Accessory Dwelling Unit (ADU) Permit — Wheat Ridge, Colorado · Requirements sheet
Verified 2026-07-05 · Source: https://www.ci.wheatridge.co.us/1852/Accessory-Dwelling-Units
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Accessory Dwelling Unit (ADU) Permit in Wheat Ridge, Colorado
Required for construction of an ADU on a single-unit dwelling lot in Wheat Ridge. Legalized citywide by Ordinance 1744 (effective August 15, 2022); the underlying building permit follows the standard City of Wheat Ridge Building Permit process and fee schedule.
Verified 2026-07-05 · Source
When you need this permit
- ADUs allowed in all residential, agricultural, planned development, and mixed-use neighborhood zone districts as an accessory use to a single-unit home; NOT permitted on duplex or multi-unit properties
- Maximum size: 1,000 sq ft or 50% of the main house's gross floor area (including attached garage), whichever is more restrictive; units of 500-750 sq ft are always allowed provided they remain smaller than the main house; detached ADU footprint capped at 1,000 sq ft
- Height: detached ADUs capped at 25 feet; attached ADUs must follow the main house's height requirements
- ADUs cannot be subdivided or sold separately from the main house
- No additional off-street parking required for a standard ADU (short-term-rental use of an ADU triggers separate STR parking standards)
- All sides of a new ADU must be within 150 feet of an approved fire access road, or fire sprinklers may be required; attached ADUs require a fire-rated wall separation from the primary dwelling
- Existing (built before August 15, 2022) unpermitted ADUs have until August 15, 2026 to apply for legal status
- Governed by Ordinance 1744, approved July 11, 2022, effective August 15, 2022
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour, for new ADU construction
- 2
Framing
Framing complete; fire separation/fire-rated wall verified for attached ADUs where required
- 3
Rough Electrical/Plumbing/Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete, fire-access/sprinkler and occupancy compliance confirmed
See the full Wheat Ridge inspection guide — scheduling & re-inspection fees →
Tips
- Confirm your zone district allows ADUs and that your lot holds a single-unit (not duplex/multi-unit) dwelling before assuming eligibility.
- If your property is more than 150 feet from an approved fire access road, budget for a fire sprinkler system in the new ADU.
- If you already have an unpermitted ADU built before August 15, 2022, the City has set a firm August 15, 2026 deadline to apply for legal status — don't let this lapse.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wheat Ridge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Wheat Ridge
Accessory Dwelling Unit (ADU) Permit in other cities
Compare accessory dwelling unit (adu) permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Wheat Ridge project checklist
Describe your project once and get every permit, document, and fee it triggers in Wheat Ridge — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →