Commercial Tenant Improvement / Tenant Finish Permit in Aspen, Colorado

Required for tenant finishes and interior alterations of commercial spaces in Aspen — a genuinely distinct, heavily documented track given downtown retail/restaurant turnover. The City maintains a dedicated Tenant Finish Cheatsheet (Building, Updated 4/14/2026) and a dedicated Tenant Finish Guide for Planning & Historic Preservation (Updated 5/1/2026). There is no separately named 'TI permit' — tenant finishes are building permits classified as New Mini or New Minor permits by scope, and qualifying commercial-zone interior/minor-exterior alterations can run through the EPIC (Expedited Permits in Commercial Zones) program with its own published 4-5 week Round-1 SLA.

Verified 2026-08-02 · Source

When you need this permit

  • Work may only be performed by a contractor licensed with the City of Aspen as a light commercial or unlimited contractor; on historic properties the GC must also hold the City's Historic Preservation contractor certification (Tenant Finish Cheatsheet, Updated 4/14/2026) Contractor
  • Asbestos: regardless of building age, removing the volume equivalent of a 55-gallon drum of any material besides concrete, wood, brick, or steel triggers a required asbestos test; if asbestos is found and will be disturbed, a final air clearance abatement report is required before permit issuance
  • Occupant load and means of egress must be calculated (IBC Chapter 10) and shown on plans with exit access travel distances; restaurants count occupant load by seating and must delineate 36-inch clear egress paths
  • Accessibility: all new or altered construction must be accessible; alterations within the space of primary function additionally require an accessible entrance, accessible route, accessible toilet facilities, and accessible drinking fountain, with an exception where those upgrades would exceed 20% of the total project budget (construction estimates required to claim it)
  • Fire/sound resistance: all fire- and sound-rated assemblies must be labeled on plans referencing listed and tested assemblies; disturbing more than 32 sq ft of drywall in a required fire-rated assembly triggers bringing it up to current code; penetrations of rated assemblies must be protected; dropped ceilings below rated horizontal assemblies must be non-combustible or fire-retardant-treated framing
  • Interior lighting changes require lighting plans, fixture cutsheets, and an Interior Lighting COMcheck complying with the 2021 Aspen Energy Code (C405.2 controls); on a change of use, a lighting plan and COMcheck are required even with no lighting changes
  • Structural plans (stamped) are required if any walls or potentially structural elements are altered, with a Special Inspection and Testing Agreement where the stamped plans call for items in IBC Sec. 1704; changes to interior walls require stamped plans or a stamped letter of structural engagement plus an asbestos test (within 1 year) if affecting more than 160 sq ft of potentially asbestos-containing materials (EPIC checklist)
  • Change of use (between Mercantile, Business, Assembly, Residential, Storage/parking use groups) triggers additional requirements: lighting COMcheck regardless of scope, required toilet-facility count compliance, and possibly an additional exit; a change between commercial, residential, or lodging uses also requires contacting the Planner of the Day and is a zoning/land-use matter
  • Restaurants: commercial kitchen plans must show all equipment, sinks, and drains, with Type I/II hood design, PCU for charbroilers (90% PM10 filtration per the EPIC checklist), mechanical ventilation and make-up air calculations, grease trap, and equipment schedule; new food establishments or ownership changes also need a Retail Food Establishment license (foodsafety@aspen.gov)
  • EPIC eligibility (Updated 4.16.26 policy): commercial use in a commercial zone district; interior and/or minor exterior alterations only; NO change in use, NO change in net leasable space or floor area, NO rooftop changes within the foreground of a mountain view plane, NO outdoor lighting or signage changes in scope; building must have a Letter of Completion; work without a permit or a red tag disqualifies the project; Change Orders to an EPIC permit are not expedited
  • Changes to demising walls or vertical circulation (elevators, stairs, dumbwaiters) are excluded from EPIC and may impact net leasable space or floor-area allocation — the Planning & HP Tenant Finish Guide directs applicants to the Planning Permit Review Team before submitting because a land use review may be required
  • Signage may NOT be included in a tenant-finish building permit — all signage requires a separate sign permit (published Round-1 SLA: 3-4 weeks); exterior lighting changes are likewise excluded from EPIC scope and go in a non-EPIC building permit or standalone electrical permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Submittal FeePer aspen.gov/236; in the EPIC track, Building Support makes submittal fees available after completeness review, and paying them triggers scheduling of the virtual EPIC review meeting
Assessed once the application is deemed complete; payment starts the review clock
Building Permit Fee + Plan Review (valuation-based)No static percentage-based fee table published as plain text on Building Department web pages; no TI-specific fee line item exists — tenant finishes are fee'd as building permits on CBO-verified valuation
Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2)

