Skip to main content
PermitBase

Residential Addition / Alteration-Remodel Permit in Basalt, Colorado

Required for additions and alterations/remodels to existing single-family, duplex, and townhome structures in Basalt, using the same 'Single Family, Duplex, and Townhomes' IRC checklist as new construction, with items marked N/A where not applicable to the smaller scope.

Verified 2026-07-06 · Source

When you need this permit

  • Reviewed under the 2021 IRC/IBC as locally amended; the Town's checklist explicitly covers 'New Construction, Addition, Alteration' with a note that 'not all items listed will be applicable' for a remodel or addition
  • Asbestos test required for remodels disturbing greater than 160 SF, 260 LF, or a volume equivalent to a 55-gallon drum
  • Level 3 Remodels trigger a Home Energy Assessment and Baseline Blower Door Test under the Sustainable Building Regulations; Additions greater than 500 SF require Electric-Ready items and Solar incorporated into drawings per Part 5.0 of the SBR Ordinance; Level 3 Remodels over 750 SF require the full combined SBR package
  • Plan Submittal Fee of 50% of the calculated plan review fee due (non-refundable) at submittal
  • Water and Sanitation Approval required per the applicable provider for the parcel's neighborhood
  • Verification of current Town of Basalt Contractor Licensing, including SBR certification currency if the project is subject to SBR requirements

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (same valuation-based schedule as new construction)
$21.00 minimum, scaling per the valuation tiers in the Town of Basalt Building Permit Fee Schedule
Plan Submittal Fee
50% of the calculated plan review fee, due at submittal, non-refundable

Review timeline

Plan review
Not published — contact the department

How long did your Residential Addition / Alteration-Remodel Permit permit actually take in Basalt?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation (additions with new footings only)

  2. 2

    Rough Frame

    Framing complete, connection to existing structure verified

  3. 3

    Rough Mechanical / Plumbing

  4. 4

    Final Inspection

See the full Basalt inspection guide — scheduling & re-inspection fees →

Tips

  • The Town uses the SAME checklist document for new construction, additions, and alterations/remodels — mark non-applicable items as N/A rather than assuming a separate lighter-weight form exists for smaller scopes.
  • An addition over 500 SF triggers Electric-Ready and Solar drawing requirements under the Sustainable Building Regulations even if the addition itself isn't otherwise a 'Level 3 Remodel' — check the SF threshold carefully.

Frequently asked questions

Basalt requires a residential addition / alteration-remodel permit for: Reviewed under the 2021 IRC/IBC as locally amended; the Town's checklist explicitly covers 'New Construction, Addition, Alteration' with a note that 'not all items listed will be applicable' for a remodel or addition; Asbestos test required for remodels disturbing greater than 160 SF, 260 LF, or a volume equivalent to a 55-gallon drum; Level 3 Remodels trigger a Home Energy Assessment and Baseline Blower Door Test under the Sustainable Building Regulations; Additions greater than 500 SF require Electric-Ready items and Solar incorporated into drawings per Part 5.0 of the SBR Ordinance; Level 3 Remodels over 750 SF require the full combined SBR package; Plan Submittal Fee of 50% of the calculated plan review fee due (non-refundable) at submittal; Water and Sanitation Approval required per the applicable provider for the parcel's neighborhood; Verification of current Town of Basalt Contractor Licensing, including SBR certification currency if the project is subject to SBR requirements. If your project isn't listed, confirm with Town of Basalt Building Department at 970-927-4702 before starting work.

In Basalt, the published Building Permit Fee (same valuation-based schedule as new construction) is: $21.00 minimum, scaling per the valuation tiers in the Town of Basalt Building Permit Fee Schedule. Additional published fees: Plan Submittal Fee — 50% of the calculated plan review fee, due at submittal, non-refundable. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Basalt does not publish a plan-review timeline for this permit. Contact Town of Basalt Building Department at 970-927-4702 for current turnaround.

