (damage), Seismic Design Category C, Winter Design Temperature -16°F, required ice barrier underlayment
  • Application (per the City's Building Permit & Certificate of Occupancy Application form) requires: site address/parcel number, owner information, contractor information (name, address, city license number), engineer/architect information where applicable, construction type (I-V), occupancy group, land use zone and land use, total floor area, height, stories, setbacks (front/side/street side/rear), and project cost
  • Applicant acknowledges responsibility for asbestos-regulation compliance (CDPHE Regulation No. 8, Part B) at time of application
  • Non-compliant public sidewalks must be upgraded if construction valuation exceeds $80,000, per Sec. 16-42 of City ordinances (per the Building Permit Application form's own stated threshold)
  • Applicant is responsible for scheduling all required inspections; Final Inspection must be scheduled within 10 working days of job completion
  • All electrical and plumbing work on the project is separately permitted and inspected by the State of Colorado (DORA Division of Professions and Occupations), not included in this City building permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $1 to $500City of Alamosa Permit Fee Schedule 'A', Revision 8/9/2023
$24
Building Permit Fee — valuation $501 to $2,000
$24 for the first $500, plus $3 for each additional $100 or fraction thereof, up to and including $2,000
Building Permit Fee — valuation $2,001 to $40,000
$69 for the first $2,000, plus $11 for each additional $1,000 or fraction thereof, up to and including $40,000
Building Permit Fee — valuation $40,001 to $100,000
$487 for the first $40,000, plus $9 for each additional $1,000 or fraction thereof, up to and including $100,000
Building Permit Fee — valuation $100,001 to $500,000
$1,027 for the first $100,000, plus $7 for each additional $1,000 or fraction thereof, up to and including $500,000
Building Permit Fee — valuation $500,001 to $1,000,000
$3,827 for the first $500,000, plus $5 for each additional $1,000 or fraction thereof, up to and including $1,000,000
Building Permit Fee — valuation $1,000,001 to $5,000,000
$6,327 for the first $1,000,000, plus $3 for each additional $1,000 or fraction thereof, up to and including $5,000,000
Building Permit Fee — valuation $5,000,001 and up
$18,327 for the first $5,000,000, plus $1 for each additional $1,000 or fraction thereof
Plan Review FeeFee Schedule 'B'
25% of the Building Permit Fee
Outside consulting for plan review/inspectionIncludes administration and overhead cost
Actual cost

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction) permit actually take in Alamosa?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour, per 36-inch frost depth requirement

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Final Inspection

    All City-permitted work complete per approved plans; must be scheduled within 10 working days of job completion. Electrical and plumbing final inspections are conducted separately by the State of Colorado, not the City

See the full Alamosa inspection guide — scheduling & re-inspection fees →

Tips

  • Electrical AND plumbing work on your new home are NOT part of this City building permit — both trades are permitted and inspected exclusively by the State of Colorado (DORA), a broader split than many peer jurisdictions in this corpus where only electrical routes to the state.
  • Schedule your Final Inspection within 10 working days of job completion — this is stated explicitly on the City's own application form, not just a general courtesy guideline.
  • The City's own forms disagree on the sidewalk-upgrade valuation threshold under Sec. 16-42 ($80,000 on the Building Permit Application vs. $20,000 on the Solar Permit Application) — confirm the applicable figure directly with the Building Department for your specific project type.
  • Alamosa's design snow/wind/frost criteria (30 psf snow, 115/89 mph wind, 36-inch frost depth) are notably lighter than higher-elevation Front Range jurisdictions like Golden — don't reuse a different Colorado jurisdiction's structural assumptions.

