Inspection sequence, scheduling, and re-inspection fees for building permits in Basalt, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
101 Midland Avenue, Basalt, CO 81621
Phone
970-927-4702
Office hours
Town of Basalt main line 970-927-4701; Building Department direct line 970-927-4702. Chief Building Official: Mitch Miller, 970-279-4386, mitch.miller@basalt.net. Plans Examiner & Inspector: Carlos Peugnet, 970-279-4385, carlos.peugnet@basalt.net. As of May 2017 the Building Department no longer performs inspections or site visits on Mondays and Fridays (confirmed on the Building Department page).

Inspection sequence

Applies to: Commercial Building Permit (New Construction, Addition, Alteration / Tenant Finish)

  1. 1

    Special Inspections (IBC Chapter 17)

    For projects requiring special inspection/testing per IBC Ch. 17: building-department-approved third-party special inspectors observe assigned work (continuous, or periodic only with a pre-approved written plan) throughout construction, report nonconforming items, and file written reports with the Building Official and design professional of record. The special inspector may not be employed by the contractor, subcontractor, or material supplier

  2. 2

    Rough Mechanical / Plumbing

    Town-inspected trade rough-ins before concealment; fire-rated penetration protection and fire/smoke dampers per the approved plans (electrical rough-in is inspected separately by the State of Colorado Electrical Board). The Town does not publish a formal commercial inspection-sequence card — schedule through the Building Department, noting no inspections or site visits are performed on Mondays and Fridays

  3. 3

    Final Building Inspection

    All work complete per approved plans; the special inspector's written final report documenting required special inspections and correction of discrepancies must be submitted PRIOR to the final building inspection

  4. 4

    Certificate of Occupancy prerequisites

    Prior to CO issuance, the design professional in responsible charge must submit a signed and stamped report confirming all required special-inspection reports were reviewed and the work conforms to the approved plans; an Improvement Location Certificate (ILC) is also required prior to CO per the checklist's site-plan section

Applies to: Fire Sprinkler and Fire Alarm System Permit

  1. 1

    Hydrostatic/Pneumatic Test (Sprinkler)

    200-pound hydrostatic or pneumatic test, 2 hours minimum, witnessed and approved by the RFFR inspector

  2. 2

    Rough-In Inspection

    Sprinkler piping and hangers (including grid-style ceilings) must not be covered or concealed prior to being inspected and approved

  3. 3

    Final Inspection (Sprinkler)

    Structure must be 'move in ready'; all valves labeled and hydraulic calculation sticker on riser; water-flow test through the inspector's test valve with alarm sounding in under 60 seconds; all heads trimmed out with spare head box in place; FDC unobstructed with horn above; control valves supervised; Above Ground Piping Certificate provided before final approval

  4. 4

    Final Acceptance Test (Fire Alarm)

    Witnessed by the Fire Department with adequate contractor manpower/equipment; tests initiating devices, indicating appliances, and signaling line circuits for proper alarm and trouble response; required before any certificate of occupancy or temporary CO is issued, along with a written maintenance/training policy

Applies to: Residential Addition / Alteration-Remodel Permit

  1. 1

    Foundation (additions with new footings only)

  2. 2

    Rough Frame

    Framing complete, connection to existing structure verified

  3. 3

    Rough Mechanical / Plumbing

  4. 4

    Final Inspection

Applies to: Residential Building Permit (New Construction, Single-Family/Duplex/Townhome)

  1. 1

    Foundation

    Before concrete pour, per 36-inch minimum frost depth

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Mechanical / Plumbing

    Trade rough-ins before concealment (electrical rough-in is inspected separately by the State of Colorado Electrical Board)

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Performed by the State of Colorado Electrical Board inspector, not a Town of Basalt inspector

  2. 2

    Final Inspection

    State of Colorado Electrical Board final inspection and sign-off

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Roofing Permit (Re-Roof)

  1. 1

    Mid-Roof / Underlayment Inspection

    Ice barrier underlayment and deck condition verified before roof covering installation

  2. 2

    Final Inspection

    Completed roof — material, flashing, and underlayment compliance verified

Applies to: Solar Photovoltaic (PV) System Permit

  1. 1

    Rough-In Inspection

    Verify location and placement of array (Town of Basalt Building PV inspection)

  2. 2

    Final Inspection

    Verify operation of array (Town of Basalt Building PV inspection); separate final sign-off also required from the Colorado State Electrical Board and Roaring Fork Fire Authority

Re-inspection fees

Commercial Building Permit (New Construction, Addition, Alteration / Tenant Finish)
After-hours inspections; reinspections (IBC Sec. Show full citationAfter-hours inspections; reinspections (IBC Sec. 108.8); inspections with no fee otherwise specified; additional plan review for plan changes/revisions · Town of Basalt Building Permit Fees (2023-08-07), Other inspections & Fees items 1–4 — $100.00 per hour for each, with a 2-hour minimum for inspections outside normal business hours and a half-hour minimum for inspections with no fee otherwise specified and for additional plan review. Or the total hourly cost to the jurisdiction, whichever is greater, including supervision, overhead, equipment, wages and fringe benefits. The $42.00 previously recorded is the rate in the Town's 2006 edition, which remains live and is still linked from the Town's current permit checklists even though the Building Department page links the 2023 edition.
$100.00 per hour

Basalt building permits

Get alerts for Basalt

We'll email you when Basalt's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.