Residential Addition / Remodel Permit in Fort Collins, Colorado
Required for residential additions (garage expansions, pop-the-tops, sunrooms, enclosing a covered patio) and remodels (kitchen/bath alterations, basement finishes, layout changes) in Fort Collins. Additions use the same occupancy-based Fee Schedules rate table as new construction; interior remodels use a valuation-based tiered fee table.
Verified 2026-06-30 · Source
When you need this permit
- Additions: enlarging/expanding enclosed area (pop-the-top, lean-to, garage expansion, sunroom, enclosing a covered patio) — fee calculated via Fee Schedules occupancy rate table
- Remodels: kitchen/bath alterations, interior layout changes, garage/attic/accessory-building-to-living-space conversions, converting living space to bedroom, digging out a crawlspace for a basement, finishing a large attic — fee calculated via the tiered valuation-based Permit Fee table
- Residential Mechanical Systems Design Submittal required if a mechanical system is completely new or the type of heating/cooling is changing
- Residential Energy Code Compliance Form required when a non-heated space becomes heated
- Construction Waste and Recycling Management Declaration of Responsibility required for additions larger than 2,500 sq ft
- Homeowner Affidavit required if homeowner is doing the work Owner-builder
- Basement Finish is processed as its own Fast-Track permit type with a flat $155 Building Permit Fee (see notes)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Foundation (if new footings)
Before concrete pour, for additions with new foundation work
- 2
Rough Frame / Rough Plumbing / Rough Electric / Rough Mechanical
Framing and trade rough-ins before insulation/wall cover
- 3
Insulation
Verifies air sealing and R-values before drywall
- 4
Final Building
All work complete per approved plans
See the full Fort Collins inspection guide — scheduling & re-inspection fees →
Tips
- Additions use the same occupancy-based per-square-foot fee table as new construction; interior remodels (no added enclosed area) use a separate tiered valuation-based fee table.
- Basement finishes are processed as a Fast-Track permit with a flat $155 Building Permit Fee — one of the simplest permit paths in Fort Collins.
- If the entire building has a fire sprinkler system, email buildingdocs@fortcollins.gov before a basement finish submittal so staff can confirm sprinkler-type requirements.
- Additions larger than 2,500 sq ft require Construction Waste and Recycling Management documentation.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Collins building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Fort Collins
Residential Addition / Remodel Permit in other cities
Compare residential addition / remodel permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Fort Collins project checklist
Describe your project once and get every permit, document, and fee it triggers in Fort Collins — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →