Inspection sequence, scheduling, and re-inspection fees for building permits in Bennett, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
207 Muegge Way, Bennett, CO 80102
Phone
303-644-3249
Office hours
Main Town line 303-644-3249 (Building Department extension 1032 per the Building Permits page). Chief Building Official (Steve Jones, Charles Abbott Associates — Bennett's building department is staffed via a CAA contract) holds Drop-In Hours at Town Hall Tuesdays 12:30-1:30 p.m.; email bennettbuilding@bennett.co.us or stevejones@caa.inc to schedule a plan/project review meeting. Additional CAA inspection staff: Brad Jones 720-960-0576 (bradjones@caa.inc), Daniel Willman 720-361-9732 (danielwillman@caa.inc). Inspection requests must be received by 4:00 p.m. the business day before for next-day scheduling; inspections occur Monday-Friday, 7:00 a.m.-5:00 p.m., no specific-window guarantee.

Published scheduling rules

  • Using SolarAPP+ can materially speed up the code-compliance review step for a qualifying residential rooftop system, but you still apply for the permit, pay Town fees, and request inspections through Bennett's own SmartGov portal — SolarAPP+ replaces the plan-review step, not the whole permit process. (Rooftop Solar Photovoltaic (PV) Permit)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Bennett-Watkins Fire Rescue Final Inspection

    Driveway dimensions, address signage visibility, road base, sprinklers if applicable — scheduled directly with BWFD (303-644-3572), separate from the Town Building Department's own inspections

  5. 5

    Final Building Inspection

    All work complete per approved plans and applicable codes; requested via the SmartGov portal by 4:00 p.m. the business day before

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation (detached ADU with new footings)

    Before concrete pour

  2. 2

    Framing

    Structural framing complete, connection to existing structure (attached) or separation clearances (detached) verified

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment, including separate utility metering where required

  4. 4

    Final Inspection

    Egress, ventilation, sanitation, and structural requirements per IRC Appendix AQ verified

Applies to: Commercial Tenant Improvement / Core and Shell Permit

  1. 1

    Rough Frame / MEP

    Structural framing and mechanical/electrical/plumbing rough-ins before concealment

  2. 2

    Bennett-Watkins Fire Rescue Inspection

    Fire suppression, detection, water supply/cistern review specific to commercial occupancy, scheduled directly with BWFD

  3. 3

    Final Inspection / Certificate of Occupancy

    All work complete per approved plans and applicable codes

Applies to: Deck / Patio Cover / Carport Permit

  1. 1

    Footing

    Before concrete pour, footing depth and placement verified

  2. 2

    Framing

    Deck/patio cover framing, ledger attachment, guardrail posts before decking/roofing installed

  3. 3

    Final Inspection

    Guardrails, stair geometry, and structural connections verified

Applies to: Residential Addition / Interior Remodel Permit

  1. 1

    Rough Frame / Structural (additions only)

    Framing complete, connection to existing structure verified

  2. 2

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  3. 3

    Final Inspection

    All work complete per approved plans

Applies to: Demolition Permit

  1. 1

    Pre-Demolition Asbestos Verification

    Confirms CDPHE asbestos determination/inspection is on file before demolition begins

  2. 2

    Final Inspection

    Site cleared, utilities disconnected/capped per Town requirements

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: EV Charger / EVSE Installation Permit

  1. 1

    Rough Electrical

    Wiring, conduit runs, and disconnect placement before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Rooftop Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified; requested through the SmartGov portal

Bennett building permits

Get alerts for Bennett

We'll email you when Bennett's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.