This is PermitBase’s published record for Wellington as of 2026-07-06. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Wellington building permits

Wellington, Colorado — as published 2026-07-06.

Reviewed 2026-07-06 · Source

Codes adopted

2024 International Building Code (IBC) — effective January 1, 20262024 International Residential Code (IRC) — effective January 1, 20262024 International Energy Conservation Code (IECC) — effective January 1, 20262024 International Mechanical Code (IMC) — effective January 1, 20262024 International Plumbing Code (IPC) — effective January 1, 20262024 International Fire Code (IFC) — effective January 1, 20262024 International Property Maintenance Code (IPMC) — effective January 1, 20262024 International Existing Building Code (IEBC) — effective January 1, 20262024 International Swimming Pool and Spa Code (ISPSC) — effective January 1, 20262026 National Electrical Code (NFPA 70-NEC) — effective January 1, 2026 (per the Town's Building Department page; note this is one code cycle ahead of the 2023 NEC used by most other 2026-era Colorado jurisdictions in this corpus — verified directly against the Town's own 'Building Code Update' announcement, not assumed)2025 Colorado Wildfire Resiliency Code, Version 1.0 — adopted alongside the 2024 I-CodesColorado Model Electric and Solar Ready Code — adopted alongside the 2024 I-Codes, addressing HB22-1362's statewide energy/electric-readiness floorLocal Amendments — Ordinance No. 15-2025 (adopted on first reading October 14, 2025 and second reading/adoption November 12, 2025; effective January 1, 2026) replace the Town's prior 2018 I-Code local amendments (originally under Ordinance No. 5-2019) and Ordinance No. 8-2019 (2019 building fee schedule) as the current governing local amendment package. Ordinance No. 15-2025 is codified on Municode (a JavaScript single-page application at library.municode.com/co/wellington) which returns HTTP 200 but serves no static text via automated fetch, curl, or Wayback Machine snapshot as of this review; its content is evidenced instead through the Town's own Building Department webpage 'Building Departments News & Update' section (dated 11.25.2025), which names Ordinance No. 15-2025 as the vehicle for the 2024 I-Code adoption and confirms first/second reading and effective dates directly.Previous code cycle (through December 31, 2025, now superseded): 2018 International Code editions (IBC, IRC, IECC, IMC, IPC, IFGC, IPMC, IEBC, IFC) under Ordinance No. 5-2019, and 2023 NEC. The Town's own Contractors/Homeowners webpages still host several 2018-cycle 'SAFEbuilt Building Guide' packets (Re-Roof 2018, Accessory Structure 2018, Deck/Porches 2018, Patio Covers 2018, Pole Barn 2018, Swimming Pools 2018, PV System 2019) that have not yet been refreshed to reference the 2024 I-Codes as of this review — treated as legacy/stale content rather than the governing code list, consistent with the Town's own live 'Current (Effective January 1, 2026)' code list.

Permit types & fees

Residential Building Permit (New Construction)

Required for new single-family homes, duplexes, and townhomes in the Town of Wellington. Reviewed by SAFEbuilt, the Town's contracted building-department partner, under the 2024 IRC/IBC as locally amended (Ordinance No. 15-2025), effective January 1, 2026, plus the 2025 Colorado Wildfire Resiliency Code and the Colorado Model Electric and Solar Ready Code.

Reviewed 2026-07-06 · Source

Requirements

  • 'New Buildings' are explicitly listed as a permit-requiring project type on the Town's 'Do I Need a Permit?' guide
  • Plans reviewed under the 2024 IRC/IBC as locally amended by Ordinance No. 15-2025 (effective 1/1/2026), the 2025 Colorado Wildfire Resiliency Code, and the Colorado Model Electric and Solar Ready Code
  • Foundations must be designed and construction drawings stamped by a Colorado-registered design professional, based on an engineer's soils report (per the Town's codified IRC amendment to Section R401.2, carried forward from the prior 2018-cycle amendment package; not yet independently re-confirmed against the un-fetchable Ordinance No. 15-2025 text, so treated as likely-continuing rather than freshly verified for the 2024 cycle)
  • All contractors and subcontractors must hold a current Town of Wellington Contractor License in addition to any required Colorado state trade license
  • Application, plan submittal, and payment are all conducted through the Community Core/Connect online portal — mailed paper applications are not accepted

Required documents

  • RequiredBuilding Permit ApplicationSubmitted online via Community Core/Connect
  • RequiredConstruction DrawingsStamped by a Colorado-registered design professional; foundation design based on an engineer's soils report
  • RequiredTown of Wellington Contractor LicenseRequired for all contractors/subcontractors; not required for an owner acting as their own general contractor on their own dwelling

