Trinidad building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Trinidad, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 135 N. Animas Street (PO Box 880), Trinidad, CO 81082
- Phone
- (719) 846-9843 ext. 136 or ext. 128
- Office hours
- Monday-Friday, 8:00 AM - 5:00 PM (City of Trinidad normal business hours); Development Services Administrator Tara Booth; fax (719) 846-4140
- Website
- Official site
Inspection sequence
Applies to: Commercial Building Permit (New Construction)
- 1
Foundation
Before concrete pour; requires wet-stamped structural/soils documentation on file
- 2
Rough (Structural/Plumbing/Mechanical/Electrical)
Multi-trade rough inspections before concealment, consistent with the multi-trade wet-stamped plan set required at application
- 3
Final Inspection
Requires Final Approvals from Development Services, Utilities, Public Works, Fire, and Police before permit release, per the Commercial New Construction Checklist
Applies to: Residential Addition / Remodel Permit
- 1
Foundation (if new footings)
Before concrete pour, per 32-inch minimum frost depth
- 2
Rough Framing
Framing tied into existing structure before cover
- 3
Final Inspection
All work complete per approved plans
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour; foundation plans require an engineer's wet stamp
- 2
Rough Framing
Framing complete before cover
- 3
Final Inspection
All work complete per approved plans and applicable 2024 IRC/IBC provisions
Applies to: Electric Vehicle (EV) Charger Permit
- 1
Rough Electrical
EV charger circuit wiring and panel installation before concealment; inspecting authority (City vs. State Electrical Board) not conclusively confirmed.
- 2
Final Inspection
Charger installed, devices verified, system energized.
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installation before concealment; inspecting authority (City vs. State Electrical Board) not conclusively confirmed
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
Applies to: Fire Sprinkler / Fire Alarm System Permit
- 1
Rough-In Inspection
Sprinkler piping or fire alarm wiring/devices inspected before concealment
- 2
Final Acceptance Test
System tested and verified operational before approval, consistent with the 2018 IFC's fire-protection-system acceptance-testing requirements as adopted by reference
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Final inspection only: Demolition Permit, Roofing Permit (Reroof), Sign Permit, Solar PV Permit
Re-inspection fees
Reinspection / After-Hours Inspection Fee · Trinidad Municipal Code Chapter 5, Section 5-1(2)(b), IBC § 109.2 'Other Inspections and Fees'; Show full citationHide
Reinspection / After-Hours Inspection Fee · Trinidad Municipal Code Chapter 5, Section 5-1(2)(b), IBC § 109.2 'Other Inspections and Fees'; $50.00 per hour appears as two rows, 'Reinspection fees' and 'Inspections outside of normal business hours', the two-hour minimum attaching only to the latterReinspection / After-Hours Inspection Fee · Trinidad Municipal Code Chapter 5, Section 5-1(2)(b), IBC § 109.2 'Other Inspections and Fees', rows 'Reinspection fees' and 'Inspections outside of normal… Show full citationHide
Reinspection / After-Hours Inspection Fee · Trinidad Municipal Code Chapter 5, Section 5-1(2)(b), IBC § 109.2 'Other Inspections and Fees', rows 'Reinspection fees' and 'Inspections outside of normal business hours' (two-hour minimum on the latter only); Chapter 5, Section 5-3 is Reserved, so no plumbing-specific inspection fee is publishedReinspection / After-Hours Inspection Fee · Trinidad Municipal Code Chapter 5, Section 5-1(2)(b), IBC § 109.2 'Other Inspections and Fees', rows 'Reinspection fees' and 'Inspections outside of normal… Show full citationHide
Reinspection / After-Hours Inspection Fee · Trinidad Municipal Code Chapter 5, Section 5-1(2)(b), IBC § 109.2 'Other Inspections and Fees', rows 'Reinspection fees' and 'Inspections outside of normal business hours' (two-hour minimum on the latter only); the mechanical schedule at Section 5-4(2)(b) (IMC § 108.2) publishes no inspection-fee rowSources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Applications & forms
Online permit portal
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Trinidad building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Trinidad building permits
Get alerts for Trinidad
We'll email you when Trinidad's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.