How to schedule
Inspections are requested through the building department below.
- Address
- 101 Midland Avenue, Basalt, CO 81621
- Phone
- 970-927-4702
- Office hours
- Town of Basalt main line 970-927-4701; Building Department direct line 970-927-4702. Chief Building Official: Mitch Miller, 970-279-4386, mitch.miller@basalt.net. Plans Examiner & Inspector: Carlos Peugnet, 970-279-4385, carlos.peugnet@basalt.net. As of May 2017 the Building Department no longer performs inspections or site visits on Mondays and Fridays (confirmed on the Building Department page).
- Website
- Official site
Inspection sequence
Applies to: Residential Addition / Alteration-Remodel Permit
- 1
Foundation (additions with new footings only)
- 2
Rough Frame
Framing complete, connection to existing structure verified
- 3
Rough Mechanical / Plumbing
- 4
Final Inspection
Applies to: Residential Building Permit (New Construction, Single-Family/Duplex/Townhome)
- 1
Foundation
Before concrete pour, per 36-inch minimum frost depth
- 2
Framing
Structural framing complete before cover
- 3
Rough Mechanical / Plumbing
Trade rough-ins before concealment (electrical rough-in is inspected separately by the State of Colorado Electrical Board)
- 4
Final Inspection
All work complete per approved plans and applicable codes
Applies to: Electrical Permit
- 1
Rough Electrical
Performed by the State of Colorado Electrical Board inspector, not a Town of Basalt inspector
- 2
Final Inspection
State of Colorado Electrical Board final inspection and sign-off
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Roofing Permit (Re-Roof)
- 1
Mid-Roof / Underlayment Inspection
Ice barrier underlayment and deck condition verified before roof covering installation
- 2
Final Inspection
Completed roof — material, flashing, and underlayment compliance verified
Applies to: Solar Photovoltaic (PV) System Permit
- 1
Rough-In Inspection
Verify location and placement of array (Town of Basalt Building PV inspection)
- 2
Final Inspection
Verify operation of array (Town of Basalt Building PV inspection); separate final sign-off also required from the Colorado State Electrical Board and Roaring Fork Fire Authority
Final inspection only: EV Charger / EVSE Installation Permit, Fence Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Basalt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Basalt building permits
Get alerts for Basalt
We'll email you when Basalt's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.