Review timeline

Plan reviewAspen’s published plan-review target
21–70 business days

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Aspen?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment; fire-resistive penetration protection (dampers, fire caulk, rated enclosures) verified before cover

  2. 2

    Framing / Fire-Rated Assembly

    Interior framing and fire/sound-rated assembly installation per the listed and tested assemblies referenced on the approved plans, before drywall

  3. 3

    Final Inspection

    All work complete per approved plans; scheduled via the Salesforce Permit Portal (requests by 7:30 PM are scheduled next business day, site ready by 9:00 AM); fire and sanitation inspections coordinated separately

See the full Aspen inspection guide — scheduling & re-inspection fees →

Tips

  • If your project is interior-only in a commercial zone with no change of use, net leasable, or floor area — and the building has its Letter of Completion — pursue the EPIC track: one virtual meeting with every review agency and comments closed within 24 hours of that meeting, with a published 4-5 week Round-1 SLA and priority 'EPIC' queue designation on resubmittals.
  • Aspen's legacy Tenant Finish guide (2/22/2014 edition, still hosted) states commercial drawings must be stamped by a licensed architect per the Colorado Revised Statutes, with possible exemption for minor work and a stamp always required for never-occupied whitebox space; the current 4/14/2026 cheatsheet no longer restates the blanket architect-stamp line but does require stamped structural plans for any wall/structural alterations — confirm current stamp expectations with the Builder of the Day (builderoftheday@aspen.gov, 970-429-2735) for your specific scope.
  • The 55-gallon-drum asbestos threshold applies regardless of building age or how recently the space was remodeled — budget for the test on virtually any real demolition of finishes.
  • Accessibility upgrades to the entrance, route, and toilets are capped at 20% of total project budget — document construction estimates for both the base scope and the accessibility scope to claim the exception.
  • Restaurants layer on the most requirements: seating-count occupant loads, Type I/II hood design, PCU for charbroilers, grease trap, make-up air calcs, plus a separate Retail Food Establishment license for new establishments or ownership changes.
  • Signs and exterior lighting can never ride along in a tenant-finish permit — signs need their own sign permit (3-4 week published SLA) and exterior lighting goes in a non-EPIC building permit or standalone electrical permit.
  • Touching demising walls, stairs, or elevators? Talk to the Planning Permit Review Team first — those changes can shift net leasable space and trigger a land use review that no building-permit timeline accounts for.

Frequently asked questions

Aspen requires a commercial tenant improvement / tenant finish permit for: Work may only be performed by a contractor licensed with the City of Aspen as a light commercial or unlimited contractor; on historic properties the GC must also hold the City's Historic Preservation contractor certification (Tenant Finish Cheatsheet, Updated 4/14/2026); Asbestos: regardless of building age, removing the volume equivalent of a 55-gallon drum of any material besides concrete, wood, brick, or steel triggers a required asbestos test; if asbestos is found and will be disturbed, a final air clearance abatement report is required before permit issuance; Occupant load and means of egress must be calculated (IBC Chapter 10) and shown on plans with exit access travel distances; restaurants count occupant load by seating and must delineate 36-inch clear egress paths; Accessibility: all new or altered construction must be accessible; alterations within the space of primary function additionally require an accessible entrance, accessible route, accessible toilet facilities, and accessible drinking fountain, with an exception where those upgrades would exceed 20% of the total project budget (construction estimates required to claim it); Fire/sound resistance: all fire- and sound-rated assemblies must be labeled on plans referencing listed and tested assemblies; disturbing more than 32 sq ft of drywall in a required fire-rated assembly triggers bringing it up to current code; penetrations of rated assemblies must be protected; dropped ceilings below rated horizontal assemblies must be non-combustible or fire-retardant-treated framing; Interior lighting changes require lighting plans, fixture cutsheets, and an Interior Lighting COMcheck complying with the 2021 Aspen Energy Code (C405.2 controls); on a change of use, a lighting plan and COMcheck are required even with no lighting changes; Structural plans (stamped) are required if any walls or potentially structural elements are altered, with a Special Inspection and Testing Agreement where the stamped plans call for items in IBC Sec. 1704; changes to interior walls require stamped plans or a stamped letter of structural engagement plus an asbestos test (within 1 year) if affecting more than 160 sq ft of potentially asbestos-containing materials (EPIC checklist); Change of use (between Mercantile, Business, Assembly, Residential, Storage/parking use groups) triggers additional requirements: lighting COMcheck regardless of scope, required toilet-facility count compliance, and possibly an additional exit; a change between commercial, residential, or lodging uses also requires contacting the Planner of the Day and is a zoning/land-use matter; Restaurants: commercial kitchen plans must show all equipment, sinks, and drains, with Type I/II hood design, PCU for charbroilers (90% PM10 filtration per the EPIC checklist), mechanical ventilation and make-up air calculations, grease trap, and equipment schedule; new food establishments or ownership changes also need a Retail Food Establishment license (foodsafety@aspen.gov); EPIC eligibility (Updated 4.16.26 policy): commercial use in a commercial zone district; interior and/or minor exterior alterations only; NO change in use, NO change in net leasable space or floor area, NO rooftop changes within the foreground of a mountain view plane, NO outdoor lighting or signage changes in scope; building must have a Letter of Completion; work without a permit or a red tag disqualifies the project; Change Orders to an EPIC permit are not expedited; Changes to demising walls or vertical circulation (elevators, stairs, dumbwaiters) are excluded from EPIC and may impact net leasable space or floor-area allocation — the Planning & HP Tenant Finish Guide directs applicants to the Planning Permit Review Team before submitting because a land use review may be required; Signage may NOT be included in a tenant-finish building permit — all signage requires a separate sign permit (published Round-1 SLA: 3-4 weeks); exterior lighting changes are likewise excluded from EPIC scope and go in a non-EPIC building permit or standalone electrical permit. If your project isn't listed, confirm with City of Aspen Community Development Department, Building Division at 970-920-5000 before starting work.

