Residential Addition / Alteration-Remodel Permit — Basalt, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://basalt.net/DocumentCenter/View/6791/Town-of-Basalt-Permit-Application-Checklist_IRC_2026-01-06
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Addition / Alteration-Remodel Permit in Basalt, Colorado
Required for additions and alterations/remodels to existing single-family, duplex, and townhome structures in Basalt, using the same 'Single Family, Duplex, and Townhomes' IRC checklist as new construction, with items marked N/A where not applicable to the smaller scope.
Verified 2026-07-06 · Source
When you need this permit
- Reviewed under the 2021 IRC/IBC as locally amended; the Town's checklist explicitly covers 'New Construction, Addition, Alteration' with a note that 'not all items listed will be applicable' for a remodel or addition
- Asbestos test required for remodels disturbing greater than 160 SF, 260 LF, or a volume equivalent to a 55-gallon drum
- Level 3 Remodels trigger a Home Energy Assessment and Baseline Blower Door Test under the Sustainable Building Regulations; Additions greater than 500 SF require Electric-Ready items and Solar incorporated into drawings per Part 5.0 of the SBR Ordinance; Level 3 Remodels over 750 SF require the full combined SBR package
- Plan Submittal Fee of 50% of the calculated plan review fee due (non-refundable) at submittal
- Water and Sanitation Approval required per the applicable provider for the parcel's neighborhood
- Verification of current Town of Basalt Contractor Licensing, including SBR certification currency if the project is subject to SBR requirements
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation (additions with new footings only)
- 2
Rough Frame
Framing complete, connection to existing structure verified
- 3
Rough Mechanical / Plumbing
- 4
Final Inspection
See the full Basalt inspection guide — scheduling & re-inspection fees →
Tips
- The Town uses the SAME checklist document for new construction, additions, and alterations/remodels — mark non-applicable items as N/A rather than assuming a separate lighter-weight form exists for smaller scopes.
- An addition over 500 SF triggers Electric-Ready and Solar drawing requirements under the Sustainable Building Regulations even if the addition itself isn't otherwise a 'Level 3 Remodel' — check the SF threshold carefully.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Basalt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Basalt
Residential Addition / Alteration-Remodel Permit in other cities
Compare residential addition / alteration-remodel permit fees across Colorado →
Look up this fee in a different city →