EV Charger / EVSE Installation Permit — Bennett, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.bennettco.gov/media/9226
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Installation Permit in Bennett, Colorado
Required for installation of a Level 2 (or higher) electric vehicle charging circuit in Bennett. Filed as a standard Electrical Permit — fees are 'Set by State' per the Colorado State Electrical Board (DORA/DPO) statewide schedule (CRS 12-23-117), but the Town of Bennett publishes its own real quick-permit minimum valuation specifically for EV chargers ($1,100) in its Permit Valuations guide, distinct from its other electrical minimum-valuation line items.
Verified 2026-07-20 · Source
When you need this permit
- Governed by the 2023 National Electrical Code (NEC) as in effect in Bennett
- Electrical permit fee itself is 'Set by State' per the Town's June 2026 Schedule of Fees — billed under the Colorado State Electrical Board's own statewide fee schedule
- Town of Bennett publishes a dedicated 'EV Charger' minimum valuation of $1,100 in its Permit Valuations (Quick Permit) guide — used as the minimum installation valuation for quick-permit processing; valuation increases if a panel/service upgrade is also needed (see the Town's separate Electrical service upgrade minimum valuations: $1,500 for 100-125 AMP, $2,500 for 150-200 AMP)
- Contractors must hold a current Colorado State Master Electric License and Colorado State Electrical Contractor License, plus a Town of Bennett Electrical Registration (no fee) Contractor
- The Town's 2026 code update adopts the Colorado Model Electric and Solar Ready Code effective July 1, 2026, the state's model EV-charging/solar-readiness code — new construction and major electrical work in Bennett going forward will be reviewed for EV-ready circuit provisions under this code
- Apply via the Town of Bennett SmartGov portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Wiring, conduit runs, and disconnect placement before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
See the full Bennett inspection guide — scheduling & re-inspection fees →
Tips
- Bennett is one of the few jurisdictions in this corpus with a real, published, EV-charger-specific minimum valuation ($1,100) — distinct from its general electrical service-upgrade valuations — even though the underlying permit fee itself is billed under the Colorado State Electrical Board's statewide schedule.
- If the EV charger installation also requires a panel/service upgrade, the higher of the EV charger valuation or the applicable service-upgrade valuation (or a contractor/owner-provided valuation, if higher) governs, per the Town's Permit Valuations guide.
- The Town's adoption of the Colorado Model Electric and Solar Ready Code (effective July 1, 2026) is the state's model EV-readiness code — relevant to new-construction electrical rough-in requirements, separate from this retrofit EV charger permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bennett building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bennett
EV Charger / EVSE Installation Permit in other cities
Compare ev charger / evse installation permit fees across Colorado →
Look up this fee in a different city →