Skip to main content
PermitBase

Solar PV Permit in Trinidad, Colorado

Required for installation of rooftop or ground-mount solar photovoltaic systems in Trinidad. No standalone solar-specific fee line item is published; the structural/mounting permit is billed under the City's general valuation-based Building Permit Fee Schedule, subject to Colorado's statewide cap on active-solar-energy-system permit fees (C.R.S. § 24-48.5-113, enacted by HB21-1284): $500 maximum for residential, $1,000 maximum for nonresidential systems under 2 MW DC. Trinidad's IECC amendments require new construction to meet the Colorado Model Electric Ready and Solar Ready Code (CMERSRC), which governs solar-readiness for NEW buildings but does not itself create a separate retrofit solar permit or fee.

Verified 2026-07-20 · Source

When you need this permit

  • Building Permit Application required for the physical solar installation, submitted via the City's iWorQ portal
  • Fee is calculated from the same valuation-based Building Permit Fee Schedule used for general construction (no distinct 'solar' line item was found in the published fee schedule PDF)
  • Total permit fees may not exceed the statewide cap under C.R.S. § 24-48.5-113: $500 for residential active solar energy systems, $1,000 for nonresidential systems under 2 MW DC output — the City must charge the lesser of its actual/calculated fee or this cap
  • The issuing authority for the electrical interconnection portion could not be conclusively confirmed for Trinidad (see this database's electrical-permit entry): City sources are consistent with, but do not conclusively state, State of Colorado Electrical Board (DORA) jurisdiction over the code-compliance wiring permit, separate from the City's own utility hookup 'Electric Service Permit Application'
  • DORA has selected SolarAPP+ to deliver streamlined electrical plan review for solar installers at over 200 Colorado jurisdictions statewide (per DORA/SolarAPP+ Oct. 2025 announcement) — Trinidad's specific enrollment status was not found on the SolarAPP+ Colorado jurisdictions page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, general schedule)City of Trinidad Building Permit Fee Schedule (PDF); no solar-specific line item published
Per the City's Building Permit Fee Schedule valuation table (e.g. $24.00 minimum for $1-$500 valuation, scaling up from there)
Statewide fee cap on active solar energy systemsC.R.S. § 24-48.5-113 (HB21-1284) — caps the AGGREGATE of all fees the City may charge to install an active solar energy system
$500 residential / $1,000 nonresidential (under 2 MW DC), whichever is less than the City's calculated valuation-based fee

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Trinidad?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection (mounting/roof penetrations)

    Racking and roof-penetration compliance verified by the City Building Division

See the full Trinidad inspection guide — scheduling & re-inspection fees →

Tips

  • Colorado's statewide fee cap (C.R.S. § 24-48.5-113) means Trinidad cannot charge more than $500 total for a residential solar permit (or $1,000 for nonresidential systems under 2 MW DC) even if the general valuation-based Building Permit Fee Schedule would otherwise compute a higher number — ask the Building Division to confirm the capped fee at submittal.
  • Confirm which agency handles the electrical interconnection permit before scheduling work: Trinidad's own sources are ambiguous between State of Colorado Electrical Board (DORA) jurisdiction and a City-issued permit, consistent with the general ambiguity documented in this database's electrical-permit entry for Trinidad.

Frequently asked questions

Trinidad requires a solar pv permit for: Building Permit Application required for the physical solar installation, submitted via the City's iWorQ portal; Fee is calculated from the same valuation-based Building Permit Fee Schedule used for general construction (no distinct 'solar' line item was found in the published fee schedule PDF); Total permit fees may not exceed the statewide cap under C.R.S. § 24-48.5-113: $500 for residential active solar energy systems, $1,000 for nonresidential systems under 2 MW DC output — the City must charge the lesser of its actual/calculated fee or this cap; The issuing authority for the electrical interconnection portion could not be conclusively confirmed for Trinidad (see this database's electrical-permit entry): City sources are consistent with, but do not conclusively state, State of Colorado Electrical Board (DORA) jurisdiction over the code-compliance wiring permit, separate from the City's own utility hookup 'Electric Service Permit Application'; DORA has selected SolarAPP+ to deliver streamlined electrical plan review for solar installers at over 200 Colorado jurisdictions statewide (per DORA/SolarAPP+ Oct. 2025 announcement) — Trinidad's specific enrollment status was not found on the SolarAPP+ Colorado jurisdictions page. If your project isn't listed, confirm with City of Trinidad Development Services Department, Building Division at (719) 846-9843 ext. 136 or ext. 128 before starting work.