Fee schedule

Fee typeAmountNotes
Permit Issuance$25 flatFee Schedule effective 2026-04-01, Res. No. 38-2025 / Ord. No. 01-2026
Building Permit Fee — valuation $1 to $1,000$75
Building Permit Fee — valuation $1,001 to $25,000$75 plus $14.00 for each additional $1,000 or fraction thereof over $1,000
Building Permit Fee — valuation $25,001 to $50,000$391.25 plus $10.10 for each additional $1,000 or fraction thereof over $1,000
Building Permit Fee — valuation $50,001 to $100,000$643.75 plus $7.00 for each additional $1,000 or fraction thereof over $1,000
Building Permit Fee — valuation $100,001 to $500,000$993.75 plus $5.60 for each additional $1,000 or fraction thereof over $1,000
Building Permit Fee — valuation $500,000 to $1,000,000$3,233.75 plus $4.75 for each additional $1,000 or fraction thereof over $1,000
Building Permit Fee — valuation $1,000,000 or greater$5,608.75 plus $3.15 for each additional $1,000 or fraction thereof
Building Plan Review Fee (Townhomes, Single- and Two-Unit Residential)30% of Building Fee
Town Administrative Fee10% of Building Fee
Electrical FeeFrom State Electrical Fee Schedule (CRS 12-23-117); no separate Town valuation table

Residential Addition / Remodel Permit

Verified

Required for additions, basement finishes, and remodels to existing residential structures in Wellington. Falls under the Town's 'Permits With Plan Review' track and 'Residential Alterations' permit-naming category, reviewed by SAFEbuilt under the 2024 IRC as locally amended.

Verified 2026-07-06 · Source

Requirements

  • Reviewed under the 'Permits With Plan Review' track — requires the SAFEbuilt Building Guide packet and matching Wellington Project Checklist for the specific project type (Residential Addition, Basement Finish, or Residential Remodel)
  • Structural modifications require an engineered letter
  • Engineered plans by a Colorado-licensed engineer or architect may be required depending on project scope — reference the applicable Building Guide packet
  • All contractors/subcontractors must hold a current Town of Wellington Contractor License

Required documents

  • RequiredBuilding Permit ApplicationSubmitted online via Community Core/Connect; permit category selected per the Town's Permit Naming Categories chart (e.g. 'Residential Addition' or 'Residential Remodel')
  • RequiredSAFEbuilt Building Guide Packet — Residential AdditionMinimum submittal requirements for addition projects
  • RequiredWellington Project Checklist — Residential Addition/RemodelTown-specific checklist supplementing the SAFEbuilt guide
  • OptionalEngineered LetterRequired if the project includes structural modifications

Fee schedule

Fee typeAmountNotes
Permit Issuance$25 flat
Building Permit Fee (same valuation-based schedule as new construction)$75 minimum, scaling per the tiers in the Fee Schedule effective 2026-04-01
Building Plan Review Fee (Single- and Two-Unit Residential)30% of Building Fee
Town Administrative Fee10% of Building Fee

Electrical Permit

Required for electrical installation, alteration, or repair in Wellington. Governed by the 2026 NEC as locally adopted (effective January 1, 2026). Wellington does NOT run its own local electrical contractor licensing/certification program — it defers to Colorado State Electrical Board (DORA) licensing, with SAFEbuilt performing contemporaneous state-license verification at permit issuance per SB19-156.

Reviewed 2026-07-06 · Source

Requirements

  • Governed by the 2026 NEC as adopted by the Town, effective January 1, 2026
  • Contractors must hold a current Colorado State Electrical Board (DORA) Master Electrician license — Wellington does not issue its own separate electrical trade license; a Town of Wellington general Contractor License is still required in addition to the state trade license
  • SAFEbuilt conducts contemporaneous state-license verification at permit issuance per SB19-156, requiring photocopies of the Colorado driver's license, Colorado Master's license (wallet card acceptable), and Colorado Contractor license (wallet card acceptable)
  • Fee set by the Colorado state-mandated electrical fee schedule (CRS 12-23-117), not a Town-specific valuation table; the Town may add a local surcharge of up to 15% above the state base rate per statute

Required documents

  • RequiredElectrical Permit Application (or Electrical Service Charge / Electrical Only category)Submitted via Community Core/Connect under the 'One Stop Permits' track for standalone electrical work, or as part of a larger plan-review permit for new construction/additions
  • RequiredTown of Wellington Contractor LicenseRequired for all contractors performing electrical work
  • RequiredColorado State Electrical Board (DORA) License copiesDriver's license, Master's license, and Contractor license photocopies for contemporaneous SAFEbuilt verification

