Accessory Dwelling Unit (ADU) Permit — Fort Collins, Colorado · Requirements sheet
Verified 2026-06-30 · Source: https://www.fortcollins.gov/Business/Building-and-Development/Development-Review/Accessory-Dwelling-Units-ADUs
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Accessory Dwelling Unit (ADU) Permit in Fort Collins, Colorado
Required for construction of a new attached or detached ADU in Fort Collins. Since February 2025, Colorado state law HB 24-1152 allows ADUs in all Fort Collins zone districts (previously limited to Old Town and select neighborhoods), and prohibits owner-occupancy requirements — ADUs may be rented out separately from the primary home. Fort Collins is home to Colorado State University, making ADUs relevant for rental/student housing demand. All ADUs require a mandatory Basic Development Review before a building permit.
Verified 2026-06-30 · Source
When you need this permit
- No new units allowed in the Poudre River 100-year floodplain
- Property must have (or be allowed to build) a house, duplex, or triplex on the lot
- Most properties may add one ADU only; some zones (RUL, RF, CC, CCN, CCR, CG, CS, CL, LMN, MMN, HMN, NC, D, HC, E, I, RC) may allow a second detached house
- Detached ADU size: up to 750 sq ft if main home is under 1,667 sq ft; up to 1,000 sq ft or 45% of main home (whichever is less) if larger; existing accessory buildings may convert up to 800 sq ft
- Attached ADU size: above-grade up to 750 sq ft or 45% of main home; basement ADU up to 750 sq ft or 100% of that floor
- Detached ADU height may not exceed the main building or the zone's max height; must sit behind the front wall of the home, at least 5 ft from other buildings, and follow zone setbacks
- A walkway must connect the ADU's main door to the street, and the ADU's address must be visible from the street
- ADU needs its own electric meter (Fort Collins Utilities); may require nearby transformer upgrade or trenching payment
- Utility separations: 10 ft between water/sewer lines, 10 ft between storm drains and other utilities, 6 ft trees to water/sewer, 4 ft shrubs to water/sewer
- Stormwater quality treatment (rain gardens, permeable pavers) required if the project creates more than 1,000 sq ft of new impervious surface
- Mandatory Basic Development Review (flat $6,925 fee) precedes the building permit — decision made administratively by Planning Manager or Community Development Director per HB 24-1152 (no public hearing/subjective design review)
- Building Code requirements: fire-rated separation between units (attached ADUs), separate heating systems (attached ADUs), minimum kitchen/bathroom standards, separate exit doors
- Short-term rental of ADUs is prohibited, except in Planned Unit Developments (PUDs) where STRs were previously allowed
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Setback and Footing / Foundation
Before concrete pour, per structural plans
- 2
Rough Frame / Rough Plumbing / Rough Electric / Rough Mechanical
Structural framing, egress windows, fire separation (attached ADUs), and trade rough-ins
- 3
Insulation
Air sealing and R-value verification before drywall
- 4
Final Building
All work complete; Certificate of Occupancy or Letter of Completion required before occupancy
See the full Fort Collins inspection guide — scheduling & re-inspection fees →
Tips
- Since Feb. 2025 (Colorado HB 24-1152), ADUs are allowed in ALL Fort Collins zone districts, not just Old Town and select neighborhoods as before — a major recent expansion.
- Budget for the mandatory $6,925 Basic Development Review fee BEFORE the building permit — this is required for every ADU project, with no public hearing under the state-mandated administrative review process.
- Total all-in ADU costs (BDR + utility + transportation + building permit fees) run an estimated $20,000–$25,000 per the city's own published range — budget accordingly.
- As a CSU (Colorado State University) college town, Fort Collins ADUs are commonly used for off-campus rental housing; HB 24-1152 prohibits the city from requiring owner-occupancy, but short-term rental of ADUs remains prohibited outside PUDs.
- A free optional Conceptual Design Review with City staff is available before formal application — useful for CSU-adjacent rental-oriented ADU projects to flag utility/site issues early.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Collins building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Fort Collins
Accessory Dwelling Unit (ADU) Permit in other cities
Compare accessory dwelling unit (adu) permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Fort Collins project checklist
Describe your project once and get every permit, document, and fee it triggers in Fort Collins — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →