Plumbing Permit in Fort Collins, Colorado

Required for water, sewer, gas piping and valve work in Fort Collins. The CITY of Fort Collins Building Services issues and reviews plumbing permits directly — individuals performing plumbing work must hold a State of Colorado plumbing license, and Master Plumbers must additionally register with the City of Fort Collins. Governed by the 2024 International Plumbing Code (IPC) with Fort Collins Amendments (Fort Collins uses the IPC, unlike Reno's UPC).

Verified 2026-06-30 · Source

When you need this permit

  • Work included: water, sewer, gas piping and valves
  • If more than one trade is involved (HVAC, electric, plumbing), submit a Remodel/Alteration permit instead of the Fast-Track Plumbing permit
  • If a gas line is installed for a heater, submit a Mechanical permit instead
  • Master Plumbers must be licensed by the State of Colorado (Supervisor relationship) AND separately register with the City of Fort Collins (no additional City exam required) Contractor
  • Governed by the 2024 IPC with Fort Collins Amendments (current as of April 1, 2026); Colorado Plumbing Code also referenced on the Building Code page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Plumbing (Fast-Track Building Permit Fee)City of Fort Collins Building Permits page — Fast-Track Permits, Plumbing
$65.00
Master Plumber Registration (new, renewal or reinstatement)City of Fort Collins Contractor Licensing page — Fees table
$200.00
Sales TaxCity of Fort Collins Sales Tax page
Calculated based on total project valuation (materials and labor)

Review timeline

Plan reviewTypical estimate — confirm current times with the Fort Collins building department
~0–0 business days

How long did your Plumbing Permit permit actually take in Fort Collins?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground Plumbing

    After under-slab/underground plumbing installed but before covering; 10-ft head water test or 5 psi air test required

  2. 2

    Water Line / Sewer Line

    Water service piping and building sewer inspected before covering; water/air test required if couplings used

  3. 3

    Rough Plumbing

    Interior domestic waste/vent complete (10-ft head water test or 5 psi air test); done before/concurrent with rough frame, before interior insulation

  4. 4

    Final Plumbing

    All fixtures and plumbing finishes installed

See the full Fort Collins inspection guide — scheduling & re-inspection fees →

Tips

  • Fort Collins uses the International Plumbing Code (IPC), not the Uniform Plumbing Code (UPC) used in Reno, NV — pipe materials and fixture requirements follow IPC.
  • The City — not a Colorado state board — issues and reviews plumbing permits in Fort Collins; the plumber must still hold the underlying State of Colorado plumbing license as a prerequisite for City Master Plumber registration.
  • Water heater replacement is processed as its own Fast-Track permit (see Mechanical/HVAC permit) at $65 per water heater, not under this Plumbing permit type.
  • Gas line installation for a heater is processed as a Mechanical permit, not a Plumbing permit, in Fort Collins.

Frequently asked questions

Fort Collins requires a plumbing permit for: Work included: water, sewer, gas piping and valves; If more than one trade is involved (HVAC, electric, plumbing), submit a Remodel/Alteration permit instead of the Fast-Track Plumbing permit; If a gas line is installed for a heater, submit a Mechanical permit instead; Master Plumbers must be licensed by the State of Colorado (Supervisor relationship) AND separately register with the City of Fort Collins (no additional City exam required); Governed by the 2024 IPC with Fort Collins Amendments (current as of April 1, 2026); Colorado Plumbing Code also referenced on the Building Code page. If your project isn't listed, confirm with City of Fort Collins — Building Services at 970-416-2740 before starting work.

In Fort Collins, the published Plumbing (Fast-Track Building Permit Fee) is: $65.00. Additional published fees: Master Plumber Registration (new, renewal or reinstatement) — $200.00; Sales Tax — Calculated based on total project valuation (materials and labor). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a plumbing permit in Fort Collins typically runs 0–0 business days. This is an estimate, not a published figure — confirm current review times with City of Fort Collins — Building Services at 970-416-2740.

You'll need: Plumbing Permit Application (PDF, 432KB); Master License Registration Packet (PDF, 620KB). Depending on your project, Fort Collins may also ask for: Homeowner Affidavit (PDF, 469KB); Owner Authorization Form (PDF, 374KB). See the required-documents checklist on this page for details on each.

Fort Collins requires 4 inspection(s) for a plumbing permit, in order: Underground Plumbing, Water Line / Sewer Line, Rough Plumbing, Final Plumbing. Schedule each through City of Fort Collins — Building Services (970-416-2740).

Apply through City of Fort Collins — Building Services at 281 N. College Ave., Fort Collins, CO 80524. Phone: 970-416-2740, email: BuildingServices@fortcollins.gov. Office hours: Monday–Friday, 8 a.m. to 5 p.m.. Official information: https://www.fortcollins.gov/Business/Building-and-Development/Building-Services.

Fort Collins uses the International Plumbing Code (IPC) — currently the 2024 IPC with Fort Collins Amendments, effective April 1, 2026 — not the Uniform Plumbing Code (UPC).

The City of Fort Collins Building Services issues and reviews plumbing permits directly. Plumbers must hold a State of Colorado plumbing license, and Master Plumbers must also register with the City (a $200 registration, no separate city exam).

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Collins building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.