Ault building inspections
Inspection sequence, scheduling, and re-inspection fees for building permits in Ault, Colorado.
Reviewed 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 201 1st Street, PO Box 1098, Ault, CO 80610
- Phone
- 970-834-2844
- Office hours
- Town Hall does not publish specific daily office hours on its Contact Us or Building Permits pages as of this review; the Town's public-works page separately states Public Works operates 7:00 a.m.-4:00 p.m. Monday-Friday (except holidays), and the site-wide holiday-closure banner implies a standard 9:00 a.m. reopening time, but neither is confirmed as the Building Department's specific window. Call 970-834-2844 to confirm hours before visiting in person.
- Website
- Official site
Published scheduling rules
- Ault's plan review, building official, and inspection services are performed by SAFEbuilt Colorado under contract to the Town, not by Town staff directly — expect correspondence and inspection scheduling to come from SAFEbuilt. (Residential Building Permit (New Construction))
- The SAFEbuilt Re-roofing guide's inspection-scheduling email ('windsor@safebuilt.com') and its impact-resistant-shingle exception ('THE TOWN OF TIMNATH') are boilerplate from a different SAFEbuilt Colorado client town and are NOT represented as Ault-specific — confirm Ault's actual inspection scheduling method directly with SAFEbuilt/Town Hall (970-834-2844). (Roofing Permit (Re-Roof))
- The Patio Covers/Carports Guide's inspection-scheduling email ('windsor@safebuilt.com') is the same cross-town SAFEbuilt boilerplate already flagged elsewhere in this file (e.g., the Re-Roofing guide) — not Ault-specific; confirm Ault's actual inspection scheduling method with SAFEbuilt/Town Hall (970-834-2844). (Deck / Covered Patio Permit)
- Ault contracts its building official, plan review, and inspection functions to SAFEbuilt Colorado — expect to interact with SAFEbuilt (not Town staff directly) for plan review correspondence and inspection scheduling, though applications and fee payment are administered through the Town. (General)
Inspection sequence
Applies to: Residential Addition / Remodel Permit
- 1
Foundation / Foundation Wall
After trenches are excavated, reinforcement steel is in place, forms erected, and PRIOR to placing concrete (additions with new footings only)
- 2
Underground Plumbing
Before covering any piping or wiring and prior to placing concrete
- 3
Rough Trade (Electrical / Plumbing / Mechanical)
Rough installation complete prior to covering or commissioning; may be combined with the Rough Frame inspection
- 4
Rough Frame
After roof, all framing, fire stopping, sheathing, draft stopping, bracing, and fasteners are in place; connection to existing structure verified
- 5
Insulation
After insulation is in place, PRIOR to covering walls
- 6
Final Inspection
After the addition is completed
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes; approved plan set must remain on the job site through final inspection
Applies to: Deck / Covered Patio Permit
- 1
Footing/Foundation
After trenches/holes are dug, reinforcement steel is in place/forms erected, and PRIOR to placing concrete
- 2
Framing
Rim board/ledger attachment, joists, beams, and hangers verified prior to finished decking/ceiling being applied (include a rough electric inspection at the same time if wiring a patio cover)
- 3
Final Inspection
After the deck or patio cover/carport is completed, including any final electrical
Applies to: Accessory Structure Permit (incl. Accessory Dwelling / Structures)
- 1
Foundation (if applicable)
- 2
Final Inspection
Applies to: Commercial Tenant Finish / Remodel Permit
- 1
Rough Electrical / Plumbing / Mechanical
- 2
Final Inspection
Includes Health Department sign-off for restaurants/commercial kitchens before Certificate of Occupancy
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system verified
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical
Wiring and circuit installed before concealment
- 2
Final Inspection
Charger installed, circuit verified, unit energized
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Racking, roof penetrations, devices, and interconnection verified
Final inspection only: Demolition Permit, Furnace / Water Heater Replacement Permit, Roofing Permit (Re-Roof)
Re-inspection fees
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ault building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.