Demolition Permit — Aspen, Colorado · Requirements sheet
Verified 2026-07-23 · Source: https://www.aspen.gov/DocumentCenter/View/12171
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Aspen, Colorado
Required for demolition of any structure not being replaced with another structure, and separately gates any project meeting the City's residential demolition threshold (40% or more of existing exterior wall/roof surface area removed) before a building permit for redevelopment can be issued. Aspen caps qualifying residential demolition allotments at 6 per calendar year, first-come first-served, plus 2 additional allotments per year reserved for 35-year Aspen homeowners.
Verified 2026-07-23 · Source
When you need this permit
- 'Demolition' is defined as razing, disassembling, tearing down, or destroying 40% or more of a structure, measured by existing (pre-demolition) exterior wall (above finished grade) and roof surface area, excluding fenestration, compared against the same area proposed for removal
- A project meeting or exceeding this 40% threshold can only proceed to a building permit if a demolition allotment is available; allotments are capped at 6 per calendar year and awarded via LOTTERY (Council switched from first-come-first-served to a lottery system at the end of 2023, per Aspen Daily News reporting — confirmed 2026-07-23, since the City's own PDFs don't restate the award mechanism), with 2 additional allotments per year for applicants who have owned their Aspen home for at least 35 years
- Approved demolition allotments are valid for 3 years, within which the project must submit for both the demolition and the building permit
- Redevelopment following a qualifying demolition must meet residential redevelopment standards: minimum 35% by weight non-hazardous waste diversion from landfill, carbon-usage reporting for the building process/materials and projected future energy use, and design/construction readiness for future 100% electric conversion plus on-site PV/battery storage accommodation
- Projects over 2,000 sq ft affecting square footage and/or triggering demolition additionally require a Construction Waste Diversion Plan
- Contact the Building Department directly for restrictions associated with this permit type before selecting it, per the City's Permit Types & Triggers document
- Only applications deemed 'complete' under the Land Use Code enter the queue for a demolition allotment
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection
Site clear and safe per approved demolition scope
See the full Aspen inspection guide — scheduling & re-inspection fees →
Tips
- Aspen caps qualifying residential demolitions (40%+ of exterior wall/roof surface area) at just 6 allotments per calendar year, awarded by LOTTERY since a Council-directed switch took effect at the end of 2023 (previously first-come, first-served) — this is a hard scarcity gate, not a paperwork formality, and can be the actual bottleneck on a teardown-rebuild project rather than plan review itself.
- If you've owned your Aspen home for 35+ years, ask about the 2 additional reserved allotments per year set aside for long-tenured owners.
- An approved demolition allotment is only valid for 3 years — both the demolition and the building permit must be submitted within that window or the allotment lapses.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aspen building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Aspen
Demolition Permit in other cities
Compare demolition permit fees across Colorado →