Demolition Permit in Bennett, Colorado

Required for demolition of primary and secondary/accessory structures in Bennett. Billed as a flat fee (not valuation-based), with separate rates for primary versus secondary/accessory structures. Asbestos inspection guidance is published alongside the demolition permit materials.

Verified 2026-07-06 · Source

When you need this permit

  • Primary Structure and Secondary/Accessory Structure demolitions are billed at different flat fees
  • Asbestos inspection required per Colorado Department of Public Health and Environment (CDPHE) regulations — the Town publishes CDPHE's 'Is an Asbestos Inspection Required?' guidance and a dedicated 'Asbestos - Renovation and Demolition' resource directly on the Building Permits page
  • A Town of Bennett 'Demolition and Renovation' guide defines submittal requirements
  • A 'Demolition' Building Guide is also published on the Building Guides and Checklists page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition Permit — Primary StructureFlat fee, June 24, 2026 Schedule of Fees
$250.00
Demolition Permit — Secondary/Accessory StructureFlat fee
$50.00

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Bennett?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-Demolition Asbestos Verification

    Confirms CDPHE asbestos determination/inspection is on file before demolition begins

  2. 2

    Final Inspection

    Site cleared, utilities disconnected/capped per Town requirements

See the full Bennett inspection guide — scheduling & re-inspection fees →

Tips

  • Demolition permits in Bennett are a FLAT fee ($250 primary structure, $50 secondary/accessory), unlike most other Bennett building permits which are valuation-based — don't apply the general Building Permit fee table to a demolition scope.
  • Confirm your asbestos inspection obligation using the Town-published CDPHE 'Is an Asbestos Inspection Required?' guidance before scheduling demolition; this is a state environmental requirement layered on top of the Town's own demolition permit process.

Frequently asked questions

Bennett requires a demolition permit for: Primary Structure and Secondary/Accessory Structure demolitions are billed at different flat fees; Asbestos inspection required per Colorado Department of Public Health and Environment (CDPHE) regulations — the Town publishes CDPHE's 'Is an Asbestos Inspection Required?' guidance and a dedicated 'Asbestos - Renovation and Demolition' resource directly on the Building Permits page; A Town of Bennett 'Demolition and Renovation' guide defines submittal requirements; A 'Demolition' Building Guide is also published on the Building Guides and Checklists page. If your project isn't listed, confirm with Town of Bennett Community Development Department, Building Department at 303-644-3249 before starting work.

No. Bennett charges a flat demolition permit fee — $250.00 for a primary structure or $50.00 for a secondary/accessory structure — rather than a valuation-based fee like most other Bennett building permits.

Bennett does not publish a plan-review timeline for this permit. Contact Town of Bennett Community Development Department, Building Department at 303-644-3249 for current turnaround.

You'll need: Demolition Permit Application; Asbestos Inspection Report / CDPHE Determination. Depending on your project, Bennett may also ask for: Town of Bennett Demolition and Renovation Guide. See the required-documents checklist on this page for details on each.

Bennett requires 2 inspection(s) for a demolition permit, in order: Pre-Demolition Asbestos Verification, Final Inspection. Schedule each through Town of Bennett Community Development Department, Building Department (303-644-3249).

Apply through Town of Bennett Community Development Department, Building Department at 207 Muegge Way, Bennett, CO 80102. Phone: 303-644-3249, email: bennettbuilding@bennett.co.us. Office hours: Main Town line 303-644-3249 (Building Department extension 1032 per the Building Permits page). Chief Building Official (Steve Jones, Charles Abbott Associates — Bennett's building department is staffed via a CAA contract) holds Drop-In Hours at Town Hall Tuesdays 12:30-1:30 p.m.; email bennettbuilding@bennett.co.us or stevejones@caa.inc to schedule a plan/project review meeting. Additional CAA inspection staff: Brad Jones 720-960-0576 (bradjones@caa.inc), Daniel Willman 720-361-9732 (danielwillman@caa.inc). Inspection requests must be received by 4:00 p.m. the business day before for next-day scheduling; inspections occur Monday-Friday, 7:00 a.m.-5:00 p.m., no specific-window guarantee.. Official information: https://www.bennettco.gov/community-development/page/building-department.

Bennett, Colorado has adopted: 2024 International Building Code (IBC) — effective July 1, 2026 per Town of Bennett 'Building Code Update 2026' notice; 2024 International Residential Code (IRC) — effective July 1, 2026; 2024 International Existing Building Code (IEBC) — effective July 1, 2026; 2024 International Mechanical Code (IMC) — effective July 1, 2026; 2024 International Energy Conservation Code (IECC) — effective July 1, 2026; 2024 International Plumbing Code (IPC) — effective July 1, 2026; 2024 International Fire Code (IFC) — effective July 1, 2026 for the Town's own adoption (Bennett-Watkins Fire Rescue, the separate special district that performs fire plan review/inspection for Bennett, Watkins, and unincorporated Adams/Arapahoe County, is separately shown by its own website as still operating under the 2018 IFC as of this review — confirm current fire-district code edition directly with Bennett-Watkins Fire Rescue at 303-644-3572, since fire code adoption is that district's own action, not the Town Building Department's); 2024 International Fuel Gas Code (IFGC) — effective July 1, 2026; 2024 International Swimming Pool and Spa Code (ISPSC) — effective July 1, 2026 (new code title added in this cycle; no 2018-cycle equivalent was listed); Colorado Model Electric and Solar Ready Code — effective July 1, 2026 (statewide model code addressing EV/solar readiness, adopted by the Town as part of the 2026 cycle); 2025 Colorado Wildfire Resiliency Code — effective July 1, 2026; 2023 National Electrical Code (NEC) — currently in effect per the Town's Adopted Building Department Codes list (the NEC was not part of the July 1, 2026 update batch and continues under its existing adoption); PRIOR CYCLE (2018 codes), still governing permits issued before July 1, 2026 that have not expired: 2018 IBC, 2018 IRC, 2018 IPC, 2018 IMC, 2018 IEBC, 2018 IFC, 2018 IFGC, 2018 IECC.; Transition rule (per the Town's 'Building Code Update 2026' notice, verified directly): the Town issued NO permits under the 2024 cycle before July 1, 2026. Permits issued under the 2018 cycle before July 1, 2026 may finish construction on that code cycle, UNLESS the permit expires after July 1, 2026, in which case renewal or a new permit after that date requires meeting 2024 code. All permits issued on or after July 1, 2026 must meet the 2024 I-codes. EXCEPTION: 8 named residential master-plan developments currently under construction on 2018-cycle approved master plans (Bennett Avenue Townhomes; Bennett Crossing Filing 5 Phases 1A/1B; Bennett Ranch Filing 1; Bennett Ranch Filing 2; Horizon Village; Muegge Farms Filing 4 Phases 4A/4B; Muegge Farms Filing 5; Muegge Farms Filing 7 Phase 1) are given until July 1, 2028 to finish their current phase under the 2018 cycle. As of this file's lastVerified date (2026-07-06), the 2024 cycle is the live, current adopted code for new permit applications outside these named exceptions.. Local amendments apply — see the Bennett overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bennett building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.