Wheat Ridge building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Wheat Ridge, Colorado.

Verified 2026-07-05 · Source

How to schedule

Inspections are requested through the building department below.

Address
7500 W. 29th Ave., 2nd Floor, Wheat Ridge, CO 80033
Phone
303-235-2855 (Option 1: Building Permits & Contractor Licensing; Option 2: Inspections; Option 4: Plan Review); General City phone 303-234-5900
Office hours
Walk-in hours Monday-Friday, 9:00 a.m.-3:30 p.m.; service also available by appointment or phone/email starting at 7:30 a.m. Inspection request windows: AM inspections typically 8 a.m.-noon, PM typically noon-3 p.m., with a 2-hour window given on inspection day.

Published scheduling rules

  • Same-day inspections are available (11 a.m. cutoff, $170 fee); routine building inspections need only next-day notice (by 4 p.m.), but zoning/engineering inspections require up to a week's advance notice — plan trade-specific inspection requests accordingly. (General)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour, for new ADU construction

  2. 2

    Framing

    Framing complete; fire separation/fire-rated wall verified for attached ADUs where required

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete, fire-access/sprinkler and occupancy compliance confirmed

Applies to: Commercial Building Permit (New Construction / Shell)

  1. 1

    Footing/Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans and applicable code; may be paired with special-district sign-off where applicable

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour, for new footings/foundations

  2. 2

    Framing

    Framing and connection to existing structure before cover

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing/Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans and applicable code

Applies to: Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing/Demising Walls

    Interior framing and demising wall/fire separation before cover, where applicable

  2. 2

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment

  3. 3

    Final Inspection

    All work complete per approved plans and applicable code

Applies to: Electric Vehicle Charger Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Charging equipment installed and energized, circuit/receptacle verified per NEC

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed, before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: Fire Sprinkler & Fire Alarm Permit

  1. 1

    Acceptance Testing

    All system components must be fully tested by the contractor and ready for Acceptance Testing before the inspection is scheduled; required fire department and City/County permits must be available on-site

  2. 2

    Final Inspection

    Conducted by West Metro Fire Protection District; a $300-$360 re-inspection fee applies if the system fails or the inspection is a no-show

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork and equipment installed before concealment

  2. 2

    Final Inspection

    Equipment operational; combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified

Re-inspection fees

Electrical Permit
Re-inspection Fee · City of Wheat Ridge Permit Valuation & Fees page, Other Fees table — re-inspection at $85.00 per hour, one hour minimum. Show full citationRe-inspection Fee · City of Wheat Ridge Permit Valuation & Fees page, Other Fees table — re-inspection at $85.00 per hour, one hour minimum. The $60.00 late-cancellation charge is published on the City's Building Inspections page: cancellation requests must be received by 8 a.m. on the day of the scheduled inspection, and a later request is subject to a $60 re-inspection fee. It is not on the FAQ page, which carries no fee figures.
$85/hour, minimum 1 hour (City's Permit Valuation & Fees page); a separate $60 late-cancellation re-inspection fee is cited on the City's Building Inspections page for day-of cancellations after 8 a.m.
Roofing Permit (Reroof)Re-inspection Fee · City of Wheat Ridge Permit Valuation & Fees page, Other Fees table — re-inspection fee at $85.00 per hour, one hour minimum. Priced per the 2026 adopted budget.
$85/hour, minimum 1 hour
Fire Sprinkler & Fire Alarm Permit
Re-Inspection Fee · West Metro Fire Protection District Fees page lists $360.00; Show full citationRe-Inspection Fee · West Metro Fire Protection District Fees page lists $360.00; the District's separate Fire Alarms and Sprinkler Permitting and Testing page states a system-failure re-inspection fee of '$300.00' — both figures are published by the District and are documented here rather than picking one
$360.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-05.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wheat Ridge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Wheat Ridge building permits

Get alerts for Wheat Ridge

We'll email you when Wheat Ridge's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.