Englewood building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Englewood, Colorado.
Verified 2026-07-19 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 1000 Englewood Parkway, 3rd Floor, Englewood, CO 80110
- Phone
- 303-762-2357 (Building Department main line); 303-762-2356
- Office hours
- Monday through Friday, 8:00 a.m. to 5:00 p.m. (holidays excepted) — per the City's general Contact Us / Business Hours page (englewoodco.gov/our-city/contact-us); no Building & Codes Division-specific hours are separately published, so this is City Hall's general business hours as of verification.
- Website
- Official site
Published scheduling rules
- The Solar Energy Resources page reports 719 residential solar PV permits issued since 2015 and an average residential solar inspection turnaround of 24 hours — that 24-hour figure describes inspection scheduling/turnaround, not the 5-business-day plan-review/issuance commitment, and the two should not be conflated. (Solar PV Permit (Rooftop))
Inspection sequence
Applies to: Building Permit
- 1
Rough Inspection
Per the City's Inspections page — rough-in inspections occur before work is covered/concealed; approval status ('approved' or 'partial inspection only') is tracked in the applicant's iMS account.
- 2
Special Inspection
Required for certain structural/technical elements per the adopted 2024 IBC, as determined by the plans examiner or building official.
- 3
Final Inspection
Final inspection prior to closing out the permit / issuing a Certificate of Occupancy.
Applies to: EV Charger / EVSE Permit (Billed as General Building Permit)
- 1
Rough Inspection
Charger circuit wiring verified before concealment, if applicable
- 2
Final Inspection
EVSE installed, GFCI/disconnect and connections verified per 2023 NEC Article 625
Applies to: Residential Re-Roof Permit
- 1
Mid-Roof Inspection
Tied to the Mid-Roof Compliance Form required since July 1, 2024, for all one- and two-family residential re-roofs.
- 2
Final Inspection
Final roofing inspection prior to permit close-out.
Final inspection only: Fence Permit, Solar PV Permit (Rooftop)
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Englewood building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Englewood building permits
Get alerts for Englewood
We'll email you when Englewood's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.