Required for demolition of any structure not being replaced with another structure, and separately gates any project meeting the City's residential demolition threshold (40% or more of existing exterior wall/roof surface area removed) before a building permit for redevelopment can be issued. Aspen caps qualifying residential demolition allotments at 6 per calendar year, first-come first-served, plus 2 additional allotments per year reserved for 35-year Aspen homeowners.

Verified 2026-07-23 · Source

When you need this permit

  • 'Demolition' is defined as razing, disassembling, tearing down, or destroying 40% or more of a structure, measured by existing (pre-demolition) exterior wall (above finished grade) and roof surface area, excluding fenestration, compared against the same area proposed for removal
  • A project meeting or exceeding this 40% threshold can only proceed to a building permit if a demolition allotment is available; allotments are capped at 6 per calendar year and awarded via LOTTERY (Council switched from first-come-first-served to a lottery system at the end of 2023, per Aspen Daily News reporting — confirmed 2026-07-23, since the City's own PDFs don't restate the award mechanism), with 2 additional allotments per year for applicants who have owned their Aspen home for at least 35 years
  • Approved demolition allotments are valid for 3 years, within which the project must submit for both the demolition and the building permit
  • Redevelopment following a qualifying demolition must meet residential redevelopment standards: minimum 35% by weight non-hazardous waste diversion from landfill, carbon-usage reporting for the building process/materials and projected future energy use, and design/construction readiness for future 100% electric conversion plus on-site PV/battery storage accommodation
  • Projects over 2,000 sq ft affecting square footage and/or triggering demolition additionally require a Construction Waste Diversion Plan
  • Contact the Building Department directly for restrictions associated with this permit type before selecting it, per the City's Permit Types & Triggers document
  • Only applications deemed 'complete' under the Land Use Code enter the queue for a demolition allotment

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition Permit FeeNo static percentage-based fee table published as plain text; note that per the City's Permit Types & Triggers document, Demolition/IFFR/Repair/Change Orders/Temporary Structure permits are excluded from standard submittal fees
Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2)

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Aspen?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Site clear and safe per approved demolition scope

See the full Aspen inspection guide — scheduling & re-inspection fees →

Tips

  • Aspen caps qualifying residential demolitions (40%+ of exterior wall/roof surface area) at just 6 allotments per calendar year, awarded by LOTTERY since a Council-directed switch took effect at the end of 2023 (previously first-come, first-served) — this is a hard scarcity gate, not a paperwork formality, and can be the actual bottleneck on a teardown-rebuild project rather than plan review itself.
  • If you've owned your Aspen home for 35+ years, ask about the 2 additional reserved allotments per year set aside for long-tenured owners.
  • An approved demolition allotment is only valid for 3 years — both the demolition and the building permit must be submitted within that window or the allotment lapses.

Frequently asked questions

Aspen requires a demolition permit for: 'Demolition' is defined as razing, disassembling, tearing down, or destroying 40% or more of a structure, measured by existing (pre-demolition) exterior wall (above finished grade) and roof surface area, excluding fenestration, compared against the same area proposed for removal; A project meeting or exceeding this 40% threshold can only proceed to a building permit if a demolition allotment is available; allotments are capped at 6 per calendar year and awarded via LOTTERY (Council switched from first-come-first-served to a lottery system at the end of 2023, per Aspen Daily News reporting — confirmed 2026-07-23, since the City's own PDFs don't restate the award mechanism), with 2 additional allotments per year for applicants who have owned their Aspen home for at least 35 years; Approved demolition allotments are valid for 3 years, within which the project must submit for both the demolition and the building permit; Redevelopment following a qualifying demolition must meet residential redevelopment standards: minimum 35% by weight non-hazardous waste diversion from landfill, carbon-usage reporting for the building process/materials and projected future energy use, and design/construction readiness for future 100% electric conversion plus on-site PV/battery storage accommodation; Projects over 2,000 sq ft affecting square footage and/or triggering demolition additionally require a Construction Waste Diversion Plan; Contact the Building Department directly for restrictions associated with this permit type before selecting it, per the City's Permit Types & Triggers document; Only applications deemed 'complete' under the Land Use Code enter the queue for a demolition allotment. If your project isn't listed, confirm with City of Aspen Community Development Department, Building Division at 970-920-5000 before starting work.

In Aspen, the published Demolition Permit Fee is: Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Aspen does not publish a plan-review timeline for this permit. Contact City of Aspen Community Development Department, Building Division at 970-920-5000 for current turnaround.

You'll need: Demolition Permit Application (Salesforce Permit Portal); Demolition Percentage Calculation. Depending on your project, Aspen may also ask for: Construction Waste Diversion Plan. See the required-documents checklist on this page for details on each.

Aspen requires 1 inspection(s) for a demolition permit, in order: Final Inspection. Schedule each through City of Aspen Community Development Department, Building Division (970-920-5000).

Apply through City of Aspen Community Development Department, Building Division at 427 Rio Grande Place, Aspen, CO 81611. Phone: 970-920-5000, email: buildingsupport@aspen.gov. Office hours: City of Aspen main line 970-920-5000. Building Support (permit requirement inquiries, pre-submittal questions): buildingsupport@aspen.gov, Monday-Friday 9:00am-5:00pm. Builder of the Day (building code/regulations questions): builderoftheday@aspen.gov, 970-429-2735, Monday-Friday 8:30am-4:30pm. Planner of the Day (zoning, floor area, net leasable, signage, mountain view plane, exterior design): planneroftheday@aspen.gov, 970-429-2764, walk-in hours Monday-Friday 9:00am-12:00pm. Historic Preservation: HP@aspen.gov, 970-429-2758. Construction hours: Monday-Friday 7:30am-5:30pm, Saturday 9:00am-5:00pm, no construction on Sundays.. Official information: https://aspen.gov/179/Building.

Residential demolitions meeting the City's 40%-or-more exterior surface area threshold are capped at 6 allotments per calendar year, plus 2 additional allotments per year reserved for applicants who have owned their Aspen home for at least 35 years. Allotments are awarded by lottery — Council switched from a first-come, first-served process to a lottery at the end of 2023.