Skip to main content
PermitBase

Demolition Permit in Alamosa, Colorado

Required for demolition of structures within Alamosa city limits, per the City's dedicated Demolition Permit Application. An approved State of Colorado Demolition Permit must be provided at the time of application; the City's own demolition permit fee is a flat, low-cost line item, valid for only 30 days.

Verified 2026-07-06 · Source

When you need this permit

  • A copy of an approved State of Colorado Demolition Permit is required at the time of application, per the Application for Demolition Permit form's own stated requirement
  • Application (per the form) requires: project address, property owner and contractor information, description of demolition, description of materials being removed, occupancy group, hazardous materials testing information, list of materials being removed, and disclosure of which service utility connections (gas, plumbing, electrical) are present
  • If partial demolition, the application requires a description of the portion being demolished
  • Applicant must notify the City of Alamosa Building Department within 10 working days of job completion, per the form
  • The City's Demolition Permit fee is valid for 30 days, per Fee Schedule 'B'

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition Permit FeeCity of Alamosa Permit Fee Schedule 'B', Revision 8/9/2023; must provide approved State Demolition Permit; valid for 30 days
$15.00

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Alamosa?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Confirms complete removal per permit scope; City must be notified within 10 working days of job completion

See the full Alamosa inspection guide — scheduling & re-inspection fees →

Tips

  • You need the STATE demolition permit approved and in hand first — the City's own application form requires a copy of the approved state permit as a condition of applying, mirroring the Durango model.
  • The City's demolition permit fee ($15.00) is one of the lowest flat fees in the schedule, but it is only valid for 30 days — don't let the window lapse before starting work.
  • The demolition application specifically asks you to disclose which service utilities (gas, plumbing, electrical) are connected — have disconnection status confirmed before applying.

Frequently asked questions

Alamosa requires a demolition permit for: A copy of an approved State of Colorado Demolition Permit is required at the time of application, per the Application for Demolition Permit form's own stated requirement; Application (per the form) requires: project address, property owner and contractor information, description of demolition, description of materials being removed, occupancy group, hazardous materials testing information, list of materials being removed, and disclosure of which service utility connections (gas, plumbing, electrical) are present; If partial demolition, the application requires a description of the portion being demolished; Applicant must notify the City of Alamosa Building Department within 10 working days of job completion, per the form; The City's Demolition Permit fee is valid for 30 days, per Fee Schedule 'B'. If your project isn't listed, confirm with City of Alamosa Building Department (Development Services) at (719) 589-6631 before starting work.

$15.00, per the City's Permit Fee Schedule 'B' (Revision 8/9/2023). The permit is valid for 30 days from issuance.

Alamosa does not publish a plan-review timeline for this permit. Contact City of Alamosa Building Department (Development Services) at (719) 589-6631 for current turnaround.

You'll need: Approved State of Colorado Demolition Permit; Application for Demolition Permit; Hazardous Materials Testing documentation. See the required-documents checklist on this page for details on each.

Alamosa requires 1 inspection(s) for a demolition permit, in order: Final Inspection. Schedule each through City of Alamosa Building Department (Development Services) ((719) 589-6631).

Apply through City of Alamosa Building Department (Development Services) at 300 Hunt Ave, Alamosa, CO 81101. Phone: (719) 589-6631, email: Not published as a direct department email on the current alamosa.gov Building Department or Development Services pages as of this review; general inquiries route through (719) 589-6631 (Building Department / Development Services Director Rachel James) or the main City line (719) 589-2593. Office hours: Standard office hours are not published on the current Building Department page; inspections must be scheduled at least one day in advance and occur between 10am and 4pm, by calling (719) 589-6631. Official information: https://www.alamosa.gov/building-department.

Alamosa, Colorado has adopted: 2018 International Building Code (IBC) — City of Alamosa Building Department page (alamosa.gov/building-department); 2018 International Residential Code (IRC); 2018 International Mechanical Code (IMC); 2018 International Energy Conservation Code (IECC); 2018 International Fire Code (IFC); 2018 International Property Maintenance Code (IPMC); 2018 International Existing Building Code (IEBC); 2009 ICC/ANSI A117.1 Accessible and Usable Buildings and Facilities (ICCA 2009); 2023 National Electrical Code (NEC) — State of Colorado adopted edition, enforced by the state (not the City) per the City's own Building Department page; 2021 International Plumbing Code (IPC) — State of Colorado adopted edition, enforced by the state (not the City); 2021 International Fuel Gas Code (IFGC) — State of Colorado adopted edition, enforced by the state (not the City); Local design criteria published alongside the adopted codes: Ground Snow Load 30 psf; Wind Design Speed 115/89 mph; Frost Line Depth 36 inches (ice) / 32 inches (damage); Seismic Design Category C; Winter Design Temperature -16°F; Air Freezing Index 3000; Mean Annual Temperature 45°F; Ice Barrier Underlayment required. Local amendments apply — see the Alamosa overview page for the full list.

No. The City's own Application for Demolition Permit form requires a copy of an approved State of Colorado Demolition Permit to be provided at the time of application.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Alamosa building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.