In Trinidad, the published Building Permit Fee (valuation-based, general schedule) is: Per the City's Building Permit Fee Schedule valuation table (e.g. $24.00 minimum for $1-$500 valuation, scaling up from there). Additional published fees: Statewide fee cap on active solar energy systems — $500 residential / $1,000 nonresidential (under 2 MW DC), whichever is less than the City's calculated valuation-based fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Trinidad does not publish a plan-review timeline for this permit. Contact City of Trinidad Development Services Department, Building Division at (719) 846-9843 ext. 136 or ext. 128 for current turnaround.

You'll need: Building Permit Application (iWorQ portal). Depending on your project, Trinidad may also ask for: City of Trinidad Electric Service Permit Application (utility hookup form). See the required-documents checklist on this page for details on each.

Trinidad requires 1 inspection(s) for a solar pv permit, in order: Final Inspection (mounting/roof penetrations). Schedule each through City of Trinidad Development Services Department, Building Division ((719) 846-9843 ext. 136 or ext. 128).

Apply through City of Trinidad Development Services Department, Building Division at 135 N. Animas Street (PO Box 880), Trinidad, CO 81082. Phone: (719) 846-9843 ext. 136 or ext. 128, email: Not published on the Building Inspections, Contractor Licenses & Permits page as of this review; contact via main office line. Office hours: Monday-Friday, 8:00 AM - 5:00 PM (City of Trinidad normal business hours); Development Services Administrator Tara Booth; fax (719) 846-4140. Official information: https://www.trinidad.co.gov/services/community_development/building_inspections___permits.php.

Trinidad, Colorado has adopted: 2024 International Building Code (IBC), including Appendix C (Group U Agricultural Buildings) and Appendix J (Grading) — Trinidad Municipal Code Chapter 5, Section 5-1 (Ord. 4052, Article 1, repealed and reenacted eff. 6-26-26); 2024 International Residential Code (IRC), including Appendix Chapters BE (Radon) and NF (Alternative Building Thermal Envelope Insulation R-Value Options) — Municipal Code Chapter 5, Section 5-2; 2024 International Mechanical Code (IMC), including Appendix A (Chimney Connector Pass-Throughs) — Municipal Code Chapter 5, Section 5-4; 2024 International Fuel Gas Code (IFGC) — Municipal Code Chapter 5, Section 5-5; 2024 International Energy Conservation Code (IECC), amended to require compliance with the Colorado Model Electric Ready and Solar Ready Code (CMERSRC) for both residential (R401.2) and commercial (C401.2) buildings, EXCEPT Chapter 3 Electric Ready Provisions, which are deferred to a City-utility implementation plan beginning July 1, 2027 — Municipal Code Chapter 5, Section 5-6; 2025 International Existing Building Code (IEBC) — Municipal Code Chapter 5, Section 5-7 (the ordinance text names the 2025 edition in its adoption sentence but refers to '2024 Edition' in the following administrative sentences; both readings point to the same currently-adopted IEBC cited in the live ordinance, flagged here as a genuine internal inconsistency in the ordinance's own text rather than resolved by assumption); 2024 International Property Maintenance Code (IPMC), including Appendix Chapter A (Boarding Standard) — Municipal Code Chapter 5, Section 5-8; Section 5-3 (where the International Plumbing Code would sit, per Chapter 15 Section 15-1's own cross-reference 'See Chapter 5, Section 5-3') and Section 5-9 (where a National Electrical Code adoption would typically sit) are both listed as 'Reserved' in the current live Chapter 5 ordinance text as of this review — no standalone IPC or NEC adoption section could be located in the current municipal code; this is a genuine gap, not an oversight in this extraction (see localAmendments); Table R301.2 local design criteria (IRC amendment): Ground Snow Load not less than 30 psf; Wind Design Speed not less than 115 mph; Seismic Design Category B; Frost line depth 32 inches; Ice Barrier Underlayment Required: YES; Weathering: Severe; Termite: Slight to moderate; Flood Hazard FIRM 080107 0001 B, adopted 4/3/84. Local amendments apply — see the Trinidad overview page for the full list.

Yes. Colorado's statewide C.R.S. § 24-48.5-113 (HB21-1284) caps the aggregate permit fees any Colorado political subdivision — including Trinidad — may charge to install an active solar energy system at $500 for residential systems and $1,000 for nonresidential systems under 2 MW DC output, whichever is less than the actual cost of issuing the permit.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Trinidad building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.