Solar Photovoltaic (PV) Permit in Ault, Colorado

Ault has no separate solar/photovoltaic permit type; rooftop or ground-mounted PV is permitted as a combined Building Permit (structural/racking, 1997 UBC valuation-based table, Exhibit B) and Electrical Permit (State of Colorado Electrical Board fee schedule plus the Town's 15% local surcharge), administered locally by SAFEbuilt Colorado under contract to the Town. As in every Colorado jurisdiction, the combined total of all governmental fees for the installation is capped by state law at $500 for a residential system and $1,000 for a commercial system (C.R.S. § 24-48.5-113, enacted by HB21-1284).

Verified 2026-07-20 · Source

When you need this permit

  • Building Permit required for the structural/racking portion, reviewed under the Town's adopted code (2023 NEC referenced for electrical work per the SAFEbuilt Residential Application Check List)
  • Electrical Permit required for PV wiring/interconnection, billed at the current State of Colorado Electrical Board fee schedule amount plus the Town's 15% local surcharge (the statutory maximum under C.R.S. § 12-23-117(3))
  • Electrical contractor must hold a current Colorado State Electrical Board (DORA) license
  • By statute (C.R.S. § 24-48.5-113 / HB21-1284), the aggregate of all permit fees and charges imposed by any Colorado governmental body for an active solar energy system installation is capped at $500 residential / $1,000 commercial
  • Submit via SAFEbuilt Colorado, the Town's contracted building department

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Statewide aggregate solar permit fee cap — ResidentialC.R.S. § 24-48.5-113, enacted by HB21-1284 (2021), extended through Dec. 31, 2029
$500 (combined Town building + electrical fees)
Statewide aggregate solar permit fee cap — CommercialC.R.S. § 24-48.5-113, enacted by HB21-1284 (2021)
$1,000 (combined Town building + electrical fees)
Building Permit Fee (structural portion) — valuation $1.00 to $500.00Exhibit B — Fee Schedule for Services, Town of Ault (last modified 5/19/24), 1997 UBC Table 1-A; no distinct solar/PV line item — subject to the statewide cap above
$23.00
Electrical Permit FeeExhibit B — Fee Schedule for Services, Town of Ault; consistent with the maximum 15% surcharge authorized under C.R.S. § 12-23-117(3)
Current State of Colorado Electrical Board fee schedule amount, plus 15% local surcharge

Review timeline

Plan review
Not published — contact the department

How long did your Solar Photovoltaic (PV) Permit permit actually take in Ault?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Racking, roof penetrations, devices, and interconnection verified

See the full Ault inspection guide — scheduling & re-inspection fees →

Tips

  • Ault has no solar-specific fee line — the structural portion follows the Town's 1997 UBC valuation-based Building Permit table (Exhibit B) and the electrical portion follows the State Electrical Board fee schedule plus the Town's 15% surcharge, but the combined total for any Colorado solar installation cannot exceed the statewide $500 residential / $1,000 commercial cap under C.R.S. § 24-48.5-113.
  • SAFEbuilt Colorado administers permitting and inspections for the Town under contract — apply through SAFEbuilt, not directly through Town Hall.

Frequently asked questions

Ault requires a solar photovoltaic (pv) permit for: Building Permit required for the structural/racking portion, reviewed under the Town's adopted code (2023 NEC referenced for electrical work per the SAFEbuilt Residential Application Check List); Electrical Permit required for PV wiring/interconnection, billed at the current State of Colorado Electrical Board fee schedule amount plus the Town's 15% local surcharge (the statutory maximum under C.R.S. § 12-23-117(3)); Electrical contractor must hold a current Colorado State Electrical Board (DORA) license; By statute (C.R.S. § 24-48.5-113 / HB21-1284), the aggregate of all permit fees and charges imposed by any Colorado governmental body for an active solar energy system installation is capped at $500 residential / $1,000 commercial; Submit via SAFEbuilt Colorado, the Town's contracted building department. If your project isn't listed, confirm with Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) at 970-834-2844 before starting work.

The combined Town building permit and electrical permit fees cannot exceed $500 for a residential system, per the statewide cap in C.R.S. § 24-48.5-113 (HB21-1284). Ault's own building fee follows the 1997 UBC valuation table (Exhibit B) and the electrical fee follows the State Electrical Board schedule plus a 15% Town surcharge, but the combined total is capped at $500.

Ault does not publish a plan-review timeline for this permit. Contact Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) at 970-834-2844 for current turnaround.

