Roofing Permit (Re-Roof) in Ault, Colorado

Required for re-roofing work in Ault. Billed as a flat 'Single Stop Project' fee rather than the valuation-based table. Governed by 2024 IRC Section R908 re-roofing provisions per SAFEbuilt's Building Guide for Homeowners.

Verified 2026-07-06 · Source

When you need this permit

  • No more than two (2) layers of roofing are allowed upon completion of installation (2024 IRC R908.3)
  • Roof replacement (tear-off to the deck) required where the existing roof is water-soaked/deteriorated, is wood shake/slate/clay/cement/asbestos-cement tile, or already has two or more layers
  • A Final Roof inspection is required; mid-roof inspections are NOT required on residential re-roof projects per SAFEbuilt's guide, though the Building Department may require one depending on material/scope
  • Homeowner self-installation is permitted

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Roof (re-shingle) — Single Stop ProjectExhibit B — Fee Schedule for Services, Single Stop Projects Fee Schedule
$60.00

Review timeline

Plan review
Not published — contact the department

How long did your Roofing Permit (Re-Roof) permit actually take in Ault?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Roof Inspection

    Completed roof — material, underlayment, and flashing/valley compliance verified

See the full Ault inspection guide — scheduling & re-inspection fees →

Tips

  • Ault bills re-roofing as a flat $60.00 'Single Stop Project' fee, not the valuation-based Building Permit Fee table.
  • A maximum of two roofing layers is allowed after installation — a full tear-off is required if the existing roof already has two or more layers, per 2024 IRC R908.3.
  • The SAFEbuilt Re-roofing guide's inspection-scheduling email ('windsor@safebuilt.com') and its impact-resistant-shingle exception ('THE TOWN OF TIMNATH') are boilerplate from a different SAFEbuilt Colorado client town and are NOT represented as Ault-specific — confirm Ault's actual inspection scheduling method directly with SAFEbuilt/Town Hall (970-834-2844).

Frequently asked questions

Ault requires a roofing permit (re-roof) for: No more than two (2) layers of roofing are allowed upon completion of installation (2024 IRC R908.3); Roof replacement (tear-off to the deck) required where the existing roof is water-soaked/deteriorated, is wood shake/slate/clay/cement/asbestos-cement tile, or already has two or more layers; A Final Roof inspection is required; mid-roof inspections are NOT required on residential re-roof projects per SAFEbuilt's guide, though the Building Department may require one depending on material/scope; Homeowner self-installation is permitted. If your project isn't listed, confirm with Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) at 970-834-2844 before starting work.

In Ault, the published Roof (re-shingle) — Single Stop Project is: $60.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Ault does not publish a plan-review timeline for this permit. Contact Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) at 970-834-2844 for current turnaround.

You'll need: Building Permit Application (re-roof scope). See the required-documents checklist on this page for details on each.

Ault requires 1 inspection(s) for a roofing permit (re-roof), in order: Final Roof Inspection. Schedule each through Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) (970-834-2844).

Apply through Town of Ault (building official, plan review, and inspection services contracted to SAFEbuilt Colorado) at 201 1st Street, PO Box 1098, Ault, CO 80610. Phone: 970-834-2844, email: info@aultcolorado.gov. Office hours: Town Hall does not publish specific daily office hours on its Contact Us or Building Permits pages as of this review; the Town's public-works page separately states Public Works operates 7:00 a.m.-4:00 p.m. Monday-Friday (except holidays), and the site-wide holiday-closure banner implies a standard 9:00 a.m. reopening time, but neither is confirmed as the Building Department's specific window. Call 970-834-2844 to confirm hours before visiting in person.. Official information: https://www.aultcolorado.gov/buildingpermits.

Ault, Colorado has adopted: 2024 International Residential Code (IRC) — per the '2026 SAFEbuilt Residential Application Check List' (Town of Ault Building Permits page, Helpful/Residential resource): 'All submittal information must comply with the 2024 I-codes and the 2023 NEC.'; 2024 International Building Code (IBC) — per the SAFEbuilt 'New Commercial Plan Submittal Procedure' and 'Commercial Tenant Finish/Remodel Plan Submittal Procedure' documents on the Town of Ault Building Permits page, both headed '2024 INTERNATIONAL CODES.'; 2024 International Energy Conservation Code (IECC) — required compliance documentation (ResCheck or energy rating report) explicitly named in the SAFEbuilt Residential Application Check List; commercial submittal procedures likewise require 'Documentation showing compliance with the 2024 IECC.'; 2023 National Electrical Code (NEC) — explicitly named in the SAFEbuilt Residential Application Check List ('...and the 2023 NEC').; 2024 International Mechanical Code (IMC) / International Plumbing Code (IPC) — inferred from the SAFEbuilt submittal procedures' consistent requirement of 'Mechanical/Plumbing Plans' stamped by a Colorado-licensed engineer, cross-referenced against the same '2024 INTERNATIONAL CODES' heading used for the IBC/IECC citation on the same documents; not independently named by edition number in the source text, so carried at 'partial' confidence for the specific IMC/IPC edition number. 2026-07-23 re-chase: the Town's own codified Municipal Code (Title 15 Ch.04, Sections 030/060), recovered via Wayback Machine archive of the now-defunct myaultgov.org portal (Sec. 030 Mechanical captured 2022-12-05: 'International Mechanical Code, 2018 Edition'; Sec. 060 Plumbing captured 2022-12-05: 'International Plumbing Code, 2012 Edition'), shows both trade codes were LAST codified at pre-2024 editions — older than, and in unresolved tension with, SAFEbuilt's current 2024-I-code submittal language; no live, currently-hosted Municipal Code exists to confirm whether these sections have since been amended to 2024 editions, so the specific currently-governing IMC/IPC edition numbers remain genuinely unconfirmed and are NOT asserted as '2024' anywhere in this file.; 1997 Uniform Building Code (UBC), Table 1-A — still the operative VALUATION-BASED FEE TABLE per the Town's 'Building Permit Fee Schedule' (Exhibit B — Fee Schedule for Services, a SAFEbuilt consultant-services fee exhibit posted on the Town's Building Permits resource list, last modified 5/19/24). This is a fee-calculation table, not a life-safety code edition, and is retained purely because it is the Town's actual current, published fee mechanism — it does not indicate the Town is still enforcing 1997 UBC life-safety provisions, which are superseded by the 2024 I-codes cited above.; No separate Ault-specific building-code-adoption ordinance was found published online: the Town of Ault Municipal Code page (aultcolorado.gov/MuniCode) states 'A Copy of the Ault Municipal Code is Available Upon Request' and is not hosted on Municode/eCode360 or any other public code-hosting platform; the Town's online Document Archive 'Ordinances' folder contains only a 'Non-Certified Copy of 2024 Model Traffic Code' (unrelated to building codes). The SAFEbuilt submittal-requirement documents (which explicitly compel 2024 I-code / 2023 NEC compliance and are hosted directly on the Town's own Building Permits page) are therefore treated as the governing, currently-operative code-adoption source for this file, consistent with SAFEbuilt Colorado being Ault's contracted building official/plan-review/inspection provider (per Exhibit B of the Town-SAFEbuilt consultant services agreement).. Local amendments apply — see the Ault overview page for the full list.

No more than two (2) layers are allowed upon completion of installation, per the 2024 IRC (Section R908.3) as applied in SAFEbuilt's Building Guide for Homeowners — Residential Re-roofing.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ault building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.