You'll need: Building Permit Application Checklist — Single Family, Duplex, and Townhomes; Sustainable Building Regulations Checklist and Cover Page. See the required-documents checklist on this page for details on each.

Basalt requires 4 inspection(s) for a residential addition / alteration-remodel permit, in order: Foundation (additions with new footings only), Rough Frame, Rough Mechanical / Plumbing, Final Inspection. Schedule each through Town of Basalt Building Department (970-927-4702).

Apply through Town of Basalt Building Department at 101 Midland Avenue, Basalt, CO 81621. Phone: 970-927-4702, email: carlos.peugnet@basalt.net. Office hours: Town of Basalt main line 970-927-4701; Building Department direct line 970-927-4702. Chief Building Official: Mitch Miller, 970-279-4386, mitch.miller@basalt.net. Plans Examiner & Inspector: Carlos Peugnet, 970-279-4385, carlos.peugnet@basalt.net. As of May 2017 the Building Department no longer performs inspections or site visits on Mondays and Fridays (confirmed on the Building Department page).. Official information: https://www.basalt.net/132/Building.

Basalt, Colorado has adopted: 2021 International Building Code (IBC) as locally amended by Town of Basalt Ordinance (Chapter 18 amendments effective July 20, 2023) — confirmed via the Town's own 'Building' page code-adoption summary ('2021 ICC') and via the Town's detailed strike-through/underline local-amendment comparison document (2021-Code-change--ICC-reference-articles, basalt.net/DocumentCenter/View/6221); 2021 International Residential Code (IRC), as locally amended — the Town's own Building Permit Application Checklist is titled for 'Single Family, Duplex, and Townhomes' built to the IRC; 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC) — State of Colorado adopted edition referenced alongside the Town's 2021 IBC/IRC/IMC cycle; 2021 International Existing Building Code (IEBC); 2021 International Plumbing Code (IPC) — adopted at the State of Colorado level and applied by the Town; 2023 National Electrical Code (NEC) — per the Building Department page's current-adoptions summary; NOTE electrical work in Basalt is permitted and inspected by the State of Colorado Electrical Board, not the Town Building Department itself (confirmed directly on the Town's own Building Permit Application form: 'Electrical is permitted and inspected by the State of Colorado'); 2024 Sustainable Building Regulations I & II (SBRI/SBRII) — Town of Basalt Municipal Code Sec. 18-23/18-24/18-25, amended by Ordinance 20, Series of 2024, effective November 12, 2024, reflecting Holy Cross Energy's approximately 90% renewable power supply achievement by end of 2024; Prior/superseded local design-parameter reference: the Town's 'Local Structural Design Parameters' document (basalt.net/documentcenter/view/2388) still headers itself against the 2015 IBC/IRC/IMC/IECC/IEBC code cycle and 2017 NEC/2015 IPC-IFGC — the numeric structural design values on that document (ground snow load, wind speed, seismic category, frost depth) are treated as still-current in this file because the Town's later 2021-code-adoption amendment document (View/6221) re-adopts the identical IRC Table R301.2(1) frost-depth (36 inches) and retaining-wall figures verbatim rather than superseding them; the code-EDITION labels on that older PDF itself are NOT current and should not be read as Basalt's current adopted code cycle.; Local amendments to all adopted codes are codified in Chapter 18 (Building Regulations) of the Basalt Municipal Code; Municode's Basalt library returned an HTTP 403 to direct automated fetch in this session (library.municode.com/co/basalt) — the Town's own downloadable strike-through/underline amendment comparison document (View/6221) was used as the authoritative source for specific local IBC/IRC section amendments instead, since it is a primary Town document rather than a third-party mirror.. Local amendments apply — see the Basalt overview page for the full list.

No. The Town of Basalt uses the same Building Permit Application Checklist for Single Family, Duplex, and Townhomes for new construction, additions, and alterations/remodels, with instructions to mark items that don't apply to your project scope as N/A.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Basalt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.