You'll need: Building Permit Application; Electrical Permit Application. See the required-documents checklist on this page for details on each.

Ault requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) (970-834-2844).

Apply through Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) at 201 1st Street, PO Box 1098, Ault, CO 80610. Phone: 970-834-2844, email: info@aultcolorado.gov. Office hours: Town Hall does not publish specific daily office hours on its Contact Us or Building Permits pages as of this review; the Town's public-works page separately states Public Works operates 7:00 a.m.-4:00 p.m. Monday-Friday (except holidays), and the site-wide holiday-closure banner implies a standard 9:00 a.m. reopening time, but neither is confirmed as the Building Department's specific window. Call 970-834-2844 to confirm hours before visiting in person.. Official information: https://www.aultcolorado.gov/buildingpermits.

Ault, Colorado has adopted: 2024 International Residential Code (IRC) — per the '2026 SAFEbuilt Residential Application Check List' (Town of Ault Building Permits page, Helpful/Residential resource): 'All submittal information must comply with the 2024 I-codes and the 2023 NEC.'; 2024 International Building Code (IBC) — per the SAFEbuilt 'New Commercial Plan Submittal Procedure' and 'Commercial Tenant Finish/Remodel Plan Submittal Procedure' documents on the Town of Ault Building Permits page, both headed '2024 INTERNATIONAL CODES.'; 2024 International Energy Conservation Code (IECC) — required compliance documentation (ResCheck or energy rating report) explicitly named in the SAFEbuilt Residential Application Check List; commercial submittal procedures likewise require 'Documentation showing compliance with the 2024 IECC.'; 2023 National Electrical Code (NEC) — explicitly named in the SAFEbuilt Residential Application Check List ('...and the 2023 NEC').; 2024 International Mechanical Code (IMC) / International Plumbing Code (IPC) — inferred from the SAFEbuilt submittal procedures' consistent requirement of 'Mechanical/Plumbing Plans' stamped by a Colorado-licensed engineer, cross-referenced against the same '2024 INTERNATIONAL CODES' heading used for the IBC/IECC citation on the same documents; not independently named by edition number in the source text, so carried at 'partial' confidence for the specific IMC/IPC edition number. 2026-07-23 re-chase: the Town's own codified Municipal Code (Title 15 Ch.04, Sections 030/060), recovered via Wayback Machine archive of the now-defunct myaultgov.org portal (Sec. 030 Mechanical captured 2022-12-05: 'International Mechanical Code, 2018 Edition'; Sec. 060 Plumbing captured 2022-12-05: 'International Plumbing Code, 2012 Edition'), shows both trade codes were LAST codified at pre-2024 editions — older than, and in unresolved tension with, SAFEbuilt's current 2024-I-code submittal language; no live, currently-hosted Municipal Code exists to confirm whether these sections have since been amended to 2024 editions, so the specific currently-governing IMC/IPC edition numbers remain genuinely unconfirmed and are NOT asserted as '2024' anywhere in this file.; 1997 Uniform Building Code (UBC), Table 1-A — still the operative VALUATION-BASED FEE TABLE per the Town's 'Building Permit Fee Schedule' (Exhibit B — Fee Schedule for Services, a SAFEbuilt consultant-services fee exhibit posted on the Town's Building Permits resource list, last modified 5/19/24). This is a fee-calculation table, not a life-safety code edition, and is retained purely because it is the Town's actual current, published fee mechanism — it does not indicate the Town is still enforcing 1997 UBC life-safety provisions, which are superseded by the 2024 I-codes cited above.; No separate Ault-specific building-code-adoption ordinance was found published online: the Town of Ault Municipal Code page (aultcolorado.gov/MuniCode) states 'A Copy of the Ault Municipal Code is Available Upon Request' and is not hosted on Municode/eCode360 or any other public code-hosting platform; the Town's online Document Archive 'Ordinances' folder contains only a 'Non-Certified Copy of 2024 Model Traffic Code' (unrelated to building codes). The SAFEbuilt submittal-requirement documents (which explicitly compel 2024 I-code / 2023 NEC compliance and are hosted directly on the Town's own Building Permits page) are therefore treated as the governing, currently-operative code-adoption source for this file, consistent with SAFEbuilt Colorado being Ault's contracted building official/plan-review/inspection provider (per Exhibit B of the Town-SAFEbuilt consultant services agreement).. Local amendments apply — see the Ault overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ault building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.