Inspection sequence, scheduling, and re-inspection fees for building permits in Englewood, Colorado.

Verified 2026-07-19 · Source

How to schedule

Inspections are requested through the building department below.

Address
1000 Englewood Parkway, 3rd Floor, Englewood, CO 80110
Phone
303-762-2357 (Building Department main line); 303-762-2356
Office hours
Monday through Friday, 8:00 a.m. to 5:00 p.m. (holidays excepted) — per the City's general Contact Us / Business Hours page (englewoodco.gov/our-city/contact-us); no Building & Codes Division-specific hours are separately published, so this is City Hall's general business hours as of verification.

Published scheduling rules

  • The Solar Energy Resources page reports 719 residential solar PV permits issued since 2015 and an average residential solar inspection turnaround of 24 hours — that 24-hour figure describes inspection scheduling/turnaround, not the 5-business-day plan-review/issuance commitment, and the two should not be conflated. (Solar PV Permit (Rooftop))

Inspection sequence

Applies to: Building Permit

  1. 1

    Rough Inspection

    Per the City's Inspections page — rough-in inspections occur before work is covered/concealed; approval status ('approved' or 'partial inspection only') is tracked in the applicant's iMS account.

  2. 2

    Special Inspection

    Required for certain structural/technical elements per the adopted 2024 IBC, as determined by the plans examiner or building official.

  3. 3

    Final Inspection

    Final inspection prior to closing out the permit / issuing a Certificate of Occupancy.

Applies to: EV Charger / EVSE Permit (Billed as General Building Permit)

  1. 1

    Rough Inspection

    Charger circuit wiring verified before concealment, if applicable

  2. 2

    Final Inspection

    EVSE installed, GFCI/disconnect and connections verified per 2023 NEC Article 625

Applies to: Residential Re-Roof Permit

  1. 1

    Mid-Roof Inspection

    Tied to the Mid-Roof Compliance Form required since July 1, 2024, for all one- and two-family residential re-roofs.

  2. 2

    Final Inspection

    Final roofing inspection prior to permit close-out.

Final inspection only: Fence Permit, Solar PV Permit (Rooftop)

Re-inspection fees

Building PermitRe-inspection · 2026 Building Permit Fee Schedule.
$100 per hour
EV Charger / EVSE Permit (Billed as General Building Permit)Re-inspection · 2026 Building Permit Fee Schedule
$100 per hour

Englewood building permits

Get alerts for Englewood

We'll email you when Englewood's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.