Frequently asked questions

Alamosa requires a residential building permit (new construction) for: Plans must comply with the 2018 IRC/IBC as adopted by the City of Alamosa; Must meet the City's published design criteria: Ground Snow Load 30 psf, Wind Design Speed 115/89 mph, Frost Line Depth 36 inches (ice) / 32 inches (damage), Seismic Design Category C, Winter Design Temperature -16°F, required ice barrier underlayment; Application (per the City's Building Permit & Certificate of Occupancy Application form) requires: site address/parcel number, owner information, contractor information (name, address, city license number), engineer/architect information where applicable, construction type (I-V), occupancy group, land use zone and land use, total floor area, height, stories, setbacks (front/side/street side/rear), and project cost; Applicant acknowledges responsibility for asbestos-regulation compliance (CDPHE Regulation No. 8, Part B) at time of application; Non-compliant public sidewalks must be upgraded if construction valuation exceeds $80,000, per Sec. 16-42 of City ordinances (per the Building Permit Application form's own stated threshold); Applicant is responsible for scheduling all required inspections; Final Inspection must be scheduled within 10 working days of job completion; All electrical and plumbing work on the project is separately permitted and inspected by the State of Colorado (DORA Division of Professions and Occupations), not included in this City building permit. If your project isn't listed, confirm with City of Alamosa Building Department (Development Services) at (719) 589-6631 before starting work.

In Alamosa, the published Building Permit Fee — valuation $1 to $500 is: $24. Additional published fees: Building Permit Fee — valuation $501 to $2,000 — $24 for the first $500, plus $3 for each additional $100 or fraction thereof, up to and including $2,000; Building Permit Fee — valuation $2,001 to $40,000 — $69 for the first $2,000, plus $11 for each additional $1,000 or fraction thereof, up to and including $40,000; Building Permit Fee — valuation $40,001 to $100,000 — $487 for the first $40,000, plus $9 for each additional $1,000 or fraction thereof, up to and including $100,000; Building Permit Fee — valuation $100,001 to $500,000 — $1,027 for the first $100,000, plus $7 for each additional $1,000 or fraction thereof, up to and including $500,000; Building Permit Fee — valuation $500,001 to $1,000,000 — $3,827 for the first $500,000, plus $5 for each additional $1,000 or fraction thereof, up to and including $1,000,000; Building Permit Fee — valuation $1,000,001 to $5,000,000 — $6,327 for the first $1,000,000, plus $3 for each additional $1,000 or fraction thereof, up to and including $5,000,000; Building Permit Fee — valuation $5,000,001 and up — $18,327 for the first $5,000,000, plus $1 for each additional $1,000 or fraction thereof; Plan Review Fee — 25% of the Building Permit Fee; Outside consulting for plan review/inspection — Actual cost. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Alamosa does not publish a plan-review timeline for this permit. Contact City of Alamosa Building Department (Development Services) at (719) 589-6631 for current turnaround.

You'll need: Building Permit & Certificate of Occupancy Application; Construction Drawings / Plans; Site Plan. See the required-documents checklist on this page for details on each.

Alamosa requires 3 inspection(s) for a residential building permit (new construction), in order: Foundation, Rough Framing, Final Inspection. Schedule each through City of Alamosa Building Department (Development Services) ((719) 589-6631).

Apply through City of Alamosa Building Department (Development Services) at 300 Hunt Ave, Alamosa, CO 81101. Phone: (719) 589-6631, email: Not published as a direct department email on the current alamosa.gov Building Department or Development Services pages as of this review; general inquiries route through (719) 589-6631 (Building Department / Development Services Director Rachel James) or the main City line (719) 589-2593. Office hours: Standard office hours are not published on the current Building Department page; inspections must be scheduled at least one day in advance and occur between 10am and 4pm, by calling (719) 589-6631. Official information: https://www.alamosa.gov/building-department.

The City of Alamosa Building Department (part of Development Services, 300 Hunt Ave) issues building, mechanical, roofing, window-replacement, solar, and demolition permits for all work within Alamosa city limits. Alamosa is a home-rule city with its own department; Alamosa County's Building Department covers only unincorporated county areas, not the City of Alamosa, per the County's own published jurisdiction statement.

No. Per the City's own Building Department page: 'Electrical and plumbing inspections are not completed by our office, they are done by the state.' Both trades are permitted through the Colorado Division of Professions and Occupations Electrical and Plumbing Permits program (dpo.colorado.gov/EandP/Permits).

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Alamosa building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Compare residential building permit (new construction) fees across Colorado

Look up this fee in a different city →

Embed this data card →

Now live

Build your Alamosa project checklist

Describe your project once and get every permit, document, and fee it triggers in Alamosa — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →