Change of Use / Certificate of Occupancy in Bennett, Colorado
Bennett has no standalone change-of-use permit application, checklist or fee distinct from its ordinary zoning-compliance and Certificate of Occupancy processes — Chapter 16 Article II Division 3 (Site Plan, Permitted Uses, Conditional Uses, Temporary Uses, Planned Developments, Rezoning, Variances, Fair Housing Act Accommodations) contains nothing titled or scoped as one. Two concrete mechanisms do apply, though. Zoning Code Sec. 16-2-20(f) expressly names 'granting of a change in use', alongside a building permit, conditional use permit and site plan approval, as an action requiring the applicant to first demonstrate zoning compliance. And the Town publishes a detailed Certificate of Occupancy page with real submittal requirements and real processing times — up to 48 business hours residential and 72 business hours commercial — which is what actually authorizes new occupancy or a new use in practice.
Verified 2026-08-13 · Source
When you need this permit
- Municipal Code Sec. 16-2-20(f): 'Prior to issuance of a building permit, conditional use permit, site plan approval or granting of a change in use, the applicant shall demonstrate that the property will comply with all applicable provisions of this Chapter' (Ord. 646-14 §1(Exh. A), 12-9-2014; Ord. 742-22, §11, 6-14-2022) — this is the only place in the Town's Zoning Code where 'change in use' appears as its own named triggering action, and it folds the change-of-use scenario into the same up-front zoning-compliance-demonstration requirement used for building permits, conditional use permits, and site plan approvals, rather than creating its own separate permit type or fee
- A Certificate of Occupancy (CO) is required before any new residential or commercial building in Bennett can be legally used, per the Town's own live Certificate of Occupancy page (bennettco.gov/community-development/page/certificate-occupancy) — the CO confirms construction was completed per approved plans, all required inspections passed, and the structure meets zoning, building, safety, and health standards; the property may not be occupied until the CO is approved and issued
- To request a CO, applicants must submit the final Improvement Location Certificate (with grading and drainage), an inspection card with all final inspections signed off, and payment of any outstanding fees
- Commercial CO requests additionally require approvals from the Fire Department (Bennett-Watkins Fire Rescue — see the fire-sprinkler-alarm-permit entry), Engineering, and Planning, plus confirmation of a valid business license
- Residential CO requests may take up to 48 business hours to process once submitted; commercial CO requests may take up to 72 business hours — both figures are the Town's own published processing-time statements, not the usual reviewTimelineDays convention (see reviewTimelineNote)
- A separate Temporary Certificate of Occupancy (TCO) process exists for occupancy before all final conditions are met, with its own published flat fee ($500.00, $100.00 renewal — already documented in the residential-building-permit entry) and its own request form and procedures document
- Certain use changes may separately require a Conditional Use Permit under the Division 3 framework if the new use is classified as a conditional use (rather than a use by right) in the applicable zoning district — this is a distinct process from both the Sec. 16-2-20(f) compliance-demonstration trigger and the CO process, and is not itself documented as a standalone entry in this record
- If a change of use involves construction, remodeling, alteration, or a change in occupancy classification, the ordinary Town Building Permit process applies (see the residential-addition-remodel and commercial-tenant-improvement entries)
- Contact the Community Development/Building Department directly (bennettbuilding@bennett.co.us, 303-644-3249 ext. 1032) to confirm current practice for a specific change-of-use scenario, since no standalone process or fee for that exact scenario (independent of the CO and Sec. 16-2-20(f) mechanisms above) is published
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No standalone CO fee line item, separate from 'any outstanding fees' referenced generically on the Town's own CO page, was found in the June 24, 2026 Schedule of Fees — a standard CO issued on… Show full citationHide
No standalone CO fee line item, separate from 'any outstanding fees' referenced generically on the Town's own CO page, was found in the June 24, 2026 Schedule of Fees — a standard CO issued on completion of an already-permitted project appears to be included within the Building Permit Fee already paid, rather than carrying its own additional charge. Genuinely unpublished as a distinct line item, not an oversight.Sec. 16-2-20(f) requires a zoning-compliance demonstration before 'granting of a change in use' but does not itself establish a separate fee for that demonstration distinct from whatever underlying… Show full citationHide
Sec. 16-2-20(f) requires a zoning-compliance demonstration before 'granting of a change in use' but does not itself establish a separate fee for that demonstration distinct from whatever underlying permit (building permit, conditional use permit, site plan approval) the change actually requires.Review timeline
Inspection process
See the full Bennett inspection guide — scheduling & re-inspection fees →
Tips
- Bennett's Zoning Code has no dedicated 'change of use permit' section — Chapter 16 Article II Division 3 moves from Site Plan Requirement directly through Permitted Uses, Conditional Uses, Temporary Uses, Planned Developments, Rezoning, Variances, and Fair Housing Act Reasonable Accommodations, with 'change in use' appearing only as a triggering phrase inside Sec. 16-2-20(f)'s general zoning-compliance requirement, not as its own numbered section.
- In practice, what actually authorizes new occupancy or a changed use of an existing building in Bennett is the Certificate of Occupancy process — the Town's own live CO page is unusually concrete for a town this size, publishing real submittal requirements and real processing-time figures (up to 48 business hours residential, 72 business hours commercial) rather than staying silent on timing the way most of the other permitTypes must.
- If your project involves both a genuine change in use AND construction work, the construction side is unambiguously covered by the ordinary Town Building Permit (see residential-addition-remodel or commercial-tenant-improvement in this record); it is the standalone, construction-free change-of-use scenario specifically that has no dedicated Bennett process beyond the Sec. 16-2-20(f) compliance-demonstration requirement.
- Commercial Certificate of Occupancy requests pull in three additional Town/District reviewers beyond the Building Department itself — Bennett-Watkins Fire Rescue, Engineering, and Planning — plus confirmation of a valid business license; budget the full 72-business-hour window (not the 48-hour residential figure) for a commercial CO.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fee schedules
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bennett building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Bennett's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Bennett yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Bennett lands. Privacy.
Other permits in Bennett
Change of Use / Certificate of Occupancy in other cities
Compare change of use / certificate of occupancy fees across Colorado →
Look up this fee in a different city →