Fee schedule

Fee typeAmountNotes
Electrical FeeSet by the Colorado state-mandated electrical fee schedule per CRS 12-23-117, with Town surcharge of up to 15% above the state base rate permitted by statuteThe Town's current (effective 2026-04-01) Master Fee Schedule (Res. No. 38-2025 / Ord. No. 01-2026) lists this line item as 'From State Electrical Fee Schedule' without a locally tabulated dollar figure. A Town-published 'Electrical Permit Fees' document shows the historical calculation method (Residential: banded by square footage; All Other: banded by installation valuation) but its dollar amounts are dated 'as of July 1, 2019' and are NOT current — omitted here rather than presented as today's rate.
Permit Issuance$25 flat

Plumbing Permit

Verified

Required for plumbing installation, alteration, or repair in Wellington. Governed by the 2024 IPC as locally adopted (effective January 1, 2026). Wellington does NOT run its own local plumbing contractor licensing program — it defers to Colorado State Plumbing Board (DORA) licensing, with SAFEbuilt performing contemporaneous state-license verification per HB19-1086.

Verified 2026-07-06 · Source

Requirements

  • Governed by the 2024 IPC as adopted by the Town, effective January 1, 2026
  • Contractors must hold a current Colorado State Plumbing Board (DORA) Master Plumber license — Wellington does not issue its own separate plumbing trade license; a Town of Wellington general Contractor License is still required in addition
  • SAFEbuilt conducts contemporaneous state-license verification at permit issuance per HB19-1086, requiring photocopies of the Colorado driver's license, Colorado Master's license, and Colorado Contractor license

Required documents

  • RequiredPlumbing Permit Application (or Misc. Mechanical/Plumbing/Electrical category)Submitted via Community Core/Connect; standalone plumbing work uses the 'One Stop Permits' track
  • RequiredTown of Wellington Contractor LicenseRequired in addition to Colorado DORA Plumbing license
  • RequiredColorado State Plumbing Board (DORA) License copiesDriver's license, Master's license, and Contractor license photocopies for contemporaneous SAFEbuilt verification per HB19-1086

Fee schedule

Fee typeAmountNotes
Plumbing Permit Fee (same valuation-based schedule as Building/Mechanical)$75 minimum, scaling per the tiers in the Fee Schedule effective 2026-04-01No separate plumbing-specific valuation table is published; billed under the general Building Permit Fee schedule
Permit Issuance$25 flat
Building Plan Review Fee (Single- and Two-Unit Residential)30% of Permit Fee

Mechanical / HVAC Permit

Verified

Required for heating, cooling, and ventilation equipment installation or replacement in Wellington. Governed by the 2024 IMC as locally adopted (effective January 1, 2026). Furnace, AC, and AC/Furnace Combo replacements are processed under the Town's 'One Stop Permits — No Plan Review' track at a flat fee.

Verified 2026-07-06 · Source

Requirements

  • Governed by the 2024 IMC as adopted by the Town, effective January 1, 2026
  • Furnace/AC/AC-Furnace-Combo replacement processed as a 'One Stop Permit' (no plan review) at a flat $75 fee
  • New mechanical installation as part of new construction or an addition is reviewed as part of the combined project plan review
  • All contractors must hold a current Town of Wellington Contractor License

Required documents

  • RequiredPermit Application — Furnace/AC/Combo Replacement or new MechanicalSubmitted via Community Core/Connect under the applicable permit-naming category
  • RequiredTown of Wellington Contractor LicenseRequired for all contractors performing mechanical work

Fee schedule

Fee typeAmountNotes
Furnace or AC Replacement$75 flatFee Schedule effective 2026-04-01
New Mechanical Installation (new construction/addition)Billed under the general valuation-based Building Permit Fee schedule ($75 minimum) rather than the flat replacement fee
Permit Issuance$25 flat

Roofing Permit (Re-Roof)

Verified

Required for residential re-roofing in Wellington. Processed under the Town's 'One Stop Permits — No Plan Review' track at a flat $75 fee. Commercial re-roofing (painting a metal roof excepted) also requires a permit.

Verified 2026-07-06 · Source

Requirements

  • Residential Re-roof is a 'One Stop Permit' (no plan review) at a flat $75 fee
  • Commercial re-roofing requires a permit; painting a metal roof specifically does NOT require a permit, per the Town's 'Do I Need a Permit?' guide
  • SAFEbuilt Building Guide Re-Roof packet and the Wellington Project Checklist Roof Replacement document define minimum submittal/material requirements
  • All contractors must hold a current Town of Wellington Contractor License

Required documents

  • RequiredPermit Application — Residential Roof (Asphalt or Other)Submitted via Community Core/Connect under the applicable 'Residential Roof' permit-naming category
  • RequiredWellington Project Checklist — Roof ReplacementTown-specific checklist supplementing the SAFEbuilt Re-Roof guide

Fee schedule

Fee typeAmountNotes
Roof/Re-roof$75 flatFee Schedule effective 2026-04-01
Permit Issuance$25 flat

Solar Photovoltaic (PV) System Permit

Required for rooftop and ground-mount photovoltaic solar installations in Wellington. Falls under the Town's 'Permits With Plan Review' track ('Residential Alteration' category), reviewed alongside the Colorado Model Electric and Solar Ready Code adopted with the 2024 I-Codes.

