How to schedule

Inspections are requested through the building department below.

Address
281 N. College Ave., Fort Collins, CO 80524
Phone
970-416-2740
Office hours
Monday–Friday, 8 a.m. to 5 p.m.

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Setback and Footing

    Inspection of footing formwork prior to concrete being poured

  2. 2

    Foundation

    Inspection of foundation formwork prior to concrete being poured

  3. 3

    Rough Frame / Rough Plumbing / Rough Electric / Rough Mechanical

    Framing, plumbing, electric, and mechanical rough-ins — done before or concurrently, before interior insulation installed

  4. 4

    Insulation

    After all rough inspections approved, verifies air sealing and R-values match approved energy documents, before drywall

  5. 5

    Final Building

    After all work shown on approved plans is complete, including Final Plumbing, Final Electric, and Final Mechanical

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Setback and Footing / Foundation

    Before concrete pour, per structural plans

  2. 2

    Rough Frame / Rough Plumbing / Rough Electric / Rough Mechanical

    Structural framing, egress windows, fire separation (attached ADUs), and trade rough-ins

  3. 3

    Insulation

    Air sealing and R-value verification before drywall

  4. 4

    Final Building

    All work complete; Certificate of Occupancy or Letter of Completion required before occupancy

Applies to: Electrical Permit

  1. 1

    Underground Electric

    With conduits installed and/or direct-burial conductors, prior to backfill (if applicable)

  2. 2

    Rough Electric

    After wiring system installed, before interior insulation; done before/concurrent with rough frame

  3. 3

    Energize Electric

    Electrical service equipment installed, wired and bonded to grounding electrode system; authorizes Fort Collins Utilities to energize for construction use; done before drywall

  4. 4

    Final Electric

    All electrical receptacles, devices, lighting and panels completed

Applies to: Mechanical / HVAC Permit

  1. 1

    Gas Line Test

    After gas piping/fittings/unions/valves installed, before covered or connected to fixtures; 10 psi air test required

  2. 2

    Rough Mechanical

    After ductwork installed and sealed; before/concurrent with rough frame, before interior insulation

  3. 3

    Fireplace/Stove (if applicable)

    Concurrent with frame inspection; factory-built units inspected after chimney framing and fire-stopping complete, before covering

  4. 4

    Final Mechanical

    All registers trimmed, mechanical equipment completed and operational; approved mechanical documents required on site

Applies to: Plumbing Permit

  1. 1

    Underground Plumbing

    After under-slab/underground plumbing installed but before covering; 10-ft head water test or 5 psi air test required

  2. 2

    Water Line / Sewer Line

    Water service piping and building sewer inspected before covering; water/air test required if couplings used

  3. 3

    Rough Plumbing

    Interior domestic waste/vent complete (10-ft head water test or 5 psi air test); done before/concurrent with rough frame, before interior insulation

  4. 4

    Final Plumbing

    All fixtures and plumbing finishes installed

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour, for additions with new foundation work

  2. 2

    Rough Frame / Rough Plumbing / Rough Electric / Rough Mechanical

    Framing and trade rough-ins before insulation/wall cover

  3. 3

    Insulation

    Verifies air sealing and R-values before drywall

  4. 4

    Final Building

    All work complete per approved plans

Applies to: Commercial Tenant Improvement / Remodel Permit

  1. 1

    Rough Frame / Rough Plumbing / Rough Electric / Rough Mechanical

    Trade rough-ins for the tenant space before wall cover

  2. 2

    Hood/Duct (if applicable)

    Commercial kitchen/industrial hoods and associated ductwork, inspected before ceilings installed

  3. 3

    Final Building

    All work complete per approved plans, including accessibility compliance for commercial projects

Applies to: Deck / Covered Patio Permit

  1. 1

    Setback and Footing

    Footing formwork inspected before concrete pour, per the 30-inch Fort Collins frost depth

  2. 2

    Rough Frame

    Deck framing, ledger attachment, and structural connections before decking/covering installed

  3. 3

    Final Building

    Completed deck or patio cover inspected against approved plans

Applies to: EV Charger / Electric Vehicle Charging Station Permit

  1. 1

    Rough Electric

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Energize Electric

    Fort Collins Utilities meter/energize step, if the charger requires new or upgraded electrical service

  3. 3

    Final Electric

    Charger mounted, wired, and tested; all connections verified

Applies to: Solar PV Permit

  1. 1

    Rough Electric

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Energize Electric

    Fort Collins Utilities meter/energize step for the interconnected system

  3. 3

    Final Building / Final Electric

    Panel mounting, racking attachment, roof penetration sealing, and all electrical connections/interconnection verified

Applies to: Change of Use / Change of Occupancy

  1. 1

    Zoning/Use Compliance Check

    Confirms the proposed use is a permitted or limited-permitted use in the applicable zone district under Article 4's Table of Primary Uses, before or alongside building-permit review

  2. 2

    Final Building

    All work complete per the approved Commercial Remodel plans, including any accessibility upgrades or life-safety changes required by the 2024 IEBC for the new occupancy classification

Applies to: Demolition Permit

  1. 1

    Pre-Demolition Documentation Review

    Verification of asbestos disclosure/assessment and, for complete demolition, the State Demolition Approval Notice, before work begins

  2. 2

    Final

    Confirms demolition scope complete per approved permit and site is left safe/compliant

Applies to: Fire Sprinkler and Fire Alarm System Permit

  1. 1

    Rough-In Inspection

    Sprinkler piping or alarm wiring installed and inspected before concealment

  2. 2

    Final Inspection / Acceptance Test

    System tested per the applicable NFPA standard (13/13R/13D for sprinklers, 72 for alarms) and PFA's acceptance-documentation requirements

Final inspection only: Roofing Permit (Reroof), Sign Permit

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Collins building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Fort Collins building permits

Get alerts for Fort Collins

We'll email you when Fort Collins's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.