Bennett building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Bennett, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 207 Muegge Way, Bennett, CO 80102
- Phone
- 303-644-3249
- Office hours
- Main Town line 303-644-3249 (Building Department extension 1032 per the Building Permits page). Chief Building Official (Steve Jones, Charles Abbott Associates — Bennett's building department is staffed via a CAA contract) holds Drop-In Hours at Town Hall Tuesdays 12:30-1:30 p.m.; email bennettbuilding@bennett.co.us or stevejones@caa.inc to schedule a plan/project review meeting. Additional CAA inspection staff: Brad Jones 720-960-0576 (bradjones@caa.inc), Daniel Willman 720-361-9732 (danielwillman@caa.inc). Inspection requests must be received by 4:00 p.m. the business day before for next-day scheduling; inspections occur Monday-Friday, 7:00 a.m.-5:00 p.m., no specific-window guarantee.
- Website
- Official site
Published scheduling rules
- Using SolarAPP+ can materially speed up the code-compliance review step for a qualifying residential rooftop system, but you still apply for the permit, pay Town fees, and request inspections through Bennett's own SmartGov portal — SolarAPP+ replaces the plan-review step, not the whole permit process. (Rooftop Solar Photovoltaic (PV) Permit)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Bennett-Watkins Fire Rescue Final Inspection
Driveway dimensions, address signage visibility, road base, sprinklers if applicable — scheduled directly with BWFD (303-644-3572), separate from the Town Building Department's own inspections
- 5
Final Building Inspection
All work complete per approved plans and applicable codes; requested via the SmartGov portal by 4:00 p.m. the business day before
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation (detached ADU with new footings)
Before concrete pour
- 2
Framing
Structural framing complete, connection to existing structure (attached) or separation clearances (detached) verified
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment, including separate utility metering where required
- 4
Final Inspection
Egress, ventilation, sanitation, and structural requirements per IRC Appendix AQ verified
Applies to: Commercial Tenant Improvement / Core and Shell Permit
- 1
Rough Frame / MEP
Structural framing and mechanical/electrical/plumbing rough-ins before concealment
- 2
Bennett-Watkins Fire Rescue Inspection
Fire suppression, detection, water supply/cistern review specific to commercial occupancy, scheduled directly with BWFD
- 3
Final Inspection / Certificate of Occupancy
All work complete per approved plans and applicable codes
Applies to: Deck / Patio Cover / Carport Permit
- 1
Footing
Before concrete pour, footing depth and placement verified
- 2
Framing
Deck/patio cover framing, ledger attachment, guardrail posts before decking/roofing installed
- 3
Final Inspection
Guardrails, stair geometry, and structural connections verified
Applies to: Residential Addition / Interior Remodel Permit
- 1
Rough Frame / Structural (additions only)
Framing complete, connection to existing structure verified
- 2
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 3
Final Inspection
All work complete per approved plans
Applies to: Demolition Permit
- 1
Pre-Demolition Asbestos Verification
Confirms CDPHE asbestos determination/inspection is on file before demolition begins
- 2
Final Inspection
Site cleared, utilities disconnected/capped per Town requirements
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
Applies to: EV Charger / EVSE Installation Permit
- 1
Rough Electrical
Wiring, conduit runs, and disconnect placement before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Rooftop Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before cover
- 2
Final Inspection
Racking, roof penetrations, and electrical connections verified; requested through the SmartGov portal
Final inspection only: Furnace / Water Heater Replacement (Quick Permit), Re-Roof Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bennett building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Bennett building permits
Get alerts for Bennett
We'll email you when Bennett's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.