Reviewed 2026-07-06 · Source

Requirements

  • Reviewed under the 'Permits With Plan Review' track, using the SAFEbuilt PV System Building Guide and the Wellington Project Checklist PV System document
  • Interacts with the Colorado Model Electric and Solar Ready Code, adopted alongside the 2024 I-Codes effective January 1, 2026, and HB22-1362's statewide solar/EV-readiness floor
  • Electrical scope of the installation billed under the state-mandated electrical fee schedule (CRS 12-23-117), not the Town's building valuation table
  • All contractors must hold a current Town of Wellington Contractor License plus applicable Colorado state electrical trade license

Required documents

  • RequiredPermit Application — PV SystemSubmitted via Community Core/Connect under the 'PV System' permit-naming category
  • RequiredWellington Project Checklist — PV SystemTown-specific checklist supplementing the SAFEbuilt PV System guide

Fee schedule

Fee typeAmountNotes
Electrical Fee (PV/solar electrical scope)From State Electrical Fee Schedule (CRS 12-23-117), plus Town surcharge up to 15% above state base rate
Permit Issuance$25 flat

Demolition Permit

Verified

Required for demolition of structures in Wellington. Listed as a distinct permit-requiring project type on the Town's 'Do I Need a Permit?' guide and processed under the 'One Stop Permits — No Plan Review' track.

Verified 2026-07-06 · Source

Requirements

  • Demolition is explicitly listed as a permit-requiring project type on the Town's 'Do I Need a Permit?' guide and as a distinct 'One Stop Permit' category on the Permit Naming Categories chart
  • All contractors must hold a current Town of Wellington Contractor License

Required documents

  • RequiredPermit Application — DemolitionSubmitted via Community Core/Connect under the 'Demolition' permit-naming category; requires the address where work is to be performed and contractor information

Fee schedule

Fee typeAmountNotes
Demolition / Mitigation$50 flatFee Schedule effective 2026-04-01
Permit Issuance$25 flat

Deck / Patio Cover / Pergola Permit

Verified

Required for uncovered decks, patio covers, pergolas, gazebos, and carports in Wellington. Falls under the 'Permits With Plan Review' track ('Residential Alteration' category).

Verified 2026-07-06 · Source

Requirements

  • Reviewed under the 'Permits With Plan Review' track using the applicable SAFEbuilt Building Guide (Uncovered Decks & Porches, or Patio Covers & Carports) and matching Wellington Project Checklist
  • All contractors must hold a current Town of Wellington Contractor License; homeowners acting as their own general contractor on their own dwelling do not need one

Required documents

  • RequiredPermit Application — Deck, Carport/Patio Cover/PergolaSubmitted via Community Core/Connect under the applicable permit-naming category
  • RequiredWellington Project Checklist — Uncovered Deck & Porches, or Patio Covers/Pergolas/GazebosTown-specific checklist matching project scope

Fee schedule

Fee typeAmountNotes
Building Permit Fee (valuation-based, general schedule)$75 minimum, scaling per the tiers in the Fee Schedule effective 2026-04-01No separate flat deck/patio fee is published; billed under the general valuation-based Building Permit Fee schedule
Permit Issuance$25 flat
Building Plan Review Fee (Single- and Two-Unit Residential)30% of Building Fee

Water Heater Replacement Permit

Verified

Required for water heater installation/replacement in Wellington. Processed under the 'One Stop Permits — No Plan Review' track at a flat $75 fee, distinct from the combined 'furnace-water-heater-replacement' bundling seen in some other Colorado jurisdictions — Wellington bills Water Heater Replacement and Furnace/AC Replacement as separate but identically priced flat-fee line items.

Verified 2026-07-06 · Source

Requirements

  • Water Heater Replacement is its own 'One Stop Permit' (no plan review) line item, flat $75, separate from the Furnace/AC Replacement line item (also flat $75)
  • All contractors must hold a current Town of Wellington Contractor License

Required documents

  • RequiredPermit Application — Water HeaterSubmitted via Community Core/Connect under the 'Water Heater' permit-naming category

Fee schedule

Fee typeAmountNotes
Water Heater Replacement$75 flatFee Schedule effective 2026-04-01; identical flat rate to Furnace/AC Replacement but a separate line item
Permit Issuance$25 flat

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wellington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Later version (2026-07-07) →View current record →All versions →

Permalink: /colorado/larimer-county/wellington/as-of/2026-07-06/

Snapshot date: 2026-07-06

Commit: dc2fcc8

Reproducible from PermitBase’s version-controlled dataset, commit dc2fcc8.