In Aspen, the published Submittal Fee is: Assessed once the application is deemed complete; payment starts the review clock. Additional published fees: Building Permit Fee + Plan Review (valuation-based) — Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Aspen's published plan-review target for a commercial tenant improvement / tenant finish permit is 21–70 business days.

You'll need: Tenant Finish Cheatsheet (Building Department); Tenant Finish Guide for Planning & Historic Preservation; Building Permit Application Checklist for Commercial and Multifamily Projects (2021 IBC) — Alteration columns; Permit Application Signature Packet; Construction Management Plan (CMP). Depending on your project, Aspen may also ask for: EPIC questionnaire + completed EPIC checklist. See the required-documents checklist on this page for details on each.

Apply through City of Aspen Community Development Department, Building Division at 427 Rio Grande Place, Aspen, CO 81611. Phone: 970-920-5000, email: buildingsupport@aspen.gov. Office hours: City of Aspen main line 970-920-5000. Building Support (permit requirement inquiries, pre-submittal questions): buildingsupport@aspen.gov, Monday-Friday 9:00am-5:00pm. Builder of the Day (building code/regulations questions): builderoftheday@aspen.gov, 970-429-2735, Monday-Friday 8:30am-4:30pm. Planner of the Day (zoning, floor area, net leasable, signage, mountain view plane, exterior design): planneroftheday@aspen.gov, 970-429-2764, walk-in hours Monday-Friday 9:00am-12:00pm. Historic Preservation: HP@aspen.gov, 970-429-2758. Construction hours: Monday-Friday 7:30am-5:30pm, Saturday 9:00am-5:00pm, no construction on Sundays.. Official information: https://aspen.gov/179/Building.

Not by that name — tenant finishes are building permits classified by scope as New Mini Permits (3-4 week published Round-1 review) or New Minor Permits (8-10 weeks), and qualifying interior/minor-exterior commercial-zone alterations can use the EPIC expedited program (4-5 weeks, with all review agencies issuing comments within 24 hours of a single virtual review meeting). The City publishes dedicated Tenant Finish guidance from both its Building Department (cheatsheet updated 4/14/2026) and its Planning & Historic Preservation staff (guide updated 5/1/2026).

Per the EPIC policy (updated 4/16/2026): any change in use between commercial, residential, or lodging; any change in net leasable space or floor area; rooftop changes within the foreground of a mountain view plane; outdoor lighting or signage in the scope; a building without a Letter of Completion; prior work without a permit or a stop-work/red tag; and Change Orders to an existing EPIC permit. Historic properties are limited to like-for-like exterior repairs, mechanical/ventilation upgrades without impact to character-defining elements, and accessibility improvements.

If the previous tenant was a different IBC use group (Mercantile, Business, Assembly, Residential, Storage/parking), you are changing the use: a lighting plan and COMcheck are required even with no lighting changes, toilet-facility counts must be brought up to requirement, and an additional exit may be required for a higher occupant load. A change between commercial, residential, or lodging uses is also a zoning matter requiring the Planner of the Day, and it disqualifies the project from EPIC.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Aspen.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Aspen's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Aspen yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Aspen lands. Privacy.