Solar Photovoltaic (PV) Permit in Ault, Colorado
Ault has no separate solar/photovoltaic permit type; rooftop or ground-mounted PV is permitted as a combined Building Permit (structural/racking, 1997 UBC valuation-based table, Exhibit B) and Electrical Permit (State of Colorado Electrical Board fee schedule plus the Town's 15% local surcharge), administered locally by SAFEbuilt Colorado under contract to the Town. As in every Colorado jurisdiction, the combined total of all governmental fees for the installation is capped by state law at $500 for a residential system and $1,000 for a commercial system (C.R.S. § 24-48.5-113, enacted by HB21-1284).
Verified 2026-07-20 · Source
When you need this permit
- Building Permit required for the structural/racking portion, reviewed under the Town's adopted code (2023 NEC referenced for electrical work per the SAFEbuilt Residential Application Check List)
- Electrical Permit required for PV wiring/interconnection, billed at the current State of Colorado Electrical Board fee schedule amount plus the Town's 15% local surcharge (the statutory maximum under C.R.S. § 12-23-117(3))
- Electrical contractor must hold a current Colorado State Electrical Board (DORA) license
- By statute (C.R.S. § 24-48.5-113 / HB21-1284), the aggregate of all permit fees and charges imposed by any Colorado governmental body for an active solar energy system installation is capped at $500 residential / $1,000 commercial
- Submit via SAFEbuilt Colorado, the Town's contracted building department
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Racking, roof penetrations, devices, and interconnection verified
See the full Ault inspection guide — scheduling & re-inspection fees →
Tips
- Ault has no solar-specific fee line — the structural portion follows the Town's 1997 UBC valuation-based Building Permit table (Exhibit B) and the electrical portion follows the State Electrical Board fee schedule plus the Town's 15% surcharge, but the combined total for any Colorado solar installation cannot exceed the statewide $500 residential / $1,000 commercial cap under C.R.S. § 24-48.5-113.
- SAFEbuilt Colorado administers permitting and inspections for the Town under contract — apply through SAFEbuilt, not directly through Town Hall.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ault building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Ault
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Colorado →