Fence Permit in Aspen, Colorado

Required for construction of a fence, constructed barrier, or berm in Aspen. Governed by Aspen Municipal Code Sec. 26.575.050 (allowed materials) and Sec. 26.575.e.5.q (height limits), plus the 2024 Colorado Wildfire Resiliency Code's noncombustible/ignition-resistant material requirements near structures.

Verified 2026-07-23 · Source

When you need this permit

  • Allowed fence materials per Sec. 26.575.050: metal, masonry, stone, and wood
  • Wildfire Resiliency Code requirement: fences within 8 feet of a structure must be constructed of noncombustible or ignition-resistant materials; hedges within 5 feet of a structure must use ignition-resistant vegetation
  • Maximum fence/hedge height per Sec. 26.575.e.5.q, measured from finished grade: up to 42 inches generally, or up to 6 feet in areas entirely recessed behind the vertical plane of the building facade closest to the street (applies on all street-facing facades of a parcel)
  • If the property is historically designated, a signed Certificate of No Negative Effect is required (contact Historic Preservation staff)
  • Signed Homeowner Association Compliance form required
  • Improvement Survey with an original wet stamp/signature showing property lines, all easements/rights-of-way, all existing structures/improvements/fences, and location/trunk diameter/species of all trees is required; if a tree's critical root zone will be impacted, Parks Department approval and a separate permit are required
  • Elevation drawings showing design, dimensions, and materials of the proposed fence required
  • Reach out to Engineering if a fence is proposed within an easement or right-of-way

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fence Permit FeeNo static percentage-based fee table published as plain text on Building Department web pages reviewed for this file
Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2)

Review timeline

Plan reviewAspen’s published plan-review target
7–14 business days

How long did your Fence Permit permit actually take in Aspen?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Fence height, material, and setback compliance verified

See the full Aspen inspection guide — scheduling & re-inspection fees →

Tips

  • Fences within 8 feet of a structure must now use noncombustible or ignition-resistant materials under the 2024 Colorado Wildfire Resiliency Code (adopted by Aspen Ordinance 6, 2026, effective April 23, 2026) — a newer requirement layered on top of the pre-existing materials list in Sec. 26.575.050.
  • If any tree's critical root zone will be impacted by fence construction, a separate Parks Department approval and permit are required in addition to the fence permit itself.

Frequently asked questions

Aspen requires a fence permit for: Allowed fence materials per Sec. 26.575.050: metal, masonry, stone, and wood; Wildfire Resiliency Code requirement: fences within 8 feet of a structure must be constructed of noncombustible or ignition-resistant materials; hedges within 5 feet of a structure must use ignition-resistant vegetation; Maximum fence/hedge height per Sec. 26.575.e.5.q, measured from finished grade: up to 42 inches generally, or up to 6 feet in areas entirely recessed behind the vertical plane of the building facade closest to the street (applies on all street-facing facades of a parcel); If the property is historically designated, a signed Certificate of No Negative Effect is required (contact Historic Preservation staff); Signed Homeowner Association Compliance form required; Improvement Survey with an original wet stamp/signature showing property lines, all easements/rights-of-way, all existing structures/improvements/fences, and location/trunk diameter/species of all trees is required; if a tree's critical root zone will be impacted, Parks Department approval and a separate permit are required; Elevation drawings showing design, dimensions, and materials of the proposed fence required; Reach out to Engineering if a fence is proposed within an easement or right-of-way. If your project isn't listed, confirm with City of Aspen Community Development Department, Building Division at 970-920-5000 before starting work.

In Aspen, the published Fence Permit Fee is: Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Aspen's published plan-review target for a fence permit is 7–14 business days.

You'll need: Fence Permit Application Checklist; Improvement Survey (wet-stamped); Elevation Drawings; Homeowner Association Compliance Form. Depending on your project, Aspen may also ask for: Certificate of No Negative Effect. See the required-documents checklist on this page for details on each.

Aspen requires 1 inspection(s) for a fence permit, in order: Final Inspection. Schedule each through City of Aspen Community Development Department, Building Division (970-920-5000).

Apply through City of Aspen Community Development Department, Building Division at 427 Rio Grande Place, Aspen, CO 81611. Phone: 970-920-5000, email: buildingsupport@aspen.gov. Office hours: City of Aspen main line 970-920-5000. Building Support (permit requirement inquiries, pre-submittal questions): buildingsupport@aspen.gov, Monday-Friday 9:00am-5:00pm. Builder of the Day (building code/regulations questions): builderoftheday@aspen.gov, 970-429-2735, Monday-Friday 8:30am-4:30pm. Planner of the Day (zoning, floor area, net leasable, signage, mountain view plane, exterior design): planneroftheday@aspen.gov, 970-429-2764, walk-in hours Monday-Friday 9:00am-12:00pm. Historic Preservation: HP@aspen.gov, 970-429-2758. Construction hours: Monday-Friday 7:30am-5:30pm, Saturday 9:00am-5:00pm, no construction on Sundays.. Official information: https://aspen.gov/179/Building.

Aspen, Colorado has adopted: 2021 International Building Code (IBC) — adopted by Ordinance #1, 2023 (January 24, 2023), effective for permits submitted March 31, 2023 and later; the IRC has NOT been adopted by the City of Aspen and is not applied — single-family, duplex, and townhouse projects are reviewed under the 2021 IBC as locally amended, per the City's own 'Building Permit Application Checklist for Singlefamily, Duplex, and Townhouse Projects (2021 IBC)'; 2021 International Existing Building Code (IEBC); 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC); 2021 International Plumbing Code (IPC); 2021 International Fire Code (IFC); 2021 International Swimming Pool and Spa Code (ISPSC); 2021 Aspen Energy Code (local amendment/supplement to the IECC); 2023 National Electrical Code (NEC), effective August 1, 2023; 2024 Colorado Wildfire Resiliency Code with local amendments — adopted by Ordinance 6, 2026 (March 25, 2026), effective April 23, 2026; referenced directly in the current Fence Permit Application Checklist (fences within 8 feet of a structure must be noncombustible/ignition-resistant; hedges within 5 feet must use ignition-resistant vegetation); Prior code cycle: 2015-edition IBC/IEBC/IMC/IFGC/IPC/IFC applied to permits submitted between February 2017 and March 2023, with local amendments in Ordinance 40, 2016 (superseded, listed for reference only); Local amendments to all adopted codes are codified in Title 8 (Building and Building Regulations) of the Aspen Municipal Code; Municode's Aspen library is a JavaScript-rendered application that could not be scraped directly in this or the prior session (confirmed again 2026-07-23: raw curl returns only the Angular SPA shell, and the shared browser environment used for the re-chase attempt this session was too unstable to reliably render deep-linked Title pages). However, the City's own 'Currently Adopted Building & Energy Codes' page (aspen.gov/197) directly publishes a 'Climate & Geographical Design Criteria' table (2026-07-23, live-confirmed): Ground snow load 100 psf; Wind Speed/Exposure Category 89 mph / B; Seismic Design Category C; Weathering Severe; Frost line depth 36 inches; Termite None to slight; Decay None to slight; Winter design temp -15°F; Summer design temp 82°F; Ice shield underlayment required Yes; Air Freezing Index 2000; Mean annual temperature 40°F. This resolves the design-criteria gap without needing Title 8/Municode.. Local amendments apply — see the Aspen overview page for the full list.

Generally up to 42 inches measured from finished grade, or up to 6 feet in areas entirely recessed behind the vertical plane established by the portion of the building facade closest to the street, per Aspen Municipal Code Sec. 26.575.e.5.q